



|
APPENDICES |
|
|
Appendix A Site
Map and Works Area
Appendix D Implementation
Status of Environmental Mitigation Measures
Appendix E Monitoring
Locations
Appendix G Interim
Notifications of Environmental Quality Limits Exceedances
|
TABLES |
|
|
Table 3-1 Frequency of Air
Quality, Noise and Water Quality Monitoring
Table 3-2 Air
Quality Monitoring Locations
Table 3-3 Noise
Monitoring Locations
Table 3-4 Water
Quality Monitoring Locations
Table 3-5 Action
& Limit Levels for Air Quality
Table 3-6 Action
& Limit Levels for Noise
Table 3-7 Action
& Limit Levels for Water Quality
Table 3-8 Summary
of Air Quality Monitoring Results
Table 3-9 Summary
of Impact Noise Monitoring Results
Table 3-10 Summary
of Impact Water Quality Monitoring Results
Table 3-11 Summary
of Impact Marine Water Quality Monitoring Results
Table 4-1 Waste Generated from October to December 2010
Table 4-2 Summary of Project- related Exceedances
Table 5-1 Cumulative Statistics
of Environmental Complaints
Table 6-1 Cumulative
Statistics of Notification of Summons and Successful Prosecutions
Table 7-1
Total Wastes Generated from
October to December 2010
1
This
quarterly EM&A summary report under the Main Contract for the Design and
Construction of Tsuen Wan Drainage Tunnel (hereafter referred to as the
“Project”) to Maeda-CREC-SELI Joint Venture (MCSJV), which summarises the
findings of environmental impact monitoring works during the period from
October to December 2010.
2
Noise
monitoring was performed at five monitoring stations (NSR1, NSR3, NSR6, NSR8
and NSR9). Air quality monitoring was
carried out at four monitoring stations (ASR1, ASR3, ASR8 and ASR9). Water quality monitoring was carried out at
four monitoring stations (Intake I-1, Intake I-2, Intake I-3 and Outfall O-1).
Noise level was measured in terms of Leq, L10 and L90 (30min). Air quality was measured in terms of 1-hour
Total Suspended Particulates (TSP). Water quality was measured in terms of
Temperature, pH, Dissolved Oxygen (DO), Turbidity (Tby) and Suspended Solid
(SS).
3
Details of
all monitoring stations are summarized in the below table.
|
Type of Monitoring |
Monitoring Station ID |
Name of Premises |
Status of Monitoring Works during the Reporting Period |
|
Air
Quality Monitoring |
ASR1 |
Sik
Sik Yuen Ho Fung College |
Ongoing |
|
ASR3 |
Hong
Hoi Chee Hong Temple |
Ongoing |
|
|
ASR8 |
Beach
Tower (Long Beach Gardens) |
Ongoing |
|
|
ASR9 |
Greenview
Terrace (Block 1) |
Ongoing |
|
|
Noise
Monitoring |
NSR1 |
Sik
Sik Yuen Ho Fung College |
Ongoing |
|
NSR3 |
Hong
Hoi Chee Hong Temple |
Ongoing |
|
|
NSR6 |
Squatters |
Ongoing |
|
|
NSR8 |
Beach
Tower (Long Beach Gardens) |
Ongoing |
|
|
NSR9 |
Greenview
Terrace (Block 1) |
Ongoing |
|
|
Water
Quality Monitoring |
I-1 |
Intake
I-1 |
Ongoing |
|
I-2 |
Intake
I-2 |
Ongoing |
|
|
I-3 |
Intake
I-3 |
Ongoing |
|
|
O-1
|
Outfall
O-1 |
Ongoing
|
4 The major construction activities undertaken by the Contractor during the period from October to December 2010 include site cleaning and tidying at I-1, I-2, I-3 and outfall; drilling, excavation and rock splitting of spiral ramp at outfall; pre-bored H-pile drilling and soil nailing for Castle Peak Road (CPR) open excavation at outfall; tunnel boring machine (TBM) drilling of the tunnel and mucking out of tunnel spoil at outfall; marine dredging works for basin scheme at Portion E; drilling and excavation of vortex shaft at I-3; temporary rock dowel drilling and installation at I-3; construction of skin wall at I-3; excavation of man access shaft and vortex drop shaft at I-2; pipe jacking at Portion G at I-2; pile caps construction for temporary platform at Portion G at I-2; cascade and channel modification concrete structure works at I-1; horizontal drilling at I-1; removal of sea wall and amour rock for basin scheme at Portion E; construction of pre-bored H-Pile for PB wall at I-3; preparation work for retaining wall at I-2; construction of footing for erecting the tower crane at I-3; drilling, excavation and rock splitting of man access shaft and vortex drop shaft at I-2; construction of approach channel structure at I-2; erection of temporary steel platform for H-pile wall at Portion G at I-2; and backfilling of spiral ramp centre void at I-1.
5 No open construction activities were carried out during restricted hours in the reporting period. Only mining works and probe drilling were conducted during restricted hours in this reporting period.
