Enhancement Works for Kwun Tong Sewage Pumping Station

To cater for future development of East Kowloon, the Drainage Services Department (DSD) will enhance the Kwun Tong Sewage Pumping Station (KTSPS), which is situated near Kwun Tong Bypass and Wai Yip Street. The enhancement works have commenced in late 2017 and are scheduled for completion in end 2022. This newsletter provides the latest information on the progress of construction and related information of the project.

Construction Sequence of the Project

Item Status
Enclosure of Site Area

Completed

Ground Investigation Completed
Diversion of Underground Utilities Completed
Construction of Piles and Foundation In progress
Construction of ELS and Excavation for Balancing Tank In progress
Construction of Balancing Tank and its Associated Facilities  
Construction of Landscaped Deck  
Installation of Ventilation System and Deodorization Facilities  
Construction of the Connecting Roads and the Ancillary Works  
Testing of Associated E&M Equipment  
Beautification of Landscaped Deck and Installation of Playground Facilities  
Testing & Commissioning  

Open to Public

What is Excavation and Lateral Support (ELS) System?

The photo above shows part of the ELS works.

The lateral support system could provide support to the soil adjacent to the excavated area, so that the underground facilities such as pile caps and basement can be constructed within the excavated area. The construction of lateral support system mainly includes:-

  • Construction of king post & installation of sheet piles
  • Installation of waling
  • Grouting to prevent groundwater ingress if necessary

The ELS system we are setting up will be used for constructing the underground balancing tank with 12 meters depth. The whole ELS system requires about 9 months to a year for completion.

The construction of the lateral support system for balancing tank are in progress. The photo above shows the preparation works for the welding of sheet piles.

The construction of the lateral support system for balancing tank are in progress. The photo above shows the preparation works for the welding of sheet piles.

The photos above show the driving, welding and testing of sheet piles.

The photos above show the driving, welding and testing of sheet piles.

The photos above show the driving, welding and testing of sheet piles.

Engaging our Neighbours

The project team of DSD and the engineering consultants introduced the project to committee members of Save Our Urban Parks Alliance and the Chairman and Vice Chairman of Laguna City (Phase 1, 2 & 4) in early March 2019 and obtained their views towards the project.

The project team of DSD and the engineering consultants introduced the project to committee members of Save Our Urban Parks Alliance and the Chairman and Vice Chairman of Laguna City (Phase 1, 2 & 4) in early March 2019 and obtained their views towards the project.

The project team of DSD and the engineering consultants introduced the project to committee members of Save Our Urban Parks Alliance and the Chairman and Vice Chairman of Laguna City (Phase 1, 2 & 4) in early March 2019 and obtained their views towards the project.

The project team of DSD and the engineering consultants introduced the project to committee members of Save Our Urban Parks Alliance and the Chairman and Vice Chairman of Laguna City (Phase 1, 2 & 4) in early March 2019 and obtained their views towards the project.