



|
|
Appendix A Site
Map and Works Area
Appendix D Implementation
Status of Environmental Mitigation Measures
Appendix E Monitoring
Locations
Appendix G Interim
Notifications of Environmental Quality Limits Exceedances
|
TABLES |
|
|
Table 3-1 Frequency of Air
Quality, Noise and Water Quality Monitoring
Table 3-2 Air Quality Monitoring
Locations
Table 3-3 Noise Monitoring
Locations
Table 3-4 Water Quality
Monitoring Locations
Table 3-5 Action & Limit
Levels for Air Quality
Table 3-6 Action & Limit
Levels for Air Borne Noise
Table 3-7 Action & Limit
Levels for Ground Borne Noise
Table 3-8 Action & Limit
Levels for Water Quality
Table 3-9 Summary of Air Quality
Monitoring Results
Table 3-10 Summary of Impact Air
Borne Noise Monitoring Results
Table 3-11 Summary of Impact Ground
Borne Noise Monitoring Results
Table 3-12 Summary of Impact Water
Quality Monitoring Results
Table 3-13 Summary of Impact Marine
Water Quality Monitoring Results
Table 4-1 Waste Generated from April to June 2011
Table 4-2 Summary of Project- related Exceedances
Table 5-1 Cumulative Statistics
of Environmental Complaints
Table 6-1 Cumulative
Statistics of Notification of Summons and Successful Prosecutions
Table 7-1 Total Wastes Generated from April to June 2011
Executive Summary
1
This
quarterly EM&A summary report under the Main Contract for the Design and
Construction of Tsuen Wan Drainage Tunnel (hereafter referred to as the
“Project”) to Maeda-CREC-SELI Joint Venture (MCSJV), which summarises the
findings of environmental impact monitoring works during the period from April to June 2011.
2
Air borne
noise monitoring was performed at five monitoring stations (NSR1, NSR3, NSR6,
NSR8 and NSR9) and ground borne noise monitoring was performed at one
monitoring station (NSR 6). Air quality
monitoring was carried out at four monitoring stations (ASR1, ASR3, ASR8 and
ASR9). Water quality monitoring was
carried out at four monitoring stations (Intake I-1, Intake I-2, Intake I-3 and
Outfall O-1). Noise level was measured in terms of Leq, L10
and L90 (30min). Air quality
was measured in terms of 1-hour Total Suspended Particulates (TSP). Water
quality was measured in terms of Temperature, pH, Dissolved Oxygen (DO),
Turbidity (Tby) and Suspended Solid (SS).
3
Details of
all monitoring stations are summarized in the table below.
|
Type of
Monitoring |
Monitoring
Station ID |
Name of Premises |
Status of
Monitoring Works during the Reporting Period |
|
Air
Quality Monitoring |
ASR1 |
Sik Sik Yuen Ho Fung
College |
Ongoing |
|
ASR3 |
Hong
Hoi Chee Hong Temple |
Ongoing |
|
|
ASR8 |
Beach
Tower (Long Beach Gardens) |
Ongoing |
|
|
ASR9 |
Greenview
Terrace (Block 1) |
Ongoing |
|
|
Air
Borne Noise Monitoring |
NSR1 |
Sik
Sik Yuen Ho Fung College |
Ongoing |
|
NSR3 |
Hong
Hoi Chee Hong Temple |
Ongoing |
|
|
NSR6 |
Squatters |
Ongoing |
|
|
NSR8 |
Beach
Tower (Long Beach Gardens) |
Ongoing |
|
|
NSR9 |
Greenview
Terrace (Block 1) |
Ongoing |
|
|
Ground
Borne Noise Monitoring |
NSR3 |
Hong
Hoi Chee Hong Temple |
To
be commenced in early August 2011 (Tentative) |
|
NSR6 |
Squatters |
Commenced
on 1 March 2011 and completed on 14 April 2011 |
|
|
Water
Quality Monitoring |
I-1 |
Intake
I-1 |
Ongoing |
|
I-2 |
Intake I-2 |
Ongoing |
|
|
I-3 |
Intake I-3 |
Ongoing |
|
|
O-1 |
Outfall O-1 |
Ongoing |
4
The major construction
activities undertaken by the Contractor during the period from April to June 2011 include site cleaning and tidying at Outfall,
I-1, I-2 and I-3; drilling, excavation and rock splitting at spiral ramp at
Outfall; tunnel boring machine (TBM) drilling of the tunnel and mucking out of
tunnel spoil at Outfall; removal of existing retaining wall and hanging support
for existing utilities at fast lane of Castle Peak Road (CPR) at Outfall;
excavation and soil nailing for box culvert construction at fast lane of CPR
east bound at Outfall; excavation and disposal of excavated material from
existing arch bridge underneath CPR at Outfall; placing levelling stone and
bagged concrete to formation of sea wall at Portion E; installation of precast
sea wall blocks at Portion E; backfilling rockfill and type II armour behind the seawall
blocks at Portion E; disposal of the excavated soil under the arch bridge to
TM38 at Portion E; relocation of
type II armour rocks behind the seawall blocks at Portion E; cascade and
channel modification concrete structure works at I-1; construction of
horizontal pipe pile (pipe roofing) for TBM break-through at I-1; pre-bored H-pile
construction for vehicular access at I-1; drilling, excavation and rock splitting of man access shaft
and vortex drop shaft at I-2; pipe jacking at Portion G at I-2; pre-bored
H-pile construction for skin wall at Portion G at I-2; construction of approach
channel structure at I-2; construction of 750 step channel and catchpit at
Portion G at I-2; construction of drainage works at Portion G at I-2; preparation works for blasting at I-2; drilling,
rock splitting and excavation of vortex shaft at I-3; construction of PB wall
structure skin wall and copping beam at I-3; construction of boulder traps at
I-3; installation of concrete blocks for temporary bund wall at I-3; tree establishment
works of the transplanted trees at I-3; backfilling for PB Wall, removal of piling platform and
slope reinstatement at I-3; and construction of base slab for approach channel
at I-3.
5
As recommended in the EIA report, no TBM
operation was undertaken during restricted hours from chainage 3308 m to 3143
m.
6
No project
related exceedance of air quality and water quality monitoring was recorded. No exceedance of noise limit level
was recorded, but EPD receives one complaint on construction noise which
triggers the exceedance of noise action level. The
below table summarizes the exceedances of air quality, noise and water quality
in the reporting period.
|
Parameter |
Action Level
Exceedance |
Limit
Level Exceedance |
|
Air
|
Nil |
Nil |
|
Air
Borne Noise |
One complaint received on 30
Jun 2011 at NSR 6 |
Nil |
|
Ground
Borne Noise |
Nil |
Nil |
|
DO |
Four
records on 7 May, 18 May and 20 Jun 2011 at O-1(FT) Ten
records on 20 May, 27 May, 30 May, 3 Jun, 7 Jun, 17 Jun and 20 Jun 2011 at
O-1(ET) |
Nineteen
records on 7 May, 13 May, 18 May, 30 May, 7 Jun, 11 Jun, 13 Jun, 15 Jun, 17
Jun, 20 Jun, 27 Jun and 29 Jun at O-1(FT) Nineteen
records on 7 May, 13 May, 20 May, 1 Jun, 9 Jun, 11 Jun, 15 Jun, 17 Jun, 20
Jun, 24 Jun, 27 Jun and 29 Jun 2011 at O-1(ET) |
|
Turbidity |
One record on 22 Jun 2011 at I-1 |
One record on 17 Jun 2011
at I-1 Two records on 17 Jun and
22 Jun 2011 at I-2 Three records on 13 May, 17
Jun and 22 June at I-3 |
|
SS |
Four
records on 8 Apr, 18 Apr, 9 Jun and 17 Jun 2011 at I-1 Four
records on 8 Apr, 11 Apr, 13 Apr and 3 May 2011 at O-1(FT) One
record on 18 May 2011 at O-1(ET) |
One
record on 6 Apr 2011 at I-1 Three
records on 13 May, 17 Jun and 22 Jun 2011 at I-2 Two
records on 13 May and 17 Jun 2011 at I-3 One
record on 27 May 2011 at O-1(FT) Three
records on 20 May, 11 Jun and 27 Jun 2011 at O-1(ET) |
7
Waste
figures during the reporting period are summarized in the table below.