6 No project related exceedances of air quality and water quality monitoring was recorded. No exceedance of noise limit level was recorded, but EPD receives two complaints on construction noise which trigger the exceedance of noise action level. The below table summarizes the exceedances of air quality, noise and water quality in the reporting period.
|
Parameter |
Action Level Exceedance |
Limit Level Exceedance |
|
Air |
Nil |
Nil |
|
Noise |
Two complaints received on 17 Nov 2010 at NSR 9 |
Nil |
|
DO |
One
record on 1 Nov 2010 at O-1(FT)(Surface) |
Two
records on 27 Oct and 3 Nov 2010 at
O-1(FT)(Surface) Three
records on 27 Oct, 1 Nov and 3 Nov 2010
at O-1(FT)(Middle) Four
records on 25 Oct, 27 Oct, 1 Nov and 3 Nov 2010 at O-1(FT)(Bottom) Two
records on 27 Oct and 29 Oct 2010 at
O-1(ET)(Surface) Two
records on 25 Oct and 27 Oct 2010 at
O-1(ET)(Middle) One
records on 27 Oct 2010 at
O-1(ET)(Bottom) |
|
Turbidity |
One record on 5 Nov
2010 at I-1 |
Two
records on 15 Oct and 5 Nov 2010 at
I-2 One
record on 15 Oct 2010 at I-3 One
record on 25 Oct 2010 at O-1(FT) One
record on 8 Nov 2010 at O-1(ET) |
|
SS |
Three
records on 20 Oct, 5 Nov and 1 Dec 2010 at I-1 Two
records on 15 Oct and 31 Dec 2010 at I-2 Three
records on 27 Oct, 3 Dec and 22 Dec 2010 at O-1(FT) Three
records on 29 Oct, 10 Nov and 24 Dec 2010 at O-1(ET) |
Four
records on 13 Oct, 22 Oct, 27 Oct and 8 Nov 2010 at I-1 Six
records on 13 Oct, 3 Nov, 5 Nov, 17 Nov, 6 Dec and 24 Dec 2010 at I-2 One
record on 24 Dec 2010 at I-3 Nine
records on 25 Oct, 5 Nov, 19 Nov, 22 Nov, 24 Nov, 26 Nov, 1 Dec, 15 Dec and
29 Dec 2010 at O-1(FT) Nine
records on 25 Oct, 27 Oct, 5 Nov, 8 Nov, 12 Nov, 15 Nov, 13 Dec, 15 Dec and
29 Dec 2010 at O-1(ET) |
7 Waste figures during the reporting period are summarized in the table below.
|
Status of Waste Management |
|
|
Inert C&D Material Disposed of to Public Fill
at Tuen Mun (m3) |
24,652.4 |
|
Inert C&D Material
Reused in this Contract (m3) |
675.0 |
|
Inert C&D Material Reused in other Contract*
(m3) |
16,085.0 |
|
Metals Generated (kg) |
18.0 |
|
Paper / Cardboard Packaging (kg) |
400.0 |
|
Plastics (kg) |
20.0 |
|
Chemical Waste (kg) |
10,762.2 |
|
General Waste Disposed of to NENT Landfill (m3) |
131.8 |
* Other Contracts include DC/2007/08,
DC/2008/12, YL/2009/01, HY/2007/10, DC/2007/17 and Wo Shang Wai.
8 During the reporting period, two environmental complaints were received. EPD received two public complaints regarding daytime construction noise from outfall construction site on 17 November 2010. The complaints were about barge squeaking and rock breaking. The ET have conducted site inspection at the Outfall construction site and the Greenview Terrace (NSR 9) on 2 and 17 December 2010 to review and audit the site setting, noise mitigation measures implemented on-site and the environmental performance of the contractor. Enhanced on-site noise mitigation measures have been implemented by the contractor. A noise investigation report was submitted to the EPD on 24 December 2010. The issue of noise complaints was considered closed.
9
No
Notification of Summons was received since the commencement of the Project.
1.1.1
The
Drainage Services Department (DSD) proposes to construct a tunnel of an
internal diameter of 6.5m and length 5.13km, with the purpose to alleviate the
flooding risk in Tsuen Wan and Kwai Chung.
1.1.2
This
project is a Designated Project under Schedule 2 Part I Category Q, of the
Environmental Impact Assessment Ordinance (EIAO) as part of the proposed Tsuen
Wan Drainage Tunnel (TWDT) passes underneath the existing Tai Mo Shan Country
Park. An Environmental Impact Assessment
(EIA) Study has therefore been undertaken to provide information on the nature
and extent of environmental impacts arising from the construction and operation
of the proposed designed project and related activities taking place
concurrently. From the EIA the
recommendations for monitoring contained herein, are made.
1.1.3
The Maeda-CREC-SELI
Joint Venture (MCSJV) was awarded by DSD with
the Contract – Design and Construction of Tsuen Wan Drainage Tunnel.
1.1.4
Hyder was
commissioned by the MCSJV as the ET to implement an EM&A program in
accordance with the EM&A Manual. The
proposed tunnel section flows from the junction of Shing Mun Road and Wo Yi Hop
Road and discharges to south of Yau Kom Tau underneath Castle Peak Road as
shown in Appendix A.
1.1.5 The construction works of the Project commenced in January 2008. This is the eleventh quarterly EM&A report summarising the impact monitoring results and audit findings of the EM&A program during the reporting period between October and December 2010.
2.1 Project Organization and Management Structure
2.1.1 The organization chart and lines of communication with respect to the on-site environmental management are shown in Appendix B.
2.2.1
It is
anticipated that the overall project programme from the detail design to
completion of all civil works shall take approximately 54 months. The construction programme is presented in
Appendix C.
