APPENDICES

Appendix A            Site Map and Works Area

Appendix B            Organization Chart

Appendix C            Works Programme

Appendix D            Implementation Status of Environmental Mitigation Measures

Appendix E            Monitoring Locations

Appendix F             Monitoring Results

Appendix G            Interim Notifications of Environmental Quality Limits Exceedances

Appendix H            Complaint Log

 

TABLES

Table 3-1      Frequency of Air Quality, Noise and Water Quality Monitoring

Table 3-2      Air Quality Monitoring Locations

Table 3-3      Noise Monitoring Locations

Table 3-4      Water Quality Monitoring Locations

Table 3-5      Action & Limit Levels for Air Quality

Table 3-6      Action & Limit Levels for Air Borne Noise

Table 3-7      Action & Limit Levels for Water Quality

Table 3-8      Summary of Air Quality Monitoring Results

Table 3-9      Summary of Impact Air Borne Noise Monitoring Results

Table 3-10    Summary of Impact Water Quality Monitoring Results

Table 3-11    Summary of Impact Marine Water Quality Monitoring Results              

Table 4-1      Waste Generated from January to March 2012

Table 4-2      Summary of Project- related Exceedances

Table 5-1      Cumulative Statistics of Environmental Complaints

Table 6-1      Cumulative Statistics of Notification of Summons and Successful Prosecutions

Table 7-1      Total Wastes Generated from January to March 2012

 

 


Executive Summary

1      This quarterly EM&A summary report under the Main Contract for the Design and Construction of Tsuen Wan Drainage Tunnel (hereafter referred to as the “Project”) to Maeda-CREC-SELI Joint Venture (MCSJV), which summarises the findings of environmental impact monitoring works during the period from January to March 2012.

2      Air borne noise monitoring was performed at five monitoring stations (NSR1, NSR3, NSR6, NSR8 and NSR9).  Air quality monitoring was carried out at four monitoring stations (ASR1, ASR3, ASR8 and ASR9).  Water quality monitoring was carried out at four monitoring stations (Intake I-1, Intake I-2, Intake I-3 and Outfall O-1). Noise level was measured in terms of Leq, L10 and L90 (30min).  Air quality was measured in terms of 1-hour Total Suspended Particulates (TSP). Water quality was measured in terms of Temperature, pH, Dissolved Oxygen (DO), Turbidity (Tby) and Suspended Solids (SS).

3      Details of all monitoring stations are summarized in the table below.

Type of Monitoring

Monitoring Station ID

Name of Premises

Status of Monitoring Works during the Reporting Period

Air Quality Monitoring

ASR1

Sik Sik Yuen Ho Fung College

Ongoing

ASR3

Hong Hoi Chee Hong Temple

Ongoing

ASR8

Beach Tower (Long Beach Gardens)

Ongoing

ASR9

Greenview Terrace (Block 1)

Ongoing

Air Borne Noise Monitoring

NSR1

Sik Sik Yuen Ho Fung College

Ongoing

NSR3

Hong Hoi Chee Hong Temple

Ongoing

NSR6

Squatters

Ongoing

NSR8

Beach Tower (Long Beach Gardens)

Ongoing

NSR9

Greenview Terrace (Block 1)

Ongoing

Water Quality Monitoring

I-1

Intake I-1

Ongoing

I-2

Intake I-2

Ongoing

I-3

Intake I-3

Ongoing

O-1

Outfall O-1

Ongoing

 

4      The major construction activities undertaken by the Contractor during the period from January to March 2012 include site cleaning and tidying at Outfall, I-1, I-2 and I-3; tunnel boring machine (TBM) drilling of the tunnel and mucking out of tunnel spoil at Outfall; dismantling and removal of TBM services at Outfall and I-1; asphalt paving for the Castle Peak Road fast lane at Outfall; construction of box culvert and L-shaped retaining wall at Outfall; construction of spiral ramp structure at Outfall; removal of muck hopper at Outfall; construction of the open channel, seawall copping and baffle wall at Portion E; installation of precast sea wall blocks and panels at Portion E; placing leveling stone and trimming formation for precast slab at Portion E; reinstatement of rock armour including placing of rock armour on step blocks at Portion E; trimming formation for precast slab at Portion E; blasting and excavation at man access shaft, deaeration chamber and main adit tunnel at I-2; construction for reinforced cement concrete (RCC) frame for stop log and columns for trash grill at I-1; construction of L-shaped retaining wall at I-2; construction of bund wall at I-2; construction of 300 U-channel and catchpit at Portion G at I-2; construction of skin wall at Portion G at I-2; construction of boulder traps at I-2; drainage works (1500 mm diameter pipe and associated works) at Portion G at I-2; excavation for construction of L-shaped wall at I-2; grouting dowel bars and shotcreting at upper man access adit at I-2; construction of man access adit at I-3; construction of man access shaft at I-3; construction of approach channel at I-3; construction of deaeration chamber at I-3; construction of preventive measure for temporary drainage management plan (TDMP) at I-3; construction of road drainage (U-channel and 900 mm diameter pipe) at proposed access road at I-3; drilling hole and excavation for main adit tunnel at I-3; and lowering down the permanent access road at PB wall at I-3.

5      Underground mining and probe drilling were undertaken during the restricted hours in the reporting period.

6      As confirmed by the Contractor, no marine mud dredging works for basin scheme at Portion E was conducted in the reporting period.

7      No project related exceedance of air quality and water quality monitoring was recorded. No air borne noise limit level exceedance was recorded during the reporting period, but one construction noise complaint at I-3 was received on 8 February 2012 and regarded as one action level exceedance. The table below summarizes the exceedances of air quality, noise and water quality in the reporting period.