|
Status of Waste Management |
Quantity |
|
Inert C&D Material Disposed of to
Public Fill at Tuen Mun (m3) |
12,268.2 |
|
Inert C&D
Material Reused in this Contract (m3) |
773.5 |
|
Inert C&D Material Reused in
other Contract* (m3) |
53,664.2 |
|
Metals Generated (kg) |
Nil |
|
Paper / Cardboard Packaging (kg) |
350.0 |
|
Plastics (kg) |
Nil |
|
Chemical Waste (kg) |
6,153.4 |
|
General Waste Disposed of to NENT
Landfill (m3) |
120.9 |
* Other
Contracts include DC/2007/08, YL/2009/01, HY/2007/10,HY/2008/09, Wo Shang Wai, DC/2007/17, CV/2009/14, Tailor
Recycle Aggregate, XRL 823A and 823B, XRL 825, TW 7 and CUHK.
8
During the
reporting period, one environmental complaint was received. EPD informed ET on 8 July
2011 that one public complaint regarding construction dust and daytime
construction noise from the Intake I-3 construction site was received on 30
June 2011. The ET conducted site investigations at Intake I-3 construction site
on 8 and 20 July 2011 to review and audit the site setting, mitigation measures
implemented on-site, and the environmental performance of the Contractor. Noise
monitoring at NSR 6 was increased to twice per week from 11 July to 30 July
2011 according to the requirement of EM&A Manual. An investigation report was submitted to EPD
in August 2011. The issue of complaint was considered closed. The noise monitoring results would be
reported in the Monthly EM&A Report of July 2011.
9
No
Notification of Summons was received since the commencement of the Project.
1.1.1
The
Drainage Services Department (DSD) proposes to construct a tunnel of an
internal diameter of 6.5m and length 5.13km, with the purpose to alleviate the
flooding risk in Tsuen Wan and Kwai Chung.
1.1.2
This
project is a Designated Project under Schedule 2 Part I Category Q, of the
Environmental Impact Assessment Ordinance (EIAO) as part of the proposed Tsuen
Wan Drainage Tunnel (TWDT) passes underneath the existing Tai Mo Shan Country
Park. An Environmental Impact Assessment
(EIA) Study has therefore been undertaken to provide information on the nature
and extent of environmental impacts arising from the construction and operation
of the proposed designed project and related activities taking place
concurrently. From the EIA the
recommendations for monitoring contained herein, are made.
1.1.3
The Maeda-CREC-SELI
Joint Venture (MCSJV) was awarded by DSD with
the Contract – Design and Construction of Tsuen Wan Drainage Tunnel.
1.1.4
Hyder was
commissioned by the MCSJV as the ET to implement an EM&A program in
accordance with the EM&A Manual. The
proposed tunnel section flows from the junction of Shing Mun Road and Wo Yi Hop
Road and discharges to south of Yau Kom Tau underneath Castle Peak Road as
shown in Appendix A.
1.1.5 The construction works of the Project commenced in January 2008. This is the thirteenth quarterly EM&A report summarising the impact monitoring results and audit findings of the EM&A program during the reporting period between April and June 2011.
2.1 Project Organization and Management Structure
2.1.1 The organization chart and lines of communication with respect to the on-site environmental management are shown in Appendix B.
2.2.1
It is
anticipated that the overall project programme from the detail design to
completion of all civil works shall take approximately 54 months. The construction programme is presented in
Appendix C.
2.2.2
The major
construction activities undertaken in the reporting quarter are:
l
Site
cleaning and tidying at Outfall, I-1, I-2 and I-3;
l
Drilling,
excavation and rock splitting at spiral ramp at Outfall;
l
Tunnel
boring machine (TBM) drilling of the tunnel and mucking out of tunnel spoil at
Outfall;
l
Removal of
existing retaining wall and hanging support for existing utilities at fast lane
of Castle Peak Road (CPR) at Outfall;
l
Excavation
and soil nailing for box culvert construction at fast lane of CPR east bound at
Outfall;
l
Excavation
and disposal of excavated material from existing arch bridge underneath CPR at
Outfall;
l
Placing
levelling stone and bagged concrete to formation of sea wall at Portion E;
l
Installation
of precast sea wall blocks at Portion E;
l Backfilling rockfill and
type II armour behind the seawall blocks at Portion E;
l Disposal of the
excavated soil under the arch bridge to TM38 at Portion E;
l Relocation of type II armour rocks behind the
seawall blocks at Portion E;
l
Cascade and
channel modification concrete structure works at I-1;
l
Construction
of horizontal pipe pile (pipe roofing) for TBM break-through at I-1;
l Pre-bored H-pile
construction for vehicular access at I-1;
l
Drilling,
excavation and rock splitting of man access shaft and vortex drop shaft at I-2;
l
Pipe
jacking at Portion G at I-2;
l
Pre-bored
H-pile construction for skin wall at Portion G at I-2;
l
Construction
of approach channel structure at I-2;
l
Construction
of 750 step channel and catchpit at Portion G at I-2;
l Construction of
drainage works at Portion G at I-2;
l
Preparation
works for blasting at I-2;
l
Drilling,
rock splitting and excavation of vortex shaft at I-3;
l
Construction
of PB wall structure skin wall and copping beam at I-3;
l
Construction
of boulder traps at I-3;
l
Installation
of concrete blocks for temporary bund wall at I-3;
l Tree establishment
works of the transplanted trees at I-3;
l Backfilling for PB Wall, removal of piling
platform and slope reinstatement at I-3; and
l Construction of base slab for approach channel
at I-3.
2.3.1 The environmental mitigation measures that were implemented and their statuses are given in Appendix D.
3.1.1 The EM&A requirements are stipulated in the EM&A Manual. The principal purposes of the EM&A program are to assess the compliance with applicable environmental legislation and associated regulations, to ensure the implementation of mitigation measures specified in the EM&A Manual, and to identify any remedial works necessary for redressing any unacceptable or unanticipated environmental impacts.