2.2.2
The major
construction activities undertaken in the reporting quarter are:
· Site cleaning and tidying at I-1, I-2, I-3 and outfall;
· Drilling, excavation and rock splitting of spiral ramp at outfall;
· Pre-bored H-pile drilling and soil nailing for CPR open excavation at outfall;
· Tunnel boring machine (TBM) drilling of the tunnel and mucking out of tunnel spoil at outfall;
· Marine dredging works for basin scheme at Portion E;
· Drilling and excavation of vortex shaft at I-3;
· Temporary rock dowel drilling and installation at I-3;
· Construction of skin wall at I-3;
· Excavation of man access shaft and vortex drop shaft at I-2;
· Pipe jacking at Portion G at I-2;
· Pile caps construction for temporary platform at Portion G at I-2;
· Cascade and channel modification concrete structure works at I-1;
· Horizontal drilling at I-1;
· Removal of sea wall and amour rock for basin scheme at Portion E;
· Construction of pre-bored H-Pile for PB wall at I-3;
· Preparation work for retaining wall at I-2;
· Construction of footing for erecting the tower crane at I-3;
· Drilling, excavation and rock splitting of man access shaft and vortex drop shaft at I-2;
·
Construction
of approach channel structure at I-2;
·
Erection of
temporary steel platform for H-pile wall at Portion G at I-2; and
·
Backfilling of spiral ramp centre void at I-1.
2.3.1 The environmental mitigation measures that were implemented and their statuses are given in Appendix D.
3.1.1 The EM&A requirements are stipulated in the EM&A Manual. The principal purposes of the EM&A program are to assess the compliance with applicable environmental legislation and associated regulations; to ensure the implementation of mitigation measures specified in the EM&A Manual; and to identify any remedial works necessary for redressing any unacceptable or unanticipated environmental impacts.
3.2 EM&A on Air Quality; Noise and Water Quality
3.2.1
The air
quality, noise and water quality monitoring frequencies and parameters are
shown inTable
3-1.
|
Type of Monitoring |
Monitoring Station ID |
Parameter |
Frequency |
|
Air Quality
Monitoring |
ASR1; ASR3;
ASR8 and ASR9 |
1-hour TSP |
Once every 6 days |
|
Noise
Monitoring |
NSR1; NSR3;
NSR6; NSR8 and NSR9 |
Leq (30 min.) |
Once every week |
|
Water Quality
Monitoring |
I-1; I-1-C;
I-2; I-2-C; I-3; I-3-C, O-1(FT), O-1-C(FT), O-1(ET) and O-1-C(ET) |
DO (mg/l) |
Three days per week |
|
SS (mg/l) |
|||
|
Turbidity (NTU) |
|||
|
pH |
|||
|
Temperature (oC) |
Table 3-1 Frequency of Air Quality, Noise and Water Quality Monitoring
3.3.1 The monitoring locations for air quality, noise and water quality are shown in Tables 3-2, 3-3, 3-4 and Appendix E.
|
Monitoring Station ID |
Name of Premises |
Floor Level |
|
ASR1 |
|
G/F |
|
ASR3 |
|
Podium |
|
ASR8 |
|
G/F |
|
ASR9 |
Greenview Terrace (Block 1) |
G/F |
Table 3-2 Air Quality Monitoring Locations
|
Name of Premises |
Floor Level |
|
|
NSR1 |
|
G/F |
|
NSR3 |
|
Podium |
|
NSR6 |
Squatters |
G/F |
|
NSR8 |
|
G/F |
|
NSR9 |
Greenview Terrace (Block 1) |
Podium (up to 6 July 2009) Roof* (from 16 July 2009) |
* The noise monitoring location of NSR9 had been adjusted at rooftop from 16 July 2009.
Table 3-3 Noise Monitoring Locations
|
Monitoring Station ID |
Name of Premises |
|
I-1 |
Intake I-1 |
|
I-1-C |
Control of Intake I-1 |
|
I-2 |
Intake I-2 |
|
I-2-C |
Control of Intake I-2 |
|
I-3 |
Intake I-3 |
|
I-3-C^ |
Control of Intake I-3 |
|
O-1
(FT) & (ET)* |
Outfall
1During Flood Tide and Ebb Tide |
|
O-1-C (FT)*# |
Control of Outfall O-1 During Flood Tide |
|
O-1-C (ET)*# |
Control of Outfall O-1 During Ebb Tide |
Note: *Water
quality monitoring will be undertaken when the construction of the outfall basin at the
seashore is started.
#Note that there are two control stations for
Outfall O-1; one for sampling during flood tide and one for sampling during ebb
tide. Only one of those control stations
for Outfall O-1 shall be sampled during each sampling. Control station to be sampled will be determined
according to the tidal information provided by the Hong Kong Observatory.
^ The
upper stream location (I-3-C^) had been relocated from the end of February 2009
due to coarse stone blockage.
Table 3-4 Water Quality Monitoring Locations
3.4
Performance Limits (
3.4.1
In
accordance with the EM&A Manual; the appropriate Action and Limit Levels
for air quality, noise and water quality were established and are presented in Table 3-5, Table 3-6 and Table 3-7. Should non-compliance of the air quality,
noise and water quality criteria occur, actions in accordance with the Event /
Action Plan stipulated in contract specific EM&A Manual should be carried
out.
|
Station |
1-hr TSP Level in μg/m3 |
|
|
Action Level |
Limit Level |
|
|
ASR1 |
307 |
500 |
|
ASR3 |
327 |
500 |
|
ASR8 |
337 |
500 |
|
ASR9 |
329 |
500 |
Table 3-5 Action & Limit Levels for Air Quality
|
Time Period |
Action |
Limit |
|
0700 – 1900 hrs on normal weekdays |
When one documented complaint is received |
75 dB(A)* |
* For
educational establishments the limit level shall be 70dB(A) and reduced to 65dB(A)
during examination periods between 0700-1900 hrs on normal weekdays.