 Parameter

Action Level Exceedance

Limit Level Exceedance

Air

Nil

Nil

Air Borne Noise

One recorded on 8 Feb 2012 at I-3

Nil

DO

One record on 22 Feb 2012 at O-1(FT)

Twelve records on 3 Jan, 5 Jan, 10 Feb, 15 Feb, 22 Feb, 24 Feb, 27 Feb, 2 Mar, 5 Mar, 7 Mar and 16 Mar 2012 at O-1(ET)

 

Forty-nine records on 3 Jan , 5 Jan, 7 Jan , 18 Jan, 3 Feb, 6 Feb, 8 Feb, 13 Feb, 15 Feb, 17 Feb, 20 Feb, 22 Feb, 24 Feb, 27 Feb, 29 Feb, 2 Mar, 5 Mar, 9 Mar, 12 Mar, 14 Mar, 16 Mar, 23 Mar and 30 Mar 2012 at O-1(FT)

Forty-one records on 3 Jan, 5 Jan, 7 Jan, 28 Jan, 8 Feb, 13 Feb, 15 Feb, 17 Feb, 20 Feb, 22 Feb, 24 Feb, 27 Feb, 29 Feb, 2 Mar, 5 Mar, 9 Mar, 12 Mar, 14 Mar, 16 Mar, 23 Mar, 26 Mar and 30 Mar 2012 at O-1(ET)

Turbidity

Nil

Nil

SS

Two records on 7 Jan and 9 Mar 2012 at I-1

One record on 12 Mar 2012 at I-2

Six records on 7 Jan, 11 Jan ,16 Jan, 24 Feb , 2 Mar and 5 Mar 2012 at O-1(FT)

One record on 18 Jan 2012 at O-1(ET)

 

Three recorded on 20 Feb, 22 Feb and 19 Mar 2012 at I-1

Two records on 29 Feb and 5 Mar 2012 at I-2

One record on 6 Feb 2012 at I-3

Two records on 20 Jan and 22 Feb 2012 at O-1(FT)

Eight records on 11 Jan , 16 Jan , 30 Jan , 1 Feb, 6 Feb, 15 Feb, 2 Mar and 14 Mar 2012 at O-1(ET)

 

8      Waste figures during the reporting period are summarized in the table below.

Status of Waste Management

Quantity

Inert C&D Material Disposed of to Public Fill at Tuen Mun (m3)

3797.8

Inert C&D Material Reused in this Contract (m3)

532.5

Inert C&D Material Reused in other Contract* (m3)

6982.5

Metals Generated (kg)

229052.0

Paper / Cardboard Packaging (kg)

350.0

Plastics (kg)

20.0

Chemical Waste (kg)

411.0

General Waste Disposed of to NENT Landfill (m3)

196.5

* Other Contracts include CV/2009/14, DC/2007/08, DC/2007/09, HY/2007/09, HY/2007/10, HY/2008/09, XRL823AB and Tailor Recycle Aggregate

9      One environmental complaint was received on 8 February 2012 by SOR about daytime construction noise from the Intake I-3 construction site on 8 February 2012. The Contractor informed ET that one public complaint regarding daytime construction noise from the Intake I-3 construction site was received by SOR on 8 February. The ET conducted site inspections at Intake I-3 construction site on 9 and 23 February 2012 to review and audit the site setting, mitigation measures implemented on-site and the environmental performance of the Contractor. Noise monitoring at NSR 6 was increased to twice per week from 10 February 2012 to 29 February 2012 according to the Event/Action Plan and no exceedance of limit level was recorded. An investigation report was prepared and submitted on 5 March 2012. Since no further complaint was received, the complaint was considered closed.

10    No Notification of Summons was received since the commencement of the Project.


1                     Introduction

1.1.1                The Drainage Services Department (DSD) proposes to construct a tunnel of an internal diameter of 6.5 m and length 5.13 km, with the purpose to alleviate the flooding risk in Tsuen Wan and Kwai Chung.

1.1.2                This project is a Designated Project under Schedule 2 Part I Category Q, of the Environmental Impact Assessment Ordinance (EIAO) as part of the proposed Tsuen Wan Drainage Tunnel (TWDT) passes underneath the existing Tai Mo Shan Country Park.  An Environmental Impact Assessment (EIA) Study was undertaken to provide information on the nature and extent of environmental impacts arising from the construction and operation of the proposed designed project and related activities taking place concurrently.  From the EIA the recommendations for monitoring contained herein, are made.

1.1.3                The Maeda-CREC-SELI Joint Venture (MCSJV) was awarded by DSD with the Contract – Design and Construction of Tsuen Wan Drainage Tunnel.

1.1.4                Hyder was commissioned by the MCSJV as the ET to implement an EM&A program in accordance with the EM&A Manual.  The proposed tunnel section flows from the junction of Shing Mun Road and Wo Yi Hop Road and discharges to south of Yau Kom Tau underneath Castle Peak Road, as shown in Appendix A.

1.1.5                The construction works of the Project commenced in January 2008. This is the sixteenth quarterly EM&A report summarising the impact monitoring results and audit findings of the EM&A program during the reporting period between January and March 2012.

2                     Project Information

2.1               Project Organization and Management Structure

2.1.1                The organization chart and lines of communication with respect to the on-site environmental management are shown in Appendix B.

2.2               Construction Progress

2.2.1                It is anticipated that the overall project programme from the detail design to completion of all civil works shall take approximately 54 months.  The construction programme is presented in Appendix C.

2.2.2                The major construction activities undertaken in the reporting quarter are: 

·       Site cleaning and tidying at Outfall, I-1, I-2 and I-3;

·       Tunnel boring machine (TBM) drilling of the tunnel and mucking out of tunnel spoil at Outfall;

·       Dismantling and removal of TBM services at Outfall and I-1;

·       Asphalt paving for the Castle Peak Road fast lane at Outfall;

·       Construction of box culvert and L-shaped retaining wall at Outfall;

·       Construction of spiral ramp structure at Outfall;

·       Removal of muck hopper at Outfall;

·       Construction of the open channel, seawall copping and baffle wall at Portion E;

·       Installation of precast sea wall blocks and panels at Portion E;

·       Placing leveling stone and trimming formation for precast slab at Portion E;

·       Reinstatement of rock armour including placing of rock armour on step blocks at Portion E;

·       Trimming formation for precast slab at Portion E;

·       Blasting and excavation at man access shaft, deaeration chamber and main adit tunnel at I-2;

·       Construction for reinforced cement concrete (RCC) frame for stop log and columns for trash grill at I-1;

·       Construction of L-shaped retaining wall at I-2;

·       Construction of bund wall at I-2;

·       Construction of 300 U-channel and catchpit at Portion G at I-2;

·       Construction of skin wall at Portion G at I-2;

·       Construction of boulder traps at I-2;

·       Drainage works (1500 mm diameter pipe and associated works) at Portion G at I-2;

·       Excavation for construction of L-shaped wall at I-2;

·       Grouting dowel bars and shotcreting at upper man access adit at I-2;

·       Construction of man access adit at I-3;

·       Construction of man access shaft at I-3;

·       Construction of approach channel at I-3;

·       Construction of deaeration chamber at I-3;

·       Construction of preventive measure for temporary drainage management plan (TDMP) at I-3;

·       Construction of road drainage (U-channel and 900 mm diameter pipe) at proposed access road at I-3;

·       Drilling hole and excavation for main adit tunnel at I-3; and

·       Lowering down the permanent access road at PB wall at I-3.