3.2 EM&A on Air Quality; Noise and Water Quality
3.2.1
The air
quality, noise and water quality monitoring frequencies and parameters are
shown in Table
3-1.
|
Type of Monitoring |
Monitoring Station ID |
Parameter |
Frequency |
|
Air Quality
Monitoring |
ASR1; ASR3;
ASR8 and ASR9 |
1-hour TSP
(mg/m3) |
Once every 6 days |
|
Air Borne Noise
Monitoring |
NSR1; NSR3;
NSR6; NSR8 and NSR9 |
Leq (30
min.) |
Once every week |
|
Ground Borne
Noise Monitoring |
NSR3 and NSR6 |
Leq (30
min.) |
Once every week |
|
Water Quality
Monitoring |
I-1; I-1-C;
I-2; I-2-C; I-3; I-3-C, O-1(FT), O-1-C(FT), O-1(ET) and O-1-C(ET) |
DO (mg/L) |
Three days per week |
|
SS (mg/L) |
|||
|
Turbidity (NTU) |
|||
|
pH |
|||
|
Temperature (oC) |
Table 3-1 Frequency of Air Quality, Noise and Water Quality Monitoring
3.3.1 The monitoring locations for air quality, noise and water quality are shown in Tables 3-2, 3-3, 3-4 and Appendix E.
|
Monitoring Station ID |
Name of Premises |
Floor Level |
|
ASR1 |
|
G/F |
|
ASR3 |
|
Podium |
|
ASR8 |
|
G/F |
|
ASR9 |
Greenview Terrace (Block 1) |
G/F |
Table 3-2 Air Quality Monitoring Locations
|
Name of Premises |
Floor Level |
|
|
NSR1 |
|
G/F |
|
NSR3 |
|
Podium |
|
NSR6 |
Squatters |
G/F |
|
NSR8 |
|
G/F |
|
NSR9 |
Greenview Terrace (Block 1) |
Podium (up to 6 July 2009) Roof* (from 16 July 2009) |
* The noise monitoring location of NSR9 had been adjusted at rooftop from 16 July 2009.
* Air borne noise monitoring is conducted at all stations.
* Ground borne noise monitoring is conducted at NSR3 and NSR6 only under the requirements stated in the approved EIA Report.
Table 3-3 Noise Monitoring Locations
|
Monitoring Station ID |
Name of Premises |
|
I-1 |
Intake I-1 |
|
I-1-C |
Control of Intake I-1 |
|
I-2 |
Intake I-2 |
|
I-2-C |
Control of Intake I-2 |
|
I-3 |
Intake I-3 |
|
I-3-C^ |
Control of Intake I-3 |
|
O-1
(FT) & (ET) |
Outfall
1During Flood Tide and Ebb Tide |
|
O-1-C (FT)# |
Control of Outfall O-1 During Flood Tide |
|
O-1-C (ET)# |
Control of Outfall O-1 During Ebb Tide |
Note: #Note
that there are two control stations for Outfall O-1; one for sampling during
flood tide and one for sampling during ebb tide. Only one of those control stations for
Outfall O-1 was sampled during each sampling. Control station to be sampled was determined
according to the tidal information provided by the Hong Kong Observatory.
^ The
upper stream location (I-3-C^) had been relocated from the end of February 2009
due to coarse stone blockage.
Table 3-4 Water Quality Monitoring Locations
3.4
Performance Limits (
3.4.1
In
accordance with the EM&A Manual, the appropriate Action and Limit Levels
for air quality, air borne noise, ground borne noise and water quality were
established. They are presented in Table 3-5, Table 3-6, Table 3-7 and
Table
3-8. Should non-compliance
of the air quality, noise and water quality criteria occur, actions in
accordance with the Event / Action Plan stipulated in contract specific
EM&A Manual should be carried out.
|
Station |
1-hr TSP Level in μg/m3 |
|
|
Action Level |
Limit Level |
|
|
ASR1 |
307 |
500 |
|
ASR3 |
327 |
500 |
|
ASR8 |
337 |
500 |
|
ASR9 |
329 |
500 |
Table 3-5 Action & Limit Levels for Air Quality
|
Time Period |
Action |
Limit |
|
0700 – 1900 hrs on normal weekdays |
When one documented complaint is received |
75 dB(A)* |
* For
educational establishments the limit level shall be 70 dB(A) and reduced to 65
dB(A) during examination periods between 0700-1900 hours on normal weekdays.
Table 3-6 Action & Limit Levels for Air Borne Noise
|
Monitoring Station ID |
NSR 3 |
NSR 6 |
|
|
Name of Premises |
Hong Hoi Chee |
Squatters |
|
|
Action Level |
When one
documented complaint is received |
||
|
Limit Level |
Working days during
daytime (0700-1900 hours) (Leq(30min)) |
65 dB(A) |
65 dB(A) |
Table 3-7 Action & Limit Levels for Ground Borne Noise
|
Parameters |
Action |
Limit |
|
DO in mg/L (Surface; Middle & Bottom) |
Surface & Middle 5%-ile of baseline data for surface and
middle layer. Bottom 5%-ile of baseline data for bottom layer. |
Surface & Middle 4 mg/L, except 5 mg/L for Fish Culture
Zone (FCZ) or 1%-ile of baseline data for surface and
middle layer Bottom 2 mg/L or 1%-ile of baseline data for
bottom layer |
|
SS in mg/L (Depth-averaged) |
95%-ile of baseline data or 120% of
upstream control station’s SS at the same tide of the same day |
99%-ile of baseline or 130% of upstream
control station’s SS at the same tide of the same day and specific sensitive
receiver water quality requirements (e.g. required suspended solids levels
for concerned sea water intakes) |
|
Turbidity (Tby) in NTU (Depth-averaged) |
95%-ile of baseline data or 120% of upstream
control station’s Tby at the same tide of the same day |
99%-ile of baseline or 130% of upstream
control station’s Tby at the same tide of the same day |
Notes:
·
For DO,
non-compliance of the water quality limits occurs when monitoring result is
lower than the limits.
·
For SS and
Tby, non-compliance of the water quality limits occurs when monitoring result
is higher than the limits.
· All the figures given in the table are used for reference only and the EPD may amend the figures whenever necessary.
Table 3-8 Action & Limit Levels for Water Quality
|
1-hour TSP (mg/m3) |
Action Level |
Limit Level |
|||
|
Range |
(mg/m3) |
(mg/m3) |
|||
|
ASR1 |
55.5 |
- |
223.4 |
307 |
500 |
|
ASR3 |
64.9 |
- |
231.1 |
327 |
500 |
|
ASR8 |
46.0 |
- |
278.7 |
337 |
500 |
|
ASR9 |
42.6 |
- |
301.0 |
329 |
500 |
Italic indicates the exceedances of Action Levels
Bold indicates the exceedances of Limit Levels
Table 3-9 Summary of Air Quality Monitoring Results
3.5.2 All measured noise monitoring levels were complying with Limit Levels in the reporting period. However, EPD received one public complaint on 30 June 2011 regarding construction dust and daytime construction noise from the Intake I-3 construction site, which triggered the exceedance of action level of air borne noise during the monitoring period. The ET conducted site investigations at Intake I-3 construction site on 8 and 20 July 2011 to review and audit the site setting, mitigation measures implemented on-site and the environmental performance of the Contractor. Noise monitoring at NSR 6 was increased to twice per week from 11 July to 30 July 2011 according to the requirement of EM&A Manual. An investigation report was submitted to EPD in August 2011. The issue of complaint was considered closed. The noise monitoring results would be reported in the Monthly EM&A Report of July 2011.
3.5.3 A summary of noise monitoring results is presented in Table 3-10 and Appendix F.
|
Leq
(30mins) dB(A) |
Limit
Level |
|||
|
Range |
dB(A) |
|||
|
NSR1 |
62 |
- |
66 |
65 / 70 |
|
NSR3 |
61 |
- |
70 |
75 |
|
NSR6 |
58 |
- |
70 |
75 |
|
NSR8 |
64 |
- |
73 |
75 |
|
NSR9 |
66 |
- |
74 |
75 |
Bold indicates
the exceedances of Limit Levels
Table 3-10 Summary of Impact Air Borne Noise Monitoring Results
3.5.4 All measured ground borne noise monitoring levels were complying with Limit Levels in the reporting period. A summary of noise monitoring results is presented in Table 3-11 and Appendix F.
|
Monitoring Station |
Leq
(30mins) dB(A) |
Limit Level |
Chainage of TBM
Covered during the reporting period (m) |
||
|
Range |
dB(A) |
||||
|
NSR6 |
43.9 |
- |
46.5 |
65 |
2991 -
3189 |
Bold
indicates the exceedances of Limit Levels
Table
3-11 Summary of Impact Ground
Borne Noise Monitoring Results
3.5.5
A summary
of water quality monitoring results is presented in Table
3-12 and Appendix F.