Table 3-6 Action & Limit Levels for Noise
|
Parameters |
Action |
Limit |
|
DO in mg/L (Surface; Middle & Bottom) |
Surface & Middle 5%-ile of baseline data for surface and
middle layer. Bottom 5%-ile of baseline data for bottom layer. |
Surface & Middle 4mg/l except 5mg/l for Fish Culture Zone
(FCZ) or 1%-ile of baseline data for surface and
middle layer Bottom 2mg/l or 1%-ile of baseline data for
bottom layer |
|
SS in mg/L (Depth-averaged) |
95%-ile of baseline data or 120% of
upstream control station’s SS at the same tide of the same day |
99%-ile of baseline or 130% of upstream control
station’s SS at the same tide of the same day and specific sensitive receiver
water quality requirements (e.g. required suspended solids levels for
concerned sea water intakes) |
|
Turbidity (Tby) in NTU (Depth-averaged) |
95%-ile of baseline data or 120% of
upstream control station’s Tby at the same tide of the same day |
99%-ile of baseline or 130% of upstream
control station’s Tby at the same tide of the same day |
Notes:
·
For DO,
non-compliance of the water quality limits occurs when monitoring result is
lower than the limits.
·
For SS and
Tby, non-compliance of the water quality limits occurs when monitoring result
is higher than the limits.
· All the figures given in the table are used for reference only and the EPD may amend the figures whenever it is considered as necessary.
Table 3-7 Action & Limit Levels for Water Quality
3.5.1 All measured air quality monitoring levels were complying with the Action and Limit Levels in the reporting period. A summary of air quality monitoring results is presented in Table 3-103-8 and Appendix F.
|
1-hour TSP (mg/m3) |
Action Level |
Limit Level |
|||
|
Range |
(mg/m3) |
(mg/m3) |
|||
|
ASR1 |
35.5 |
- |
253.8 |
307 |
500 |
|
ASR3 |
24.1 |
- |
277.0 |
327 |
500 |
|
ASR8 |
30.4 |
- |
257.5 |
337 |
500 |
|
ASR9 |
28.5 |
- |
312.6 |
329 |
500 |
Italic indicates the exceedances of Action Levels
Bold indicates the exceedances of Limit Levels
Table 3-8 Summary of Air Quality Monitoring Results
3.5.2 All measured noise monitoring levels were complying with Limit Levels in the reporting period. However, EPD received two noise complaints on 17 November 2010 that triggered the exceedances of action level during the reporting period. Investigation including site inspection, review and audit of noise mitigation measures implemented on-site and the Contractor’s environmental performance has been undertaken. Reports, including the nature of the complaints, observation of site inspections, proposed action taken and any further mitigation measures necessary to alleviate the impact, were submitted to EPD.
3.5.3 A summary of noise monitoring results is presented in Table 3-9 and Appendix F.
|
Leq
(30mins) dB(A) |
Limit
Level |
|||
|
Range |
dB(A) |
|||
|
NSR1 |
63 |
- |
69 |
65/70 |
|
NSR3 |
59 |
- |
71 |
75 |
|
NSR6 |
55 |
- |
71 |
75 |
|
NSR8 |
60 |
- |
70 |
75 |
|
NSR9 |
63 |
- |
72 |
75 |
Bold indicates
the exceedances of Limit Levels
Table 3-9 Summary of Impact Noise Monitoring Results
3.5.4
A summary
of water quality monitoring results is presented in Table
3-10 and Appendix F.
3.5.5 None of exceedance related to project construction activities was recorded during reporting quarter but a total of 61 non project related exceedances were recorded.
River Water
Quality Monitoring
3.5.7
A total of 7 non project related exceedances were recorded in October
2010 including:
·
Two exceedances of turbidity (baseline) Limit Level
were recorded at I-2 and I-3 on 15 October 2010. The measured turbidity levels on both cases
were above the baseline Limit Level.
Higher turbidity levels were recorded at the upstream control stations
(I-2-C and I-3-C). On site mitigation
measures had been implemented during the construction and direct disturbance of
construction works was not observed from the sites. As such, the exceedances were considered to
be contributed by natural variation and no further action was required.
·
Four exceedances of SS Limit Level were recorded on
13, 22 and 27 at I-1 and I-2 and one exceedance of SS Action Level was recorded
on 20 October 2010 at I-2. The measured
SS levels at the impact monitoring stations were either 20% (Action Level) or
30% (Limit Level) more than the corresponding measurement results of the
upstream control stations (I-1-C and I-2-C), where low SS levels were measured
(between 2 mg/L and 2.9 mg/L). The SS results on these days were within the
range of baseline SS concentration (1 - 8.5 mg/L). Since direct disturbance of construction
works was not observed from the construction sites at I-1 and I-2 and suitable
mitigation measures had been implemented, the exceedances were considered to be
contributed by natural variation. No
further action was required.
·
Another exceedance of SS Action Level was recorded
on 15 October 2010 at I-2. The measured
SS level at the impact monitoring station was higher than 95 percentile of the
baseline data. Higher SS level was
measured at the upstream control station I-2-C. Since direct disturbance of construction
works was not observed from the construction site at I-2 and suitable
mitigation measures had been implemented, the exceedances were considered to be
contributed by natural variation and the wet weather on that day (about 3.9 mm
of rainfall were recorded at the Hong Kong Observatory on 15 October
2010). No further action was required.
3.5.7
A total of 7 non project related exceedances were recorded in November
2010 including:
·
An exceedance of turbidity Action Level was
recorded at I-1 on 5 November 2010. The measured turbidity level (10.45 NTU)
was above baseline Action Level, but it was lower than the turbidity level
measured at the upstream control station I-1-C (10.89 NTU). General site cleaning and housekeeping,
dismantle formwork for Bay 19 spiral ramp, erection of formwork for Bay 22 and
23 spiral ramp, and horizontal drilling were undertaken during measurement. No
direct disturbance was observed from the site and the turbidity result at
monitoring station was below the level of control station. Thus, the exceedance
was considered to be contributed by natural variation and no action was
required.