2.3               Mitigation Measures

2.3.1                The environmental mitigation measures that were implemented and their statuses are given in Appendix D.

 

3                     EM&A Requirement

3.1               General

3.1.1                The EM&A requirements are stipulated in the EM&A Manual.  The principal purposes of the EM&A program are to assess the compliance with applicable environmental legislation and associated regulations, to ensure the implementation of mitigation measures specified in the EM&A Manual, and to identify any remedial works necessary for redressing any unacceptable or unanticipated environmental impacts.

3.2               EM&A on Air Quality, Noise and Water Quality

Monitoring Parameters

3.2.1                The air quality, noise and water quality monitoring frequencies and parameters are shown in Table 3-1.

Type of Monitoring

Monitoring Station ID

Parameter

Frequency

Air Quality Monitoring

ASR1; ASR3; ASR8 and ASR9

1-hour TSP (mg/m3)

Once every 6 days

Air Borne Noise Monitoring

NSR1; NSR3; NSR6; NSR8 and NSR9

Leq (30 min.) (dB(A))

Once every week

Water Quality Monitoring

I-1; I-1-C; I-2; I-2-C; I-3; I-3-C,

O-1(FT),  O-1-C(FT), O-1(ET) and O-1-C(ET)

DO (mg/L)

Three days per week

SS (mg/L)

Turbidity (NTU)

pH

Temperature (oC)

Table 3-1         Frequency of Air Quality, Noise and Water Quality Monitoring

3.3               Monitoring Locations

3.3.1                The monitoring locations for air quality, noise and water quality are shown in Tables 3-2, 3-3, 3-4 and Appendix E.

Monitoring Station ID

Name of Premises

Floor Level

ASR1

Sik Sik Yuen Ho Fung College

G/F

ASR3

Hong Hoi Chee Hong Temple

Podium

ASR8

Beach Tower (Long Beach Gardens)

G/F

ASR9

Greenview Terrace (Block 1)

G/F

Table 3-2         Air Quality Monitoring Locations

Monitoring Station ID

Name of Premises

Floor Level

NSR1

Sik Sik Yuen Ho Fung College

G/F

NSR3

Hong Hoi Chee Hong Temple

Podium

NSR6

Squatters

G/F

NSR8

Beach Tower (Long Beach Gardens)

G/F

NSR9

Greenview Terrace (Block 1)

Podium (up to 6 July 2009)

Roof* (from 16 July 2009)

* The noise monitoring location of NSR9 had been relocated to the rooftop from 16 July 2009.

Table 3-3         Noise Monitoring Locations

Monitoring Station ID

Name of Premises

I-1

Intake I-1

I-1-C

Control of Intake I-1

I-2

Intake I-2

I-2-C

Control of Intake I-2

I-3

Intake I-3

I-3-C^

Control of Intake I-3

O-1 (FT) & (ET)

Outfall 1 during Flood Tide and Ebb Tide

O-1-C (FT)#

Control of Outfall O-1 During Flood Tide

O-1-C (ET)#

Control of Outfall O-1 During Ebb Tide

Note:   #Note that there are two control stations for Outfall O-1; one for sampling during flood tide and one for sampling during ebb tide.  Only one of those control stations for Outfall O-1 was sampled during each sampling.  Control station to be sampled was determined according to the tidal information provided by the Hong Kong Observatory.

^ The upper stream location (I-3-C^) had been relocated from the end of February 2009 due to coarse stone blockage.

Table 3-4         Water Quality Monitoring Locations

3.4               Performance Limits (AL Levels)

3.4.1                In accordance with the EM&A Manual, the appropriate Action and Limit Levels for air quality, air borne noise and water quality were established. They are presented in Table 3-5, Table 3-6 and Table 3-7.  Should non-compliance of the air quality, noise and water quality criteria occur, actions in accordance with the Event / Action Plan stipulated in contract specific EM&A Manual should be carried out.

Station

1-hr TSP Level in μg/m3

Action Level

Limit Level

ASR1

307

500

ASR3

327

500

ASR8

337

500

ASR9

329

500

Table 3-5         Action & Limit Levels for Air Quality

Time Period

Action

Limit

0700 – 1900 hours on normal weekdays

When one documented complaint is received

75 dB(A)*

*           For educational establishments the limit level shall be 70 dB(A) and reduced to 65 dB(A) during examination periods between 0700 and 1900 hours on normal weekdays.

Table 3-6         Action & Limit Levels for Air Borne Noise

Parameters

Action

Limit

DO in mg/L

(Surface; Middle & Bottom)

Surface & Middle

5%-ile of baseline data for surface and middle layer.

 

Bottom

5%-ile of baseline data for bottom layer.

Surface & Middle

4 mg/L, except 5 mg/L for Fish Culture Zone (FCZ) or

1%-ile of baseline data for surface and middle layer

Bottom

2 mg/L or 1%-ile of baseline data for bottom layer

SS in mg/L

(Depth-averaged)

95%-ile of baseline data or 120% of upstream control station’s SS level at the same tide of the same day

99%-ile of baseline or 130% of upstream control station’s SS level at the same tide of the same day and specific sensitive receiver water quality requirements (e.g. required suspended solids levels for concerned sea water intakes)

Turbidity (Tby) in NTU (Depth-averaged)

95%-ile of baseline data or 120% of upstream control station’s Tby at the same tide of the same day

99%-ile of baseline or 130% of upstream control station’s Tby at the same tide of the same day

Notes:

·         For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

·         For SS and Tby, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

·         All the figures given in the table are used for reference only and the EPD may amend the figures whenever necessary.

Table 3-7         Action & Limit Levels for Water Quality


3.5               Monitoring Result

3.5.1                All measured air quality monitoring levels were complying with the Action and Limit Levels in the reporting period. A summary of air quality monitoring results is presented in Table 3-9 and Appendix F.