3.5.6
None of
exceedance related to project construction activities was recorded during
reporting quarter but a total of 78
non-project related exceedances were recorded.
River Water
Quality Monitoring
3.5.7
A total of 3 non-project related
exceedances were recorded in April 2011 including:
l One
exceedance of SS action level was recorded at I-1 on 8 April 2011. The measured SS level (9.45 mg/L) was above the
baseline action level, but lower than the SS level of the control station (I-1-C)
(10.00 mg/L). General site cleaning, rebar fixing at cascade bay 3, formwork
preparing, removal of masonry wall, pipe roof corning drilling and geotechnical
instrumentation monitoring were undertaken during the measurement. No direct
disturbance was observed from the site. Thus, the exceedance was considered to
be contributed by high SS level of the upstream location and natural variation.
Therefore, no action was required.
l One
exceedance of SS action level was recorded at I-1 on 18 April 2011. The measured SS level (2.70 mg/L) was below the
baseline action level, but higher than 120% of SS level of the control station
(I-1-C) (2.10 mg/L). General site cleaning, formwork at Cascade Bay 3 and 4,
construction of H-pile platform, pipe roof drilling and geotechnical
instrumentation monitoring were undertaken during the measurement. No direct
disturbance was observed from the site. Thus, the exceedance was considered to
be contributed by natural variation and no action was required.
l One exceedance of SS limit level was recorded at I-1 on
6 April 2011. The measured SS level (10.95 mg/L) was above the baseline limit level,
but lower than 120% of SS level of the control station (I-1-C) (10.60 mg/L). General
site cleaning, rebar fixing at cascade bay 1, dismantling of formwork at
vehicle access, removal of hoarding and masonry wall and geotechnical
instrumentation monitoring were undertaken during the measurement. No direct
disturbance was observed from the site. Thus, the exceedance was considered to
be contributed by high SS level at upstream location and natural variation.
Therefore, no action was required.
3.5.8
A total of 3 non-project related
exceedances were recorded in May 2011 including:
l One exceedance of
turbidity limit level was recorded at I-3 on 13 May 2011. The measured
turbidity level (19.08 NTU) was higher than baseline limit level, but lower
than the turbidity level of the control station (I-3-C)(19.19 NTU). General
site cleaning and housekeeping, monitoring of deformation monitoring point
(DMP), drilling and rock breaking in shaft, installation of concrete blocks in
shaft, digging trail pit and breaking of blinding layer at PB wall were
undertaken during measurement. No direct disturbance was observed from the site
and about 33.5 mm rainfall was recorded on the same day. The exceedance was
considered to be contributed by high turbidity level at upstream location and
rainfall. Since the exceedance was non-projected related, no further action was
required.
l One exceedance of SS
limit level was recorded at I-2 on 13 May 2011. The measured SS level
(6.30 mg/L) was lower than baseline action level, but higher than 130% of the
SS level of the control station (I-2-C)(4.10 mg/L). General site cleaning, housekeeping
and temporary traffic arrangement, rock splitting and mucking at vortex drop
shaft, drilling holes for rock splitting, construction of H-pile and excavation
for pipe jacking at Portion G were undertaken during measurement. No direct
disturbance was observed from the site and about 33.5 mm rainfall was recorded
on the same day. The exceedance was considered to be contributed by natural
variation and high rainfall. Since the exceedance was non-projected related, no
further action was required.
l One exceedance of SS
limit level was recorded at I-3 on 13 May 2011. The measured SS level (21.50
mg/L) was higher than baseline limit level, but lower than the SS level of the
control station (I-3-C)(22.15 mg/L). General site cleaning and housekeeping,
monitoring of deformation monitoring point (DMP), drilling and rock breaking in
shaft, installation of concrete blocks in shaft, digging trail pit and breaking
of blinding layer at PB wall were undertaken during measurement. No direct
disturbance was observed from the site and about 33.5 mm rainfall was recorded
on the same day. The exceedance was considered to be contributed by high SS
level at upstream location and rainfall. Since the exceedance was non-projected
related, no further action was required.
3.5.9
A total of 11 non-project related
exceedances were recorded in June 2011 including:
l One exceedance of
turbidity action level was recorded at I-1 on 22 June 2011. The
measured turbidity level (10.57 NTU) was higher than the baseline action level
and slightly higher than the turbidity level of the control station (I-1-C)
(10.56 NTU). General site cleaning, dismantling formwork at Bay 5, 6 and 7,
removal of H-pile platform, formwork at cascade bay 8, temporary traffic
arrangement (TTA) at Shing Mun Road, and geotechnical instrumentation
monitoring were undertaken during measurement. No direct disturbance was
observed from the site. The exceedance was considered to be contributed by high
turbidity level at upstream location and heavy rainfall. Since the exceedance was
non-project related, no further action was required.
l One exceedance of
turbidity limit level was recorded at I-1 on 17 June 2011. The
measured turbidity level (14.79 NTU) was higher than the baseline limit level,
but lower than the turbidity level of the control station (I-1-C)(14.86 NTU).
General site cleaning, dismantling formwork at Bay 5 and 6, filling tie bar
hole in cascade, temporary traffic arrangement (TTA) at Shing Mun Road and
geotechnical instrumentation monitoring were undertaken during measurement. No
direct disturbance was observed from the site. The exceedance was considered to
be contributed by high turbidity level at upstream location and heavy rainfall.
Since the exceedance was non-project related, no further action was required.
l Two exceedances of
turbidity limit level were recorded at I-2 on 17 and 22 June 2011. The
measured turbidity levels (14.31 and 15.19 NTU, respectively) were higher than
the baseline limit level, but lower than the turbidity level of the control
station (I-2-C)(14.54 and 15.49 NTU, respectively). The construction conducted
on 17 June 2011 included general site cleaning, housekeeping and
temporary traffic arrangement (TTA), excavation (rock splitting and mucking) at
vortex drop shaft, drilling, survey check and rock mapping at man access shaft,
excavating the receiving pit at Portion G, and breaking footing of piling
platform and on 22 June 2011 included general site cleaning, housekeeping and
TTA, excavation (drilling holes and rock splitting) at vortex drop shaft, drilling
holes at man access shaft, rock breaking for receiving pit at Portion G slope,
and breaking footing of piling platform and excavation for skin wall. No direct disturbance was observed from the
site. The exceedances were considered to be contributed by high turbidity level
at upstream location and heavy rainfall. Since the exceedance was non-project
related, no further action was required.