·
An exceedance of turbidity Limit Level was
recorded at I-2 on 5 November 2010. The
measured turbidity level (13.61 NTU) was above the Baseline Limit level. However, it was lower than the turbidity
level measured at the upstream control station I-2-C (14.33 NTU). Construction activities including general
site cleaning and housekeeping, excavation (hole drilling) at vortex drop
shaft, excavation (rock splitting and mucking) at man access shaft, preparation
work for skin wall, pipe jacking (rock breaking for 13th jacking pipe) at
Portion G, and dismantling formwork for pile caps were undertaken during
measurement. No direct disturbance was
observed from the site. Thus, the
exceedance was considered to be due to natural variation and no action was
required.
·
An exceedance of SS Limit Level was recorded
at I-2 on 3 November 2010. The measured SS level (2.90 mg/L) was below the
baseline Action / Limit Level and was within the range of baseline SS
concentration (1 - 8.5 mg/L). It was
higher than the SS level measured at upstream control station I-2-C (2.0
mg/L). General site cleaning and
housekeeping, install wire mesh and shotcreting at vortex drop shaft,
excavation (hole drilling) at man access shaft, preparation work for skin wall,
erect steel frame for ventilation system at 20T gantry, pipe jacking (rock
breaking for 12th jacking pipe) at Portion G, and erect formwork and rebar
fixing of pile caps at Portion G were undertaken during the measurement. No direct disturbance was observed from the
site. Thus, the exceedance was considered to be contributed by natural
variation and no action was required.
·
An exceedance of SS Action Level was recorded
at I-1 on 5 November 2010. The measured SS level (4.10 mg/L) was below the
baseline Action Level. It was also
within the range of baseline SS concentration (1 - 10.5 mg/L), but was higher
than the SS level measured at upstream control station I-2-C (3.35 mg/L). General site cleaning and housekeeping,
dismantle formwork for Bay 19 spiral ramp, erection of formwork for Bay 22 and
23 spiral ramp and horizontal drilling were undertaken during measurement. No direct disturbance was observed from the
site. As such, the exceedance was
considered to be contributed by natural variation and no action was required.
·
An exceedance of SS Limit Level was recorded
at I-2 on 5 November 2010. The measured SS level (11.80 mg/L) was above the
baseline Action / Limit Level. However, the measured SS level was below 120% of
the control station’s (I-2-C) SS level (10.80 mg/L). General site cleaning and
housekeeping, excavation (drilling holes and mucking) at vortex drop shaft,
excavation (rock splitting and mucking) at man access shaft, preparation for
skin wall, erect platform for air compressor,
pipe jacking (rock breaking for 13th jacking pipe) at Portion
G, dismantle formwork for pile caps at Portion G were undertaken during
measurement. No direct disturbance was
observed from the site. Thus, the
exceedance was considered to be contributed by natural variation and no action
was required.
·
An exceedance of SS Limit Level was recorded
at I-1 on 8 November 2010. The measured SS level (3.35 mg/L) was below the
baseline Action Level. It was also
within the range of baseline SS concentration (1 - 10.5 mg/L), but was higher
than the SS level measured at the upstream control station I-1-C (2.40
mg/L). General site cleaning and
housekeeping, general cleaning at Bay 21 spiral ramp, dismantle formwork for
Bay 22 spiral ramp, rebar fixing for Bay 23 spiral ramp, and horizontal
drilling were undertaken during measurement. No direct disturbance was observed
from the site. Hence, the exceedance was
considered to be contributed by natural variation and no action was required.
·
An exceedance of SS Limit Level was recorded
at I-2 on 17 November 2010. The
measured SS level (4.05 mg/L) was below the baseline Action / Limit Level and
within the range of baseline SS concentration (1 - 8.5 mg/L). However, it was more than 130% of the SS
level measured at the upstream control station I-2-C (2.00 mg/L). General site cleaning and housekeeping,
excavation (drilling holes and rock splitting) at vortex drop shaft, excavation
(drilling holes) at man access shaft, preparation for skin wall, erection of
the noise enclosure for ventilation fan, pipe jacking (rock breaking for the
14th jacking pipe) at Portion G, pipe jacking (jacking for the 13th concrete
pipe) at Portion G, and erection of the 60-tonne temporary steel platform at
Portion G were undertaken during measurement.
No direct disturbance was observed from the site. Thus, the exceedance was considered to be
contributed by natural variation and no action was required.
3.5.8
A total of 5 non project related exceedances were recorded in December
2010 including:
·
An exceedance of SS Action Level was recorded
at I-1 on 1 December 2010. The measured SS level (2.70 mg/L) was below the
baseline Action / Limit Level and was within the range of baseline SS
concentration (1 – 10.5 mg/L). It was
higher than the SS level measured at upstream control station I-1-C (2.20
mg/L). General site cleaning and housekeeping, rebar fixing at Bay 23, formwork
at Bay 23, horizontal drilling and GI monitoring were undertaken during measurement. No direct disturbance was observed from the
site. Thus, the exceedance was
considered to be contributed by natural variation and no action was required.
·
An exceedance of SS Limit Level was recorded
at I-2 on 6 December 2010. The measured
SS level (3.20 mg/L) was below baseline Action / Limit Level and within the
range of baseline SS concentration (1 - 8.5 mg/L), but was more than 130% of
the SS level measured at the upstream control station (I-2-C)(2.00 mg/L).
General site cleaning and housekeeping, excavation (drilling holes) at vortex
drop shaft, excavation (drilling holes) at man access shaft, rock breaking for
jacking pipe at Portion G and erection of 60 ton temporary steel platform at
Portion G were undertaken during measurement.