Monitoring Station

1-hour TSP (mg/m3)

Action Level

Limit Level

Range

(mg/m3)

(mg/m3)

ASR1

18.4

-

207.5

307

500

ASR3

26.1

-

219.9

327

500

ASR8

20.1

-

196.8

337

500

ASR9

26.9

-

180.0

329

500

Italic indicates the exceedances of Action Levels

Bold indicates the exceedances of Limit Levels

Table 3-8         Summary of Air Quality Monitoring Results

3.5.2                All measured air borne noise monitoring levels were complying with the Limit Levels in the reporting period. However, one construction noise complaint at I-3 was received on 8 February 2012 and regarded as one action level exceedance. Details of the complaint are included in Section 5.12 and Appendix H.

3.5.3                A summary of noise monitoring results is presented in Table 3-9 and Appendix F.

Monitoring Station

Leq (30mins) dB(A)

Limit Level

Range

dB(A)

NSR1

62

-

64

65/70#

NSR3

58

-

64

75

NSR6

57

-

69

75

NSR8

61

-

71

75

NSR9

63

-

70

75

Bold indicates the exceedances of Limit Levels

# - Noise Limit Level was reduced to 65 dB(A) from 70 dB(A) during school examination period.

Table 3-9         Summary of Impact Air Borne Noise Monitoring Results

3.5.4                A summary of water quality monitoring results is presented in Table 3-10 and Appendix F.

3.5.5                None of exceedance related to project construction activities was recorded during the reporting quarter but a total of 129 non-project related exceedances were recorded.

River Water Quality Monitoring

3.5.6                A total of 1 non-project related exceedances were recorded in January 2012 including:

l One exceedance of SS action level was recorded at I-1 on 7 January 2012. The measured SS level (5.40 mg/L) was well below the baseline action/limit level, but higher than 120% of the SS level (4.25 mg/L) of the control station (I-1-C). Details of the construction activities conducted on the monitoring day are given in Appendix G. No direct disturbance was observed from the site. The exceedance was considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

3.5.7                A total of 4 non-project related exceedances were recorded in February 2012 including:

l Two exceedances of SS limit levels were recorded at I-1 on 20 and 22 February 2012. For 20 February 2012, the measured SS level (4.05 mg/L) was well below the baseline action/limit level, but higher than 130% of the SS level (2.95 mg/L) of the control station. Details of the construction activities conducted on the monitoring day are given in Appendix G. There was no water discharge from the construction site on the monitoring day. No direct disturbance was observed from the site. The exceedance on 20 February 2012 was considered to be contributed by natural variation and non-project related. Therefore, no further action was required. For 22 February 2012, the measured SS level (13.00 mg/L) was higher than the baseline limit level, but lower than the SS level (14.35 mg/L) of the control station. Details of the construction activities conducted on the monitoring day are given in Appendix G. There was no water discharge from the construction site on the monitoring day. No direct disturbance was observed from the site. The exceedance on 22 February 2012 was considered to be contributed by high SS level at the upstream location and non-project related. Therefore, no further action was required.

l One exceedance of SS limit level was recorded at I-2 on 29 February 2012. The measured SS level (3.10 mg/L) was well below the baseline action/limit level, but higher than 130% of the SS level (<2.00 mg/L) of the control station (I-2-C). Details of the construction activities conducted on the monitoring day are given in Appendix G. No direct disturbance was observed from the site. The exceedance was considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l One exceedance of SS limit level was recorded at I-3 on 6 February 2012. The measured SS level (2.65 mg/L) was well below the baseline action/limit level, but higher than 130% of the SS level (<2.00 mg/L) of the control station (I-3-C). Details of the construction activities conducted on the monitoring day are given in Appendix G. No direct disturbance was observed from the site. Therefore, the exceedance was considered to be contributed by natural variation. Since the exceedance was non-project related, no further action was required.

3.5.8                A total of 4 non-project related exceedances were recorded in March 2012 including:

l One exceedance of SS action level was recorded at I-1 on 9 March 2012. The measured SS level (5.50 mg/L) was below the baseline action/limit level, but higher than 120% of the SS level (4.40 mg/L) of the control station (I-1-C). Details of the construction activities conducted on the monitoring day are given in Appendix G. No direct disturbance was observed from the site. The exceedance was considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l One exceedance of SS action level was recorded at I-2 on 12 March 2012. The measured SS level (2.50 mg/L) was well below the baseline action/limit level, but higher than 120% of the SS level (<2.00 mg/L) of the control station (I-2-C). Details of the construction activities conducted on the monitoring day are given in Appendix G. No direct disturbance was observed from the site. The exceedance was considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l One exceedance of SS limit level was recorded at I-1 on 19 March 2012. The measured SS level (3.45 mg/L) was well below the baseline action/limit level, but higher than 130% of the SS level (2.25 mg/L) of the control station (I-1-C). Details of the construction activities conducted on the monitoring day are given in Appendix G. No direct disturbance was observed from the site. Therefore, the exceedance was considered to be contributed by natural variation. Since the exceedance was non-project related, no further action was required.

l One exceedance of SS limit level was recorded at I-2 on 5 March 2012. The measured SS level (2.80 mg/L) was well below the baseline action/limit level, but higher than 130% of the SS level (<2.00 mg/L) of the control station (I-2-C). Details of the construction activities conducted on the monitoring day are given in Appendix G. No direct disturbance was observed from the site. Therefore, the exceedance was considered to be contributed by natural variation. Since the exceedance was non-project related, no further action was required.