l Two exceedances of
turbidity limit level were recorded at I-3 on 17 and 22 June 2011. The measured
turbidity levels (25.75 and 9.08 NTU, respectively) were higher than the
baseline limit level, but lower than the turbidity level of the control station
(I-3-C)(26.05 and 9.20 NTU, respectively). The construction conducted on 17
June 2011 included general site cleaning and
housekeeping, monitoring of de-formation monitoring point (DMP), drilling rock
dowel and splitting holes in shaft, and slope cutting and backfilling at PB
wall and on 22 June 2011 included general site
cleaning and housekeeping, monitoring of DMP, drilling splitting holes and rock
breaking in shaft, curing of planter wall and backfilling, and slope
reinstatement and backfilling at PB wall. No direct disturbance was observed from the
site. The exceedances were considered to be contributed by high turbidity level
at upstream location and heavy rainfall. Since the exceedance was non-project
related, no further action was required.
l Two exceedances of SS
action level were recorded at I-1 on 9 and 17 June 2011. On 9 June 2011, the measured SS level (2.50
mg/L) was lower than the baseline action/limit level, but slightly higher than
120% of SS level of the control station (I-1-C) (2.00 mg/L). General site
cleaning, removing working platform next to Bay 5, formwork at cascade Bay 7,
trimming shotcrete and cutting wire mesh, installation of bracket on spiral
ramp for construction of Shing Mun Road platform and geotechnical
instrumentation monitoring were undertaken during measurement. No direct
disturbance was observed from the site. The exceedance was considered to be
contributed by low SS level at the control station. On 17 June 2011, the
measured SS level (9.65 mg/L) was higher than the baseline action level but
lower than 120% of the SS level of the control station (I-1-C) (9.00 mg/L). General
site cleaning, dismantling formwork at Bay 5 and 6, filling tie bar hole in
cascade, TTA at Shing Mun Road and geotechnical instrumentation monitoring were
undertaken during measurement. No direct disturbance was observed from the
site. The exceedance was considered to be contributed by high SS level at
upstream location and heavy rainfall. Since the exceedances were non-project
related, no further action was required.
l Two exceedances of SS
limit level were recorded at I-2 on 17 and 22 June 2011. The measured
SS levels (8.85 and 14.05 mg/L, respectively) were higher than the baseline
limit level, but former was lower than 120% of the SS level of the control
station and the latter was nearly the same as the SS level of the control
station (I-2-C) (8.75 and 14.00 mg/L, respectively). The construction
activities conducted on 17 June 2011 included general
site cleaning, housekeeping and TTA, excavation (rock splitting and mucking) at
vortex drop shaft, drilling, survey check and rock mapping at man access shaft,
excavating the receiving pit at Portion G, and breaking footing of piling
platform and on 22 June 2011 included general site cleaning, housekeeping and
TTA, excavation (drilling holes and rock splitting) at vortex drop shaft,
drilling holes at man access shaft, rock breaking for receiving pit at Portion
G slope, and breaking footing of piling platform and excavation for skin wall.
No direct disturbance was observed from the site. The exceedances were
considered to be contributed by high SS level at upstream location and heavy
rainfall. Since the exceedances were non-project related, no further action was
required.
l One exceedance of SS
limit level was recorded at I-3 on 17 June 2011. The measured SS level
(18.10 mg/L) was higher than the baseline limit level, but lower than 120% of
the SS level of the control station (I-3-C)(17.75 mg/L). General site cleaning
and housekeeping, monitoring of DMP, drilling rock dowel and splitting holes in
shaft, and slope cutting and backfilling at PB wall were undertaken during
measurement. No direct disturbance was observed from the site. The exceedance
was considered to be contributed by high SS level at upstream location and
heavy rainfall. Since the exceedance was non-project related, no further action
was required.
Marine Water
Quality Monitoring
3.5.10
A total of 3 non-project related
exceedances were recorded in April 2011 including:
l Three exceedances of SS
action levels were recorded at O-1(FT) on 8, 11 and 13 April 2011. The measured
SS levels (depth-averaged) at O-1(FT) (5.35, 5.27 and 3.90 mg/L, respectively)
were below the baseline action/limit level but were higher than 120% of the
control station's SS level (O-1-C(FT)) (4.20, 4.27 and 3.03 mg/L, respectively)
at the same tide of the same day. The construction activities conducted include
laying non-woven geo-textile and backfilling grade 200 rockfill behind
installed seawall blocks on 8 April 2011, installation of temporary concrete
blocks and placing levelling stone on 11 April 2011 and installation of bagged
concrete for seawall formation on 13 April 2011. During monitoring, silt
curtain was deployed along the Portion E boundary line and extended from
seawater level to seabed and floating type silt curtain was also employed at
the inner side. Since there was no other marine works during monitoring, the
exceedances were considered to be contributed by natural variation and no
further action was required.
3.5.11
A total of 21 non-project related
exceedances were recorded in May 2011 including:
l Three exceedances of DO action
levels were recorded at O-1(FT) on 7 and 18 May 2011. The measured DO levels
were below baseline action level. For exceedance on 7 May 2011 (marine surface)
and 18 May 2011 (marine surface), the DO levels (both levels are 6.81 mg/L) are
slightly (about 0.03 mg/L) below the baseline action level. For the exceedance on 18 May 2011 (marine
bottom), the measured DO level (6.98 mg/L) is also slightly (about 0.01 mg/L)
lower than the baseline action level and higher than DO level at the
corresponding control station (6.74 mg/L). The construction activities
conducted on 7 May 2011 include adjusting
level of installed seawall blocks and survey check on installed seawall blocks,
and the construction activities conducted on 18 May 2011 include adjusting
level of installed seawall blocks only.
No other marine works were conducted and no direct disturbance from the
construction site was observed. The exceedances were, therefore, considered as
non-project related. No further action
was required.
l Four exceedances of DO
action levels were recorded at O-1(ET) on 20, 27 and 30 May 2011. For
exceedance on 20 May 2011 (marine surface), the measured DO level (6.99 mg/L) was below the baseline action
level but higher than the marine surface DO level of the control station (6.96
mg/). For exceedances on 27 May (marine mid-depth) and 30 May 2011 (marine
surface and marine mid-depth), the measured DO levels (6.98, 6.97 and 6.94
mg/L, respectively) were slightly lower than the baseline action level and was
lower than DO levels of the corresponding control stations (7.19, 7.09 and 6.98
mg/L, respectively). The construction activities conducted included maintenance
of the inner silt curtain on 20 May 2011, backfilling grade 700 rockfill and
type II armour behind seawall blocks on 27 May 2011, and backfilling type II
armour behind seawall blocks at the eastern side on 30 May 2011. There was no other marine works undertaken
during monitoring and no direct disturbance from the construction site was
observed. The exceedances were, therefore,
considered contributed by natural variation and non-project related. No further action was required.
l Five exceedances of DO
limit levels were recorded at O-1(FT) on 7, 13, 18 and 30 May 2011. For
exceedance on 7 May (marine mid-depth), the measured DO level (6.79 mg/L) was
slightly lower than baseline limit level and was lower than DO level of the
corresponding control station (6.91 mg/L). For exceedances on 7 May (marine
bottom) and 30 May (marine bottom), the measured DO levels (6.91 and 6.95 mg/L,
respectively) were slightly lower than the baseline limit level, but higher
than DO levels of the corresponding control station (6.78 and 6.92 mg/L,
respectively). For exceedances on 13 May (marine bottom) and 18 May (marine
mid-depth), the measured DO levels (6.83 and 6.78 mg/L, respectively) were
lower than the baseline limit level and slightly lower than DO levels of the
corresponding control station (6.89 and 6.79 mg/L, respectively). The
construction activities conducted included adjusting level of installed seawall blocks and survey check
on installed seawall blocks on 7 and 18 May 2011, loading seawall blocks onto
installed seawall blocks and preparation work for geotextile on 13 May 2011,
and backfilling type II armour behind seawall blocks at eastern side on 30 May
2011. There was no other marine works
conducted during monitoring. No direct
disturbance from the construction site was observed. The exceedances were, therefore, considered
contributed by natural variation and non-project related. No further action was required.