No direct disturbance was observed from the site. Thus, the exceedance was considered to be
contributed by natural variation and no action was required.
·
An exceedance of SS Limit Level was recorded
at I-2 on 24 December 2010. The measured SS level (3.05 mg/L) was below
baseline Action / Limit Level and within the range of baseline SS concentration
(1 - 8.5 mg/L) but was more than 130% of the SS level measured at the upstream
control station (I-2-C) (2.10 mg/L). General site cleaning and housekeeping, excavation
(drilling holes) at vortex drop shaft and excavation (drilling holes) at man
access shaft, rock breaking for 16th jacking pipe at Portion G,
erection of 60 ton temporary steel platform at Portion G and excavation for 750
step channel (SC) and catchpit were undertaken during measurement. No direct disturbance was observed from the
site. Thus, the exceedance was considered to be contributed by natural
variation and no action was required.
·
An exceedance of SS Limit Level was recorded
at I-3 on 24 December 2010. The measured SS level (4.15 mg/L) was below
baseline Action / Limit Level and within the range of baseline SS concentration
(1 - 7.5 mg/L) but was more than 130% of the SS level measured at the upstream
control station (I-3-C) (2.00 mg/L). General site cleaning and housekeeping, PB
wall H-pile extension, approach channel extension, and shaft excavation were
undertaken during measurement. No direct
disturbance was observed from the site.
Thus, the exceedance was considered to be contributed by natural
variation and no action was required.
· An exceedance of SS Action Level was recorded at I-2 on 31 December 2010. The measured SS level (2.45 mg/L) was below baseline Action / Limit Level and within the range of baseline SS concentration (1 - 8.5 mg/L) but was more than 120% of the SS level measured at the upstream control station (I-2-C) (2.00 mg/L). General site cleaning, housekeeping and temporary traffic arrangement (TTA), excavation (drilling holes) at vortex drop shaft, excavation (drilling holes and rock spilling) at man access shaft, closed formwork for dry flow channel, rock breaking for 16th jacking pipe at Portion G, erection of 60 ton temporary steel platform at Portion G and excavation for 750 step channel (SC) and catchpit were undertaken during measurement. No direct disturbance was observed from the site. Thus, the exceedance was considered to be contributed by natural variation and no action was required.
Marine Water
Quality Monitoring
3.5.9
A total of 16 non project related exceedances were recorded in October
2010 including:
·
Four exceedances at O-1(FT) and five exceedances at
O-1(ET) of DO baseline Limit Level were recorded on 25, 27 and 29 October 2010.
·
Marine buoys and silt curtains were set up on 25 and
27 October 2010 and there was no dredging on these two days. As such, the eight
exceedances of DO baseline limit on 25 and 27 October 2010 were considered due
to natural variation.
·
An exceedance of surface DO limit level was
recorded at O-1(ET) (6.75 mg/L) during the ebb tide on 29 October 2010 (in contrast to the DO level of 7.44 mg/L measured at the upstream
control station O-1-C(ET) during the same tide). During monitoring, silt curtains were
deployed at the construction site and marine dredging was conducted within
these curtains. Thus, any
impact upon DO level associated with pollutants released from the marine
sediment during dredging would only be confined within the construction
site. As such, the surface DO exceedance
at O-1(ET) was considered to be contributed by natural variation. No further action was required.
·
An exceedance of
turbidity baseline Limit Level was recorded on 25 October 2010 at O-1(FT)
(14.13 NTU). High turbidity level was
also recorded at the upstream control station O-1-C(FT) on the same tide of 25
October 2010 (13.77 NTU). As no marine
dredging was conducted on that day, the exceedance was considered to be
contributed by natural variation. No action
was required.
·
Three
exceedances of SS Limit Level were recorded on 25 October 2010 at O-1(FT) and
O-1(ET), and on 27 October 2010 at O-1(ET).
Another exceedance of SS Action Level was recorded on 27 October 2010 at
O-1(FT). As there were no dredging works
undertaken in these two days, the exceedances were considered to be contributed by natural variation.
·
An exceedance of SS
Action Level was recorded on
29 October 2010 at O-1(ET). The SS level
measured at O-1(ET) was 13.33 mg/L, which was more than 95 percentile of the
baseline data. In contrast, higher SS level
(17.15 mg/L) was recorded at the upstream control station at O-1-C(ET) on 29
October 2010. While marine dredging was
undertaken at the outfall basin on the same day, mitigation measures had been
adopted, including:
Silt curtains
deployed along the dredging boundary line and extended from the seawater level
to the bottom of seabed;
Frame-type silt
curtain deployed for the marine mud dredging at the derrick barge;
Closed grab dredging
confined within the frame type silt curtain;
Daily dredging rate limited
to a maximum 960 m3;
Silt curtain with
sufficient slack to ensure the curtain rested on the seabed to cope with waves
and tides.
The condition of the
silt curtains was checked by the supervisor on-broad per working day to ensure
proper implementation and functioning prior to any marine works activities.
·
Having considered the
good forms of silt curtains and measures to limit SS generation, any SS
dispersion was localised and limited within the construction site. Thus, the exceedance was considered to be
contributed by natural variation. No
further action was required.
3.5.10
A total of 17 non project related exceedances were recorded in November
2010 including:
·
An exceedance of DO Action Level was recorded
at the surface layer of O-1(FT) on 1 November 2010. The measured DO level (6.83
mg/L) was just below the baseline Action Level (6.84 mg/L). Dredging was conducted at the Outfall basin
(portion E) on 1 November 2010. During
monitoring, silt curtains were deployed along the dredging boundary line and
extended from the seawater level to the seabed.