Marine Water Quality Monitoring

3.5.10              A total of 27 non-project related exceedances were recorded in January 2012 including:

l Two exceedances of DO action levels were recorded at O-1(ET) (marine bottom) on 3 and 5 January 2012. For 3 January 2012, the measured DO level (6.57 mg/L) at the monitoring station was below the baseline action level, but higher than the DO level (6.53 mg/L) of the corresponding control station. For 5 January 2012, the measured DO level (6.66 mg/L) at the monitoring station was below the baseline action level and lower than the DO level (6.76 mg/L) of the corresponding control station (about 1.5%). Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Four exceedances of DO limit levels were recorded at O-1(FT) (marine surface) on 3, 5, 7 and 18 January 2012. For 3, 7 and 18 January 2012, the measured DO levels (6.70, 6.72 and 6.74 mg/L, respectively) were below the baseline limit level and lower than the DO levels (6.72, 6.82 and 6.88 mg/L, respectively) of the corresponding control station (about 0.3%, 1.5% and 2.0%, respectively). For 5 January 2012, the measured DO level (6.65 mg/L) at the monitoring station was below the baseline limit level, but higher than the DO level (6.60mg/L) of the corresponding control station. Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Three exceedances of DO limit levels were recorded at O-1(FT) (marine mid-depth) on 3, 5 and 7 January 2012. For 3 and 5 January 2012, the measured DO levels (6.64 and 6.66 mg/L, respectively) at the monitoring station were below the baseline limit level, but higher than the DO levels (6.63 and 6.45 mg/L, respectively) of the corresponding control station. For 7 January 2012, the measured DO level (6.70 mg/L) at the monitoring station was below the baseline limit level and lower than the DO level (6.79 mg/L) of the corresponding control station (about 1.3%). Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Three exceedances of DO limit levels were recorded at O-1(FT) (marine bottom) on 3, 5 and 7 January 2012. For 3 and 7 January 2012, the measured DO levels (6.85 and 6.80 mg/L, respectively) at the monitoring station were below the baseline limit level, but higher than the DO levels (6.82 and 6.75 mg/L, respectively) of the corresponding control station. For 5 January 2012, the measured DO level (6.48 mg/L) at the monitoring station was below the baseline limit level and lower than the DO level (6.49 mg/L) of the corresponding control station (about 0.2%). Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Three exceedances of DO limit levels were recorded at O-1(ET) (marine surface) on 3, 5 and 7 January 2012. For 3 and 7 January 2012, the measured DO levels (6.55 and 6.82 mg/L, respectively) at the monitoring station were below the baseline limit level, but higher than the DO levels (6.42 and 6.76 mg/L, respectively) of the corresponding control station. For 5 January 2012, the measured DO level (6.62 mg/L) at the monitoring station was below the baseline limit level and lower than the DO level (6.74 mg/L) of the corresponding control station (about 1.8%). Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Four exceedances of DO limit levels were recorded at O-1(ET) (marine mid-depth) on 3, 5, 7 and 28 January 2012. For 3 January 2012, the measured DO level (6.50 mg/L) at the monitoring station was below the baseline limit level, but higher than the DO level (6.47 mg/L) of the corresponding control station. For 5, 7 and 28 January 2012, the measured DO levels (6.53, 6.64 and 6.93 mg/L, respectively) at the monitoring station were below the baseline limit level and lower than the DO levels (6.59, 6.72 and 7.01 mg/L, respectively) of the corresponding control station (about 0.9%, 1.2% and 1.1%, respectively). Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Three exceedances of SS action levels were recorded at O-1(FT) on 7, 11 and 16 January 2012. The measured SS levels (5.98, 3.78 and 4.85 mg/L, respectively) at the monitoring station were well below the baseline action/limit level, but higher than 120% of the SS levels (4.77, 3.10 and 3.90 mg/L, respectively) of the corresponding control station. Details of the construction activities conducted on the monitoring days are given in Appendix G.   No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l One exceedance of SS action level was recorded at O-1(ET) on 18 January 2012. The measured SS level (2.87 mg/L) at the monitoring station was well below the baseline action/limit level, but higher than 120% of the SS level (2.37 mg/L) of the corresponding control station. Details of the construction activities conducted on the monitoring day are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l One exceedance of SS limit level was recorded at O-1(FT) on 20 January 2012. The measured SS level (6.15 mg/L) at the monitoring station was well below the baseline action/limit level, but higher than 130% of the SS level (4.57 mg/L) of the corresponding control station. Details of the construction activities conducted on the monitoring day are given in Appendix G. No direct disturbance was observed from the site. The exceedance was considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Three exceedances of SS limit levels were recorded at O-1(ET) on 11, 16 and 30 January 2012. The measured SS levels (4.65, 4.90 and 4.95 mg/L, respectively) at the monitoring station were well below the baseline action/limit level, but higher than 130% of the SS levels (3.23, 3.62 and 3.65 mg/L, respectively) of the corresponding control station. Details of the construction activities conducted on the monitoring days are given in Appendix G.  No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

3.5.11              A total of 55 non-project related exceedances were recorded in February 2012 including:

l One exceedance of DO action level was recorded at O-1(FT) (marine mid-depth) on 22 February 2012. The measured DO level (6.82 mg/L) at the monitoring station was below the baseline action level and lower than the DO level (6.84 mg/L) of the corresponding control station (about 0.3%). Details of the construction activities conducted on the monitoring day are given in Appendix G. No direct disturbance was observed from the site. The exceedance was considered to be contributed by natural variation and non-project related. Therefore, no further action was required