l Five exceedances of DO
limit levels were recorded at O-1(ET) on 7, 13 and 20 May 2011. For exceedance
on 7 May 2011 (marine surface and marine mid-depth), the measured DO levels (6.90 and 6.84 mg/L,
respectively) were below the baseline limit level but higher than DO levels of
the corresponding control stations (6.88 and 6.76 mg/L, respectively). For
exceedances on 13 May 2011 (marine surface and marine mid-depth) and 20 May
2011 (marine mid-depth), the measured DO levels (6.90, 6.85 and 6.92 mg/L,
respectively) were slightly lower than the baseline limit level and lower than
DO levels of the corresponding control stations (7.08, 7.01 and 7.07 mg/L,
respectively). The construction activities conducted included adjusting level
of installed seawall blocks and survey check on installed seawall blocks on 7
May 2011, loading seawall blocks onto installed seawall blocks and preparation
work for geotextile on 13 May 2011, and maintenance of the inner silt curtain
on 20 May 2011. There was on other
marine works conducted during monitoring.
No direct disturbance from the construction site was observed. The exceedances were, therefore, considered
contributed by natural variation and non-project related. No further action was required.
l One exceedance of SS
action level was recorded at O-1(FT) on 3 May 2011. The measured SS level
(depth-averaged) (8.45 mg/L) at O-1(FT) was below the baseline action/limit
level but was higher than 120% of the control station's SS level at the same
tide of the same day (6.97 mg/L). Only placing seawall blocks were undertaken
and there was no other marine works conducted during the monitoring. Silt
curtain was deployed along the Portion E boundary line and extended from
seawater level to seabed. Floating type silt curtain was also employed at the
inner side. As such, the exceedance was
considered to be contributed by natural variation and no further action was
required.
l One exceedance of SS action
level was recorded at O-1(ET) on 18 May 2011. The measured SS level (7.02 mg/L)
was below the baseline action level but was slightly higher than 120% of the
measured SS level at the control station (O-1-C(ET))(5.78 mg/L). Adjusting
level of installed seawall blocks was conducted at the Outfall basin (Portion
E) during monitoring and there was no other marine works conducted. As no
direct disturbance from the site was observed and the measured SS level was
relatively low comparing with the baseline action level, the exceedance was
considered to be contributed by natural variation and non-project related.
Therefore, no further action was required.
l One exceedance of SS
limit level was recorded at O-1(FT) on 27 May 2011. The measured SS level (3.10
mg/L) at the monitoring station was well below the baseline action/limit level
but slightly higher than 130% of the SS level of the control station (2.33
mg/L). Backfilling grade 700 rockfill and type II armour behind seawall blocks
was undertaken at the Outfall basin (Portion E) during monitoring. No other
marine works was conducted. No direct disturbance from the site was observed
during monitoring. Therefore, the exceedance was considered to be contributed
by low SS level of the control station and natural variation. Since the
exceedance was non-project related, no further action was required.
l One exceedance of SS
limit level was recorded at O-1(ET) on 20 May 2011. The measured SS level (5.75
mg/L) at the monitoring station was well below the baseline action level but
higher than 130% of the SS level measured at the control station (4.27 mg/L).
Only maintenance of the inner silt curtain was undertaken at the Outfall basin
(Portion E) during monitoring and no other marine works was conducted. No
direct disturbance from the site was observed. Therefore, the exceedance was
considered to be contributed by natural variation and relatively low SS level
at the control station. Since the exceedance was non-project related, no
further action was required.
3.5.12
A total of 37 non-project related
exceedances were recorded in June 2011 including:
l One exceedance of DO
action level was recorded at O-1(FT) (marine mid-depth) on 20 June 2011. The
measured DO level (6.81 mg/L) at the monitoring station was below the baseline
action level and lower than DO level (6.96 mg/L) of the corresponding control
station (about 2.2%). Only re-position of the inner silt curtain and carrying
out fifth shipment of disposal to TM38 were undertaken at the Outfall basin
(Portion E) on the monitoring day. No other marine works was conducted. No
direct disturbance from the site was observed during monitoring. Therefore, the
exceedance was considered to be contributed by natural variation and no further
action was required.
l Three exceedances of DO
action level were recorded at O-1(ET) (marine surface) on 3 and 7 June 2011 and
at O-1(ET) (marine bottom) on 17 June 2011. The measured DO levels (6.97, 6.98
and 6.66 mg/L, respectively) at the monitoring station were below the baseline
action level and lower than DO level of the corresponding control station
(7.20, 7.02 and 6.69 mg/L, respectively).
Details of the construction activities conducted on each monitoring days
are given in Appendix G. Since no direct
disturbance from the site was observed during monitoring, the exceedances were
considered non-project related and no further action was required.
l Three exceedances of DO
action level were recorded at O-1(ET) (marine mid-depth) on 3, 7 and 20 June
2011. The measured DO levels of these three monitoring days were lower than the
baseline action level. On 3 and 20 June 2011, the measured DO levels (6.98 and
6.99 mg/L, respectively) were higher than the DO level of the corresponding
control stations (6.92 and 6.91 mg/l, respectively). On 7 June 2011, the
measured DO level (6.94 mg/L) was lower than the DO level of the corresponding
control station (7.11 mg/L). Details of the construction activities conducted
on each monitoring days are given in Appendix G. Since no direct disturbance
from the site was observed during monitoring, the exceedances were considered
non-project related and no further action was required.
l Five exceedances of DO
limit level were recorded at O-1(FT)(Marine surface) on 15, 17, 20, 27 and 29
June 2011. The measured DO levels (6.70, 6.45 and 6.70 mg/L, respectively) on
15, 17 and 20 were lower than the baseline limit level and lower than the DO
levels of the corresponding control station (6.75, 6.48 and 6.86 mg/L,
respectively). For 27 and 29 June 2011, the measured DO levels (6.74 and 6.78 mg/L,
respectively) were lower than the baseline DO limit level, but higher than the
DO levels of the corresponding control stations (6.69 and 6.58 mg/L,
respectively). Details of the construction activities conducted on each
monitoring days are given in Appendix G. Since no direct disturbance was
observed from the site during monitoring, the exceedances were considered
non-project related. Therefore, no further action was required.
l Two exceedances of DO
limit level were recorded at O-1(FT)(marine mid-depth) on 17 and 29 June 2011.