Frame-type silt curtain had also been employed at the derrick barge and
all dredging operation was confined in the frame-type silt curtain. Thus, any impact upon DO level
associated with pollutants released from the marine sediment during dredging
would only be confined within the construction site. As such, the exceedance was considered to be
contributed by natural variation. No
further action was required.
·
Five exceedances of DO
Limit Level were recorded at middle and bottom layers on 1 November and at
surface, middle and bottom layers on 3 November 2010 respectively at O-1(FT). The
measured DO levels (that varied from 6.51 to 6.70 mg/L) were below the baseline
Action / Limit Level of the corresponding layer. (In contrast, the corresponding DO levels
measured at the upstream control station O-1-C(FT) varied from 6.74 to 7.18
mg/L). Dredging was conducted at the
Outfall basin (portion E) on both 1 and 3 November 2010. During monitoring, silt curtains were deployed
along the dredging boundary line and extended from the seawater level to the
seabed. Frame-type silt curtain had also
been employed at the derrick barge and all dredging operation was confined in
the frame-type silt curtain. Thus, any impact upon DO level
associated with pollutants released from the marine sediment during dredging
would only be confined within the construction site. As such, the
exceedances were considered to be contributed by natural variation. No further action was required.
·
An exceedance of Turbidity
Limit Level was recorded at O-1(ET) on 8 November 2010. The measured SS level
(depth-averaged) (14.28 NTU) at O-1(ET) was above the baseline Action/Limit
Level but below the control station's SS level (O-1-C(ET)) (14.41 NTU) at the
same tide of the same day. Dredging was
undertaken at Portion E on 8 November 2010.
Silt curtains had been deployed along the dredging boundary line and
extended from the seawater level to the seabed.
Frame-type silt curtain had been employed at the derrick barge and all
dredging operation was confined in the frame-type silt curtain. As such, the exceedance was considered to be
contributed by natural variation (high background level of SS) and no further
action was required.
·
Five exceedances of SS Limit
Level were recorded on 5, 19, 22, 24 and 26 November 2010 at O-1(FT). The measured SS
levels (varied from 8.83 to 12.42 mg/L) were below the baseline Action/Limit
Level but was higher than 130% of the control station's SS level (O-1-C(FT))
(varied from 6.67 to 9.28 mg/L) at the same tide of the same day. No marine dredging activity was undertaken on
5 and 19 November 2010 and only rock removal at Portion E was undertaken on 22
and 24 November 2010. For 26 November
2010, rock removal at Portion E and installation of noise insulation blanket
next to wire drums were undertaken. Silt
curtains had been provided along Portion E boundary line and extended from
seawater level to the bottom of seabed during the marine works. Frame / floating type silt curtains had also
been employed at the derrick barge, and rock removal operation was confined in
the inner (frame / floating type) silt curtain. As such, the exceedances were considered to
be contributed by natural variation and no further action was required.
·
Four exceedances of
SS Limit Level were records on 5, 8, 12 and 15 November 2010 at O-1(ET). The measured SS
levels (depth-averaged) (varied from 14.42 to 23.20 mg/L) were above the
baseline Action / Limit Level. However, the measured SS levels
were below the control station's SS level on 12
November 2010 (19.35 mg/L), below 120% of the control station's SS level on 5
and 8 November 2010 (13.23 and 22.00 mg/L respectively) and below 130% of the
control station’s SS level on 15 November 2010 (11.72 mg/L). Since there was no dredging activity
undertaken on 5 and 15 November 2010, the exceedances were considered not
related to the construction activities.
During the marine works on 8 November 2010 (dredging at Portion E) and
12 November 2010 (rock removal),
mitigation measures had been implemented on-site. These included silt curtains provided along
Portion E boundary line and extended from seawater level to the bottom of
seabed, and frame / floating type silt curtains employed at the derrick
barge. Dredging and rock removal
operation were confined in the inner (frame / floating type) silt curtain. As such, the exceedances were considered to
be contributed by natural variation and no further action was required.
·
An exceedance of SS Action Level was recorded on 10 November 2010. The
measured SS level (depth-averaged) (13.72 mg/L) at O-1(ET) was between the
baseline Action Level and the Limit Level, and was below the control station's
SS level (at O-1-C(ET)) (15.78 mg/L) at the same tide of the same day. Marine dredging was undertaken at the Outfall
basin (Portion E) on 10 November 2010.
Silt curtains had been deployed along the dredging boundary line and
extended from the seawater level to the seabed.
Frame-type silt curtain had been employed at the derrick barge and all
dredging operation was confined in the frame-type silt curtain. As such, the exceedance was considered to be
contributed by natural variation (high background level of suspended solids)
and no further action was required.
3.5.11
A total of 9 non project related exceedances were recorded in December
2010 including:
·
Two exceedances of SS Action Level were recorded on 3 and 22 December 2010
at O-1(FT). The measured SS levels (7.38 and 12.95 mg/L respectively) were below the
baseline Action/Limit Level but was higher than 120% of the control station's
SS level (O-1-C(FT)) (6.13 and 10.40 mg/L respectively) at the same tide of the
same day. Only rock removal at Portion E
on 3 December 2010 and armour rock removal from the sea wall to the derrick
barge at Portion E on 22 December 2010 were undertaken during measurement. Silt
curtains had been provided along Portion E boundary line and extended from
seawater level to the bottom of seabed during the marine works. Frame / floating type silt curtains had also
been employed at the derrick barge, and rock removal operation was confined in
the inner (frame / floating type) silt curtain. As such, the exceedances were
considered to be contributed by natural variation and no further action was
required.