l One exceedance of DO action level was recorded at O-1(ET) (marine surface) on 10 February 2012. The measured DO level (6.94 mg/L) at the monitoring station was below the baseline action level and lower than the DO level (6.99 mg/L) of the corresponding control station (about 0.7%). Details of the construction activities conducted on the monitoring day are given in Appendix G. No direct disturbance was observed from the site. The exceedance was considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l One exceedance of DO action level was recorded at O-1(ET) (marine mid-depth) on 22 February 2012. The measured DO level (6.95 mg/L) at the monitoring station was below the baseline action level, but higher than the DO level (6.94 mg/L) of the corresponding control station. Details of the construction activities conducted on the monitoring day are given in Appendix G. No direct disturbance was observed from the site. The exceedance was considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Three exceedances of DO action levels were recorded at O-1(ET) (marine bottom) on 15, 24 and 27 February 2012. For 15 and 27 February 2012, the measured DO levels (6.65 and 6.60 mg/L, respectively) were below the baseline action level, but higher than the DO levels (6.47 and 6.56 mg/L, respectively) of the corresponding control station. For 24 February 2012, the measured DO level (6.66 mg/L) at the monitoring station was below the baseline action level and lower than the DO level (6.76 mg/L) of the corresponding control station (about 1.5%). Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Six exceedances of DO limit levels were recorded at O-1(FT) (marine surface) on 8, 13, 15, 17, 27 and 29 February 2012. The measured DO levels (6.63, 6.48, 6.32, 6.46, 6.64 and 6.76 mg/L, respectively) at the monitoring station were below the baseline limit level and lower than the DO levels (6.64, 6.60, 6.36, 6.49, 6.71 and 6.81 mg/L, respectively) of the corresponding control station (about 0.2%, 1.8%, 0.6%, 0.5%, 1.0% and 0.7%, respectively). Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Eight exceedances of DO limit levels were recorded at O-1(FT) (marine mid-depth) on 8, 13, 15, 17, 20, 24, 27 and 29 February 2012. For 8, 13, 15, 27 and 29 February 2012, the measured DO levels (6.61, 6.49, 6.23, 6.62 and 6.69 mg/L, respectively) at the monitoring station were below the baseline limit level and lower than the DO levels (6.68, 6.56, 6.34, 6.64 and 6.70 mg/L, respectively) of the corresponding control station (about 1.0%, 1.1%, 1.7%, 0.3% and 0.1%, respectively). For 17 and 20 February 2012, the measured DO levels (6.43 and 6.74 mg/L, respectively) at the monitoring station were below the baseline limit level, but higher than the DO levels (6.31 and 6.68 mg/L, respectively) of the corresponding control station. For 24 February 2012, the measured DO level (6.66 mg/L) at the monitoring station was below the baseline limit level and same as the DO level of the corresponding control station. Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Eleven exceedances of DO limit levels were recorded at O-1(FT) (marine bottom) on 3, 6, 8, 13, 15, 17, 20, 22, 24, 27 and 29 February 2012. For 3, 6, 8, 17, 22, 24 and 27 February 2012, the measured DO levels (6.77, 6.88, 6.68, 6.36, 6.87, 6.62 and 6.59 mg/L, respectively) at the monitoring station were below the baseline limit level and lower than the DO levels (6.80, 7.01, 6.75, 6.47, 6.88, 6.67 and 6.73 mg/L, respectively) of the corresponding control station (about 0.4%, 1.9%, 1.0%, 1.7%, 0.1%, 0.7% and 2.1%, respectively). For 13, 20 and 29 February 2012, the measured DO levels (6.47, 6.80 and 6.75 mg/L, respectively) at the monitoring station were below the baseline limit level, but higher than the DO levels (6.45, 6.78 and 6.63 mg/L, respectively) of the corresponding control station. For 15 February 2012, the measured DO level (6.41 mg/L) at the monitoring station was below the baseline limit level and same as the DO level of the corresponding control station. Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Nine exceedances of DO limit levels were recorded at O-1(ET) (marine surface) on 8, 13, 15, 17, 20, 22, 24, 27 and 29 February 2012. For 8, 17, 22 and 24 February 2012, the measured DO levels (6.48, 6.53, 6.92 and 6.78 mg/L, respectively) at the monitoring station were below the baseline limit level and lower than the DO levels (6.59, 6.63, 7.05 and 6.82 mg/L, respectively) of the corresponding control station (about 1.7%, 1.5%, 1.8%, and 0.6%, respectively). For 15, 20, 27 and 29 February 2012, the measured DO levels (6.50, 6.87, 6.63 and 6.78 mg/L, respectively) at the monitoring station were below the baseline limit level, but higher than the DO levels (6.43, 6.86, 6.51 and 6.66 mg/L, respectively) of the corresponding control station. For 13 February 2012, the measured DO level (6.30 mg/L) at the monitoring station was below the baseline limit level and same as the DO level of the corresponding control station. Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Eight exceedances of DO limit levels were recorded at O-1(ET) (marine mid-depth) on 8, 13, 15, 17, 20, 24, 27 and 29 February 2012. For 8, 15, 17, 20, 24 and 29 February 2012, the measured DO levels (6.66, 6.59, 6.41, 6.79, 6.76 and 6.71 mg/L, respectively) at the monitoring station were below the baseline limit level, but higher than the DO levels (6.53, 6.31, 6.36, 6.72, 6.70 and 6.70 mg/L, respectively) of the corresponding control station. For 13 February 2012, the measured DO level (6.35 mg/L) at the monitoring station was below the baseline limit level and lower than the DO level (6.36 mg/L) of the corresponding control station (about 0.2%). For 27 February 2012, the measured DO level (6.69 mg/L) at the monitoring station was below the baseline limit level and the same as the DO level of the corresponding control station. Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Two exceedances of DO limit levels were recorded at O-1(ET) (marine bottom) on 13 and 17 February 2012. For 13 February 2012, the measured DO level (6.42 mg/L) at the monitoring station was below the baseline limit level, but higher than the DO level (6.32 mg/L) of the corresponding control station. For 17 February 2012, the measured DO level (6.38 mg/L) at the monitoring station was below the baseline limit level and lower than the DO level (6.44 mg/L) of the corresponding control station (about 0.9%). Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedance was considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l One exceedance of SS action level was recorded at O-1(FT) on 24 February 2012. The measured SS level (7.50 mg/L) at the monitoring station was below the baseline action/limit level, but higher than 120% of the SS level (6.22 mg/L) of the corresponding control station. Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedance was considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l One exceedance of SS limit level was recorded at O-1(FT) on 22 February 2012. The measured SS level (2.68 mg/L) was well below the baseline action/limit level, but higher than 130% of the SS level (2.05 mg/L) of the corresponding control station. Details of the construction activities conducted on the monitoring days are given in Appendix G.   No direct disturbance was observed from the site. The exceedance was considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Three exceedances of SS limit levels were recorded at O-1(ET) on 1, 6 and 15 February 2012. The measured SS levels (2.95, 3.33 and 3.93 mg/L, respectively) at the monitoring station were well below the baseline action/limit level, but higher than 130% of the SS levels (2.23, 2.55 and 2.88 mg/L, respectively) of the corresponding control station. Details of the construction activities conducted on the monitoring days are given in Appendix G.   No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