The measured DO levels (6.50 and 6.68 mg/L, respectively) on 17 and 29 were
lower than the baseline limit level and slightly lower than the DO levels of
the corresponding control station (6.53 and 6.76 mg/L, respectively). Details of
the construction activities conducted on each monitoring days are given in
Appendix G. Since no direct disturbance was observed from the site during
monitoring, the exceedances were considered non-project related. Therefore, no
further action was required.
l Seven exceedances of DO
limit level were recorded at O-1(FT)(marine bottom) on 7, 11, 13, 15, 17, 20
and 29 June 2011. The measured DO levels of these seven monitoring days were
lower than the baseline limit level. On 7, 11, 15, 17 and 29 June 2011, the
measured DO levels (6.94, 6.83, 6.88, 6.60 and 6.79 mg/L, respectively) were
slightly lower than the DO levels of the corresponding control stations (7.08,
6.90, 6.91, 6.67 and 6.80 mg/L, respectively). On 13 June 2011, the measured DO
level (6.89 mg/L) were the same as the corresponding control station. For 20
June 2011, the measured DO level (6.95 mg/L) was higher than the DO level of
the corresponding control station (6.79 mg/L). Details of the construction
activities conducted on each monitoring days are given in Appendix G. Since no
direct disturbance from the site was observed, the exceedances were considered
non-project related and no further action was required.
l Eight exceedances of DO
limit level were recorded at O-1(ET) (marine surface) on 9, 11, 15, 17, 20, 24,
27 and 29 June 2011. The measured DO levels of these eight monitoring days were
lower than the baseline limit level. On 9, 11, 15, and 20 June 2011, the
measured DO levels (6.89, 6.76, 6.76 and 6.80 mg/L, respectively) were lower
than the DO levels of the corresponding control station (7.00, 6.82, 6.83 and
6.86 mg/L, respectively). For 17, 24, 27 and 29 June 2011, the measured DO
levels (6.73, 6.92, 6.89 and 6.82 mg/L, respectively) were higher than the DO
levels of the corresponding control station (6.61, 6.88, 6.82 and 6.70 mg/L).
Details of the construction activities conducted on each monitoring days are
given in Appendix G. Since no direct disturbance from the site was observed,
the exceedances were considered non-project related and no further action was
required.
l Six exceedances of DO
limit level were recorded at O-1(ET) (marine mid-depth) on 1, 11, 15, 17, 27
and 29 June 2011. The measured DO levels of these six monitoring days were
lower than the baseline limit level. On 1, 11, 15, 27 and 29 June 2011, the
measured DO levels (6.93, 6.89, 6.69, 6.82 and 6.72 mg/L, respectively) were
lower than the DO levels of the corresponding control station (7.00, 6.92,
6.77, 6.97 and 6.81 mg/L, respectively). For 17 June 2011, the measured DO level
(6.62 mg/L) was higher than the DO level of the corresponding control station
(6.55 mg/L). Details of the construction activities conducted on each
monitoring days are given in Appendix G. Since no direct disturbance from the
site was observed, the exceedance was considered non-project related and no
further action was required.
l Two exceedances of SS
limit action level were recorded at O-1(ET) (depth-averaged) on 11 and 27 June
2011. The measured SS levels (3.60 and 9.20 mg/L, respectively) at the monitoring
station were below the baseline action/limit, but higher than 130% of the SS
level of the corresponding control station (2.48 and 5.97 mg/L, respectively).
On 11 June 2011, only outer silt
curtain maintenance and repairing was undertaken at the Outfall basin (Portion
E). On 27 June 2011, the derrick barge was unloading the excavated material at
Tuen Mun Area 38. Since no other marine works was conducted, the exceedances
were considered as contributed by natural variation. Therefore, no further action
was required.
3.5.13
The above mentioned exceedances were considered non-project related.
However, proper mitigation measures had been implemented during measurements.
Details of the above mentioned investigations could be referred to the Interim
Notifications of Environmental Quality Limits Exceedances as enclosed in Appendix G.
|
Monitoring Station |
Temperature |
DO (mg/L) |
pH |
Turbidity (NTU) |
Suspended Solid (mg/L) |
||||||||||||||||||||
|
Range |
Range |
Action / Limit Level |
Range |
Range |
Action / Limit Level |
Range |
Action / Limit Level |
||||||||||||||||||
|
I-1 |
19.50 |
- |
31.60 |
6.60 |
- |
7.86 |
3.42 |
/ |
3.34 |
7.05 |
- |
8.74 |
2.05 |
- |
14.79 |
9.75 |
/ |
12.47 |
<2.00 |
- |
10.95 |
8.85 |
/ |
10.17 |
|
|
I-1C |
19.50 |
- |
31.50 |
6.63 |
- |
7.94 |
|
- |
|
7.04 |
- |
8.74 |
2.07 |
- |
14.86 |
|
- |
|
<2.00 |
- |
10.60 |
|
- |
|
|
|
I-2 |
19.70 |
- |
31.30 |
6.62 |
- |
7.60 |
3.66 |
/ |
3.63 |
7.55 |
- |
8.91 |
0.91 |
- |
15.19 |
6.63 |
/ |
6.99 |
<2.00 |
- |
14.05 |
7.68 |
/ |
8.34 |
|
|
I-2C |
19.80 |
- |
31.30 |
6.53 |
- |
7.83 |
|
- |
|
7.55 |
- |
8.90 |
0.99 |
- |
15.49 |
|
- |
|
<2.00 |
- |
14.00 |
|
- |
|
|
|
I-3 |
20.55 |
- |
31.20 |
6.50 |
- |
7.79 |
3.65 |
/ |
3.51 |
7.56 |
- |
10.95 |
1.06 |
- |
25.75 |
3.99 |
/ |
4.18 |
<2.00 |
- |
21.50 |
6.13 |
/ |
7.23 |
|
|
I-3C |
20.50 |
- |
31.05 |
6.54 |
- |
7.91 |
|
- |
|
7.56 |
- |
10.96 |
1.07 |
- |
26.05 |
|
- |
|
<2.00 |
- |
22.15 |
|
- |
|
|
Note: Italic indicates the exceedances of Action Levels
Bold indicates the exceedances of Limit Levels
Table 3-12 Summary of Impact Water Quality Monitoring Results
|
Monitoring |
Temperature |
DO (mg/L) |
pH |
Turbidity (NTU) |
Suspended Solid (mg/L) |
||||||||||||||||||||
|
Range |
Range |
Action / Limit Level |
Range |
Range |
Action / Limit Level |
Range |
Action / Limit Level |
||||||||||||||||||
|
O-1(FT) |
Surface |
19.60 |
- |
31.80 |
6.45 |
- |
7.80 |
6.84
|
/ |
6.81 |
7.87 |
- |
8.70 |
1.13 |
- |
8.71 |
10.35 |
/ |
13.15 |
<2.00 |
- |
13.68 |
14.10 |
/ |
18.08 |
|
Middle |
6.50 |
- |
7.79 |
||||||||||||||||||||||
|
Bottom |
6.60 |
- |
7.93 |
6.99
|
/ |
6.96 |
|||||||||||||||||||
|
O-1-C(FT) |
Surface |
19.77 |
- |
31.83 |
6.48 |
- |
7.71 |
- |
/ |
- |
7.87 |
- |
8.70 |
1.15 |
- |
8.82 |
- |
/ |
- |
<2.00 |
- |
13.12 |
- |
/ |
- |
|
Middle |
6.53 |
- |
7.76 |
||||||||||||||||||||||
|
Bottom |
6.67 |
- |
7.84 |
||||||||||||||||||||||
|
O-1(ET) |
Surface |
19.55 |
- |
31.97 |
6.73 |
- |
7.84 |
7.02
|
/ |
6.94 |
7.91 |
- |
8.70 |
1.22 |
- |
8.56 |
11.87 |
/ |
13.44 |
<2.00 |
- |
9.20 |
13.25 |
/ |
14.39 |
|
Middle |
6.62 |
- |
7.99 |
||||||||||||||||||||||
|
Bottom |
6.66 |
- |
7.75 |
6.70
|
/ |
6.48 |
|||||||||||||||||||
|
O-1-C(ET) |
Surface |
19.43 |
- |
31.93 |
6.61 |
- |
7.84 |
- |
/ |
- |
7.91 |
- |
8.70 |
1.30 |
- |
8.59 |
- |
/ |
- |
<2.00 |
- |
8.78 |
- |
/ |
- |
|
Middle |
6.55 |
- |
7.66 |
||||||||||||||||||||||
|
Bottom |
6.67 |
- |
7.69 |
||||||||||||||||||||||
Note: Italic indicates the exceedances of Action Levels
Bold indicates the exceedances of Limit Levels
Table 3-13 Summary of Impact Marine Water Quality Monitoring Results
3.6 High pH Records at I-3 and I-3-C
3.6.1 As indicated in Table 3-12, relatively high pH values were recorded at I-3 and I-3-C. Same monitoring equipment was used to measure pH values at other monitoring and control stations during the same period and the pH records at these locations were relatively normal.