3.5.12              A total of 38 non-project related exceedances were recorded in March 2012 including:

l Two exceedances of DO action levels were recorded at O-1(ET) (marine mid-depth) on 7 and 16 March 2012. For 7 March 2012, the measured DO level (7.01 mg/L) at the monitoring station was below the baseline action level and lower than the DO level (7.08 mg/L) of the corresponding control station (about 1.0%). For 16 March 2012, the measured DO level (6.98 mg/L) at the monitoring station was below the baseline action level, but higher than the DO level (6.85 mg/L) of the corresponding control station.  Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Three exceedances of DO action levels were recorded at O-1(ET) (marine bottom) on 2, 5 and 16 March 2012. For 2 March 2012, the measured DO level (6.55 mg/L) at the monitoring station was below the baseline action level and lower than the DO level (6.56 mg/L) of the corresponding control station (about 0.2%). For 5 and 16 March 2012, the measured DO levels (6.63 and 6.67 mg/L, respectively) at the monitoring station were below the baseline action level, but higher than the DO levels of the corresponding control station (6.54 and 6.50 mg/L, respectively). Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l One exceedance of DO limit level was recorded at O-1(FT) (marine surface) on 5 March 2012. The measured DO level (6.70 mg/L) at the monitoring station was below the baseline limit level and lower than the DO level (6.84 mg/L) of the corresponding control station (about 2.0%). Details of the construction activities conducted on the monitoring day are given in Appendix G. No direct disturbance was observed from the site. The exceedance was considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Five exceedances of DO limit levels were recorded at O-1(FT) (marine mid-depth) on 2, 5, 9, 12 and 16 March 2012. For 2 March 2012, the measured DO level (6.70 mg/L) at the monitoring station was below the baseline limit level, but higher than the DO level (6.66 mg/L) of the corresponding control station. For 5, 9, 12 and 16 March 2012, the measured DO levels (6.61, 6.79, 6.55 and 6.46 mg/L, respectively) at the monitoring station were below the baseline limit level and lower than the DO levels (6.68, 6.84, 6.71 and 6.53 mg/L, respectively) of the corresponding control station (about 1.0%, 0.7%, 2.4% and 1.1%, respectively). Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Eight exceedances of DO limit levels were recorded at O-1(FT) (marine bottom) on 2, 5, 9, 12, 14, 16, 23 and 30 March 2012. For 2, 9 and 16 March 2012, the measured DO levels (6.59, 6.88 and 6.64 mg/L, respectively) at the monitoring station were below the baseline limit level and lower than the DO levels (6.61, 6.89 and 6.75 mg/L, respectively) of the corresponding control station (about 0.3%, 0.1% and 1.6%, respectively). For 5, 12, 23 and 30 March 2012, the measured DO levels (6.61, 6.78, 6.92 and 6.84 mg/L, respectively) at the monitoring station were below the baseline limit level, but higher than the DO levels (6.60, 6.67, 6.90 and 6.79 mg/L, respectively) of the corresponding control station. For 14 March 2012, the measured DO level (6.80 mg/L) at the monitoring station was below the baseline limit level and same as the DO level of the corresponding control station. Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Eight exceedances of DO limit levels were recorded at O-1(ET) (marine surface) on 2, 5, 9, 12, 14, 16, 23 and 26 March 2012. For 2, 5, 9, 12, 14, 16 and 26 March 2012, the measured DO levels (6.75, 6.91, 6.81, 6.84, 6.93, 6.80 and 6.91 mg/L, respectively) at the monitoring station were below the baseline limit level and lower than the DO level (6.80, 7.04, 6.89, 6.89, 6.97, 6.91 and 7.12 mg/L, respectively) of the corresponding control station (about 0.7%, 1.8%, 1.2%, 0.7%, 0.6%, 1.6% and 2.9%, respectively). For 23 March 2012, the measured DO level (6.92 mg/L) at the monitoring station was below the baseline limit level, but higher than the DO level (6.91 mg/L) of the corresponding control station. Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Seven exceedances of DO limit levels were recorded at O-1(ET) (marine mid-depth) on 2, 5, 9, 12, 14, 23 and 30 March 2012. The measured DO levels (6.64, 6.59, 6.82, 6.73, 6.74, 6.88 and 6.91 mg/L, respectively) at the monitoring station were below the baseline limit level and lower than the DO levels (6.71, 6.71, 6.86, 6.75, 6.83, 6.95 and 6.94 mg/L, respectively) of the corresponding control station (about 1.0%, 1.8%, 0.6%, 0.3%, 1.3%, 1.0% and 0.4%, respectively). Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Two exceedances of SS action level were recorded at O-1(FT) on 2 and 5 March 2012. The measured SS levels (2.78 and 4.32 mg/L, respectively) at the monitoring station were well below the baseline action/limit level, but higher than 120% of the SS levels (2.17 and 3.50 mg/L, respectively) of the corresponding control station. Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

l Two exceedances of SS limit level were recorded at O-1(ET) on 2 and 14 March 2012. The measured SS levels (3.86 and 4.28 mg/L, respectively) at the monitoring station were well below the baseline action/limit level, but higher than 130% of the SS levels (2.83 and 2.98 mg/L, respectively) of the corresponding control station. Details of the construction activities conducted on the monitoring days are given in Appendix G. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and non-project related. Therefore, no further action was required.

3.5.13              The above mentioned exceedances were considered non-project related. However, proper mitigation measures had been implemented during measurements. Details of the above mentioned investigations could be referred to the Interim Notifications of Environmental Quality Limits Exceedances as enclosed in Appendix G.


Monitoring Station

Temperature (oC)

DO (mg/L)

pH

Turbidity (NTU)

Suspended Solid (mg/L)

Range

Range

Action / Limit Level

Range

Range

Action / Limit Level

Range

Action / Limit Level

I-1

12.00

-

24.10

7.06

-

9.82

3.42

/

3.34

7.60

-

8.31

2.14

-

9.25

9.75

/

12.47

<2.00

-

13.00

8.85

/

10.17

I-1-C

12.10

-

24.10

7.09

-

9.87

 

-

 

7.60

-

8.30

2.21

-

9.20

 

-

 

<2.00

-

14.35

 

-

 

I-2

11.90

-

24.75

7.19

-

9.78

3.66

/

3.63

7.54

-

8.23

1.04

-

5.26

6.63

/

6.99

<2.00

-

3.10

7.68

/

8.34

I-2-C

11.90

-

24.70

7.04

-

9.91

 

-

 

7.54

-

8.23

1.08

-

5.24

 

-

 

<2.00

-

3.65

 

-

 

I-3

11.70

-

25.00

7.04

-

9.86

3.65

/

3.51

7.50

-

8.31

0.83

-

3.58

3.99

/

4.18

<2.00

-

3.90

6.13

/

7.23

I-3-C

11.70

-

24.90

6.94

-

9.83

 

-

 

7.50

-

8.31

0.84

-

3.70

 

-

 

<2.00

-

4.50

 

-

 

Note:   Italic indicates the exceedances of Action Levels

Bold indicates the exceedances of Limit Levels

Table 3-10       Summary of Impact Water Quality Monitoring Results


 

Monitoring
Station

Temperature (oC)

DO (mg/L)

pH

Turbidity (NTU)

Suspended Solid (mg/L)

Range

Range

Action / Limit Level

Range

Range

Action / Limit Level

Range

Action / Limit Level

O-1(FT)

Surface

15.90

-

21.38

6.32

-

7.54

6.84

/

6.81

7.70

-

8.34

1.51

-

7.53

10.35

/

13.15

<2.00

-

9.52

14.10

/

18.08

Middle

6.23

-

7.59

Bottom

6.36

-

7.44

6.99

/

6.96

O-1-C(FT)

Surface

15.90

-

21.40

6.36

-

7.48

-

/

-

7.72

-

8.32

1.53

-

10.39

-

/

-

<2.00

-

15.97

-

/

-

Middle

6.31

-

7.58

Bottom

6.41

-

7.38

O-1(ET)

Surface

15.90

-

21.80

6.30

-

7.41

7.02

/

6.94

7.72

-

8.33

1.48

-

4.88

11.87

/

13.44

<2.00

-

11.22

13.25

/

14.39

Middle

6.35

-

7.54

Bottom

6.38

-

7.43

6.70

/

6.48

O-1-C(ET)

Surface

15.90

-

21.77

6.30

-

7.44

-

/

-

7.72

-

8.33

1.52

-

4.84

-

/

-

<2.00

-

9.47

-

/

-

Middle

6.31

-

7.54

Bottom

6.32

-

7.46

Note:   Italic indicates the exceedances of Action Levels

Bold indicates the exceedances of Limit Levels

Table 3-11       Summary of Impact Marine Water Quality Monitoring Results


4                     Quarterly Summary, Environmental Condition and Non-Compliance Records

4.1               Summary of Waste Disposal Records

4.1.1                According to the information provided by the Contractor; the quantities of C&D materials and other wastes in the reporting period are summarized in Table 4-1

Status of Waste Management

January 2012

February 2012

March 2012

Inert C&D Material Disposed of to Public Fill at Tuen Mun (m3)

2,196.5

1,315.6

285.7

Inert C&D Material Reused in this Contract (m3)

Nil

532.5

Nil

Inert C&D Material Reused in other Contract* (m3)

1,145.0

4,630.0

1,207.5

Metals Generated (kg)

22.0

Nil

229,030.0

Paper / Cardboard Packaging (kg)

350.0

Nil

Nil

Plastics (kg)

20

Nil

Nil

Chemical Waste (kg)

Nil

Nil

411.0

General Waste Disposed of to NENT Landfill (m3)

66.2

87.0

43.3

* Other Contracts include CV/2009/14, DC/2007/08, DC/2007/09, HY/2007/09, HY/2007/10, HY/2008/09, XRL823AB and Tailor Recycle Aggregate

Table 4-1         Waste Generated from January to March 2012

4.2               Weather Conditions

4.2.1                The weather conditions during the period from January to March 2012 were mainly sunny, cloudy and rainy.

4.3               Summary of Project-Related Exceedances

4.3.1                Summary of exceedance results are summarized in Table 4-2. Appendix G shows the Interim Notifications of Environmental Quality Limits Exceedances issued in the reporting period.


Environmental Monitoring

Total No. of Measurement

Action Level Exceedance

% of Action Level Exceedance

Limit Level Exceedance

% of Limit Level Exceedance

Air Quality

192

0

0

0

0

Air Borne Noise

69

1(Complaint)

1.4

0

0

Water

378

0

0

0

0

Table 4-2         Summary of Project- related Exceedances

5                     Complaint

5.1.1                A complaint hotline at 9850 3241 of the Contractor has been established for the Project. 

5.1.2                One environmental complaint was received on 8 February 2012 by SOR about daytime construction noise from the Intake I-3 construction site on 8 February 2012.The Contractor informed ET that one public complaint regarding daytime construction noise from the Intake I-3 construction site was received by SOR on 8 February. The ET conducted site inspections at Intake I-3 construction site on 9 and 23 February 2012 to review and audit the site setting, mitigation measures implemented on-site and the environmental performance of the Contractor. Noise monitoring at NSR 6 was increased to twice per week from 10 February 2012 to 29 February 2012 according to the Event/Action Plan and no exceedance of limit level was recorded. An investigation report was prepared and submitted on 5 March 2012. Since no further complaint was received, the complaint was considered closed. Details of the complaint investigation and observations can be referred to Appendix H.

5.1.3                Cumulative statistics of environmental complaints are shown in Table 5-1.

Complaints Received in the Reporting Period

Cumulative Number of Complaints

1

24

Table 5-1         Cumulative Statistics of Environmental Complaints

6                     Summary of Notification of Summons, Successful Prosecutions and Corrective Actions

6.1.1                No summons and successful prosecution was received during the reporting period.

6.1.2                Cumulative statistics of Notification of Summon, Successful Prosecutions and Convictions are shown in Table 6-1.

Notification of Summons

Successful Prosecution

January – March 2012

Cumulative

January – March 2012

Cumulative

0

0

0

0

Table 6-1         Cumulative Statistics of Notification of Summons and Successful Prosecutions

7                     Comments, Recommendations and Conclusion

7.1.1                During the reporting period, no project related exceedance of air quality monitoring and air borne noise monitoring was recorded. Exceedances of water quality monitoring were recorded but none of these exceedances were related to Project’s construction activities.

7.1.2                One environmental complaint was received on 8 February 2012 by SOR about daytime construction noise from the Intake I-3 construction site on 8 February 2012. Details of the complaint investigation and observations can be referred to Section 5.1.2 and Appendix H.

7.1.3                No Notification of Summons has been received since the commencement of the Project. 

7.1.4                Waste management mitigation measures have been implemented by the Contractor within the reporting period.  Waste figures during the reporting period are summarized in Table 7-1.

Status of Waste Management

Quantity

Inert C&D Material Disposed of to Public Fill at Tuen Mun (m3)

3797.8

Inert C&D Material Reused in this Contract (m3)

532.5

Inert C&D Material Reused in other Contract* (m3)

6982.5

Metals Generated (kg)

229052.0

Paper / Cardboard Packaging (kg)

350.0

Plastics (kg)

20.0

Chemical Waste (kg)

411.0

General Waste Disposed of to NENT Landfill (m3)

196.5

* Other Contracts include CV/2009/14, DC/2007/08, DC/2007/09, HY/2007/09, HY/2007/10, HY/2008/09, XRL823AB and Tailor Recycle Aggregate

Table 7-1     Total Wastes Generated From January to March 2012


 

Appendix A

RuleBentDown

Site Map and Works Area


 

Appendix B

RuleBentDown

Organization Chart


 

Appendix C

RuleBentDown

Works Programme


 

Appendix D

RuleBentDown

Implementation Status of Environmental Mitigation Measures


 

Appendix E

RuleBentDown

Monitoring Locations


 

Appendix F

RuleBentDown

Monitoring Results


 

Appendix G

RuleBentDown

Interim Notifications of Environmental Quality Limits Exceedances


 

Appendix H

RuleBentDown

Complaint Log