3.6.2 Although the source of high pH records at I-3 and I-3-C has not been identified, the pH values recorded at these stations on the same monitoring day are consistent. Thus, we considered that these high pH records were non-project related and adverse water quality impact on pH value at I-3 due to the Project was not anticipated.
4 Quarterly Summary; Environmental Condition and Non-Compliance Records
4.1 Summary of Waste Disposal Records
4.1.1 According to the information provided by the Contractor; the quantities of C&D materials in the reporting period are summarized in Table 4-1
|
Status of Waste Management |
April 11 |
May 11 |
June 11 |
|
Inert C&D Material Disposed of to Public Fill at Tuen Mun (m3) |
3,105.4 |
3912.5 |
5,250.3 |
|
Inert C&D Material Reused in this Contract (m3) |
181.0 |
475.0 |
117.5 |
|
Inert C&D Material Reused in other Contract* (m3) |
17,946.7 |
19,530.0 |
16,187.5 |
|
Metals Generated (kg) |
Nil |
Nil |
Nil |
|
Paper / Cardboard Packaging (kg) |
Nil |
Nil |
350.0 |
|
Plastics (kg) |
Nil |
Nil |
Nil |
|
Chemical Waste (kg) |
4,341.4 |
Nil |
1,812.0 |
|
General Waste Disposed of to NENT Landfill (m3) |
34.8 |
52.0 |
34.1 |
* Other Contracts include DC/2007/08,
YL/2009/01, HY/2007/10,HY/2008/09, Wo
Shang Wai, DC/2007/17, CV/2009/14, Tailor Recycle Aggregate, XRL 823A and 823B,
XRL 825, TW 7 and CUHK.
Table 4-1 Waste Generated from April to
June 2011
4.2.1
The weather
conditions during the period from April to June 2011 were mainly sunny, fine, cloudy and rainy.
4.3 Summary of Project-Related Exceedances
4.3.1 Summary of exceedance results are summarized in Table 4-2. Appendix G shows the Interim Notifications of Environmental Quality Limits Exceedances issued in the reporting period.
Environmental Monitoring |
Total No. of Measurement |
Action Level Exceedance |
% of Action Level Exceedance |
Limit Level Exceedance |
% of Limit Level Exceedance |
|
Air
Quality |
204 |
0 |
0 |
0 |
0 |
|
Air Borne Noise |
65 |
1 (complaint) |
1.5 |
0 |
0 |
|
Ground Borne Noise |
2 |
0 |
0 |
0 |
0 |
|
Water |
376 |
0 |
0 |
0 |
0 |
Table 4-2 Summary of Project-
related Exceedances
5.1.1
A complaint
hotline at 9850 3241 of the Contractor has been established for the
Project.
5.1.2
During the
reporting period, one environmental complaint was received. EPD informed ET on 8 July
2011 that one public complaint regarding construction dust and daytime
construction noise from the Intake I-3 construction site was received on 30
June 2011. The ET conducted site investigations at Intake I-3 construction site
on 8 and 20 July 2011 to review and audit the site setting, mitigation measures
implemented on-site and the environmental performance of the Contractor. Noise monitoring at NSR 6 was increased to
twice per week from 11 July to 30 July 2011 according to the requirement of the
EM&A Manual. An investigation report
was submitted to EPD in August 2011. The
issue of complaint was considered closed.
Noise monitoring results would be reported in the Monthly EM&A
Report of July 2011. Details of the complaint investigation and observations can
be referred to Appendix H.
5.1.3
Cumulative
statistics of environmental complaints are shown in Table 5-1.
|
Complaints Received in the Reporting Period |
Cumulative Number of Complaints |
|
1 |
22 |
Table 5-1 Cumulative Statistics of Environmental Complaints
6 Summary of Notification of Summons, Successful Prosecutions and Corrective Actions
6.1.1
No summons
and successful prosecution was received during the reporting period.
6.1.2 Cumulative statistics of Notification of Summon; Successful Prosecutions and Convictions are shown in Table 6-1.
|
Notification of Summons |
Successful Prosecution |
||
|
April –
June 2011 |
Cumulative |
April –
June 2011 |
Cumulative |
|
0 |
0 |
0 |
0 |
Table 6-1 Cumulative Statistics of Notification of Summons and Successful Prosecutions
7 Comments, Recommendations and Conclusion
7.1.1
During the
reporting period, no project related exceedance of air quality monitoring was
recorded. No exceedance of noise limit level was recorded, but EPD
received one noise
complaint on 30 June 2011 that triggered the exceedance of action level.
Finally, exceedances of water
quality monitoring were recorded but none of these exceedances were related to Project’s
construction activities.
7.1.2
During the
reporting period, one environmental complaint was received. EPD informed ET on 8 July 2011 that one public complaint
regarding construction dust and daytime construction noise from the Intake I-3
construction site was received on 30 June 2011. The ET conducted site
investigations at Intake I-3 construction site on 8 and 20 July 2011 to review
and audit the site setting, mitigation measures implemented on-site and the
environmental performance of the Contractor.
Noise monitoring at NSR 6 was increased to twice per week from 11 July
to 30 July 2011. An investigation report
was submitted to EPD in August 2011. The issue of complaint was considered
closed. The noise monitoring results
would be reported in the Monthly EM&A Report of July 2011.
7.1.3
No
Notification of Summons has been received since the commencement of the
Project.
7.1.4
Waste
management mitigation measures have been implemented by the Contractor within
the reporting period. Waste figures
during the reporting period are summarized in Table 7-1.
|
Status of Waste Management |
Quantity |
|
Inert C&D Material Disposed of to Public Fill
at Tuen Mun (m3) |
12,268.2 |
|
Inert C&D Material
Reused in this Contract (m3) |
773.5 |
|
Inert C&D Material Reused in other Contract*
(m3) |
53,664.2 |
|
Metals Generated (kg) |
Nil |
|
Paper / Cardboard Packaging (kg) |
350.0 |
|
Plastics (kg) |
Nil |
|
Chemical Waste (kg) |
6,153.4 |
|
General Waste Disposed of to NENT Landfill (m3) |
120.9 |
*
Other Contracts include DC/2007/08, YL/2009/01,
HY/2007/10,HY/2008/09, Wo Shang Wai,
DC/2007/17, CV/2009/14, Tailor Recycle Aggregate, XRL 823A and 823B, XRL 825,
TW 7 and CUHK.
Table 7-1 Total
Wastes Generated From April to June 2011
|
|
|
|
|
Site Map and Works Area |
|
|
|
|
|
Organization Chart |
|
|
|
|
|
Works Programme |
|
|
|
|
|
Implementation Status of Environmental Mitigation Measures |
|
|
|
|
|
Monitoring Locations |
|
|
|
|
|
Monitoring Results |
|
|
|
|
|
Interim Notifications of Environmental Quality Limits Exceedances |
|
|
|
|
|
Complaint Log |