·
Three exceedances of
SS Limit Level were recorded on 1, 15 and 29 December 2010 at O-1(FT). The
measured SS levels (varied from 3.20 to 7.83 mg/L) were below the baseline
Action / Limit Level but higher than 130%
of the control station's SS level (O-1-C(FT)) (varied from 2.37 to 5.28 mg/L)
at the same tide of the same day. Only rock-fill removal from sea bed was
undertaken on 1 December 2010 and no marine dredging activities were undertaken
on 15 and 29 December 2010. As silt curtains were provided along Portion E boundary
line and extended from seawater level to the bottom of seabed, frame / floating
type silt curtains were deployed at the derrick barge, and dredging / rock
removal operation were confined in the inner (frame / floating type) silt
curtain. As such, the exceedances were
considered to be contributed by natural variation and no further action was
required.
·
An exceedance of SS Action Level was recorded on 24 December 2010. The
measured SS level (depth-averaged) (9.82 mg/L) at O-1(ET) was below the baseline
Action/Limit Level but higher than 120% of the control station's SS level
(O-1-C(ET)) (7.87 mg/L) at the same tide of the same day. No marine works was
undertaken during measurement. As silt
curtains had been deployed along the dredging boundary line and extended from
the seawater level to the seabed and floating type silt curtain had been
employed at the inner side, the exceedance was considered to be contributed by
natural variation and no further action was required.
·
Three exceedances of
SS Limit Level were recorded on 13, 15 and 29 December 2010. The measured SS levels
(depth-averaged) (9.20, 5.53 and 9.07 mg/L respectively) were below the
baseline Action and Limit Level but higher than 130% of the control station's
SS level (O-1-C(ET)) (5.18, 3.97 and 6.03 mg/L respectively) at the same tide
of the same day. No marine works were undertaken on 13, 15 and 29 December
2010. As such, the exceedances were considered to be contributed by natural
variation and no further action was required.
3.5.12 The above mentioned exceedances were considered not project related. However, proper mitigation measures had been implemented during measurements. Details of the above mentioned investigations could be referred to the Interim Notifications of Environmental Quality Limits Exceedances as enclosed in Appendix G.
|
Monitoring Station |
Temperature |
DO (mg/L) |
pH |
Turbidity (NTU) |
Suspended Solid (mg/L) |
||||||||||||||||||||
|
Range |
Range |
Action
/ Limit Level |
Range |
Range |
Action
/ Limit Level |
Range |
Action
/ Limit Level |
||||||||||||||||||
|
I-1 |
17.20 |
- |
29.70 |
5.05 |
- |
8.06 |
3.42 |
/ |
3.34 |
7.50 |
- |
8.91 |
2.39 |
- |
10.45 |
9.75 |
/ |
12.47 |
2.00 |
- |
7.45 |
8.85 |
/ |
10.17 |
|
|
I-1C |
17.40 |
- |
29.80 |
5.08 |
- |
8.50 |
|
- |
|
7.52 |
- |
8.90 |
2.48 |
- |
10.89 |
|
- |
|
2.00 |
- |
6.25 |
|
- |
|
|
|
I-2 |
17.00 |
- |
29.50 |
4.92 |
- |
7.90 |
3.66 |
/ |
3.63 |
7.62 |
- |
8.87 |
1.20 |
- |
13.61 |
6.63 |
/ |
6.99 |
2.00 |
- |
11.80 |
7.68 |
/ |
8.34 |
|
|
I-2C |
17.10 |
- |
29.50 |
5.11 |
- |
8.27 |
|
- |
|
7.61 |
- |
8.88 |
1.25 |
- |
14.33 |
|
- |
|
2.00 |
- |
11.20 |
|
- |
|
|
|
I-3 |
17.00 |
- |
29.35 |
5.02 |
- |
7.90 |
3.65 |
/ |
3.51 |
7.60 |
- |
8.90 |
1.23 |
- |
7.80 |
3.99 |
/ |
4.18 |
2.00 |
- |
6.05 |
6.13 |
/ |
7.23 |
|
|
I-3C |
16.90 |
- |
29.60 |
5.09 |
- |
8.26 |
|
- |
|
7.56 |
- |
8.91 |
1.30 |
- |
7.88 |
|
- |
|
2.00 |
- |
6.20 |
|
- |
|
|
Note: Italic indicates the exceedances of Action Levels
Bold indicates the exceedances of Limit Levels
Table 3-10 Summary of Impact Water Quality Monitoring Results
|
Monitoring |
Temperature |
DO (mg/L) |
pH |
Turbidity (NTU) |
Suspended Solid (mg/L) |
||||||||||||||||||||
|
Range |
Range |
Action / Limit Level |
Range |
Range |
Action / Limit Level |
Range |
Action / Limit Level |
||||||||||||||||||
|
O-1(FT) |
Surface |
17.67 |
- |
27.10 |
5.50 |
- |
7.63 |
6.84 |
/ |
6.81 |
7.93 |
- |
8.32 |
2.82 |
- |
14.13 |
10.35 |
/ |
13.15 |
2.67 |
- |
21.65 |
14.10 |
/ |
18.08 |
|
Middle |
5.88 |
- |
7.65 |
||||||||||||||||||||||
|
Bottom |
5.87 |
- |
7.89 |
6.99 |
/ |
6.96 |
|||||||||||||||||||
|
O-1-C(FT) |
Surface |
17.58 |
- |
26.83 |
5.62 |
- |
7.67 |
- |
/ |
- |
7.87 |
- |
8.33 |
3.01 |
- |
13.77 |
- |
/ |
- |
2.33 |
- |
24.32 |
- |
/ |
- |
|
Middle |
5.76 |
- |
7.62 |
||||||||||||||||||||||
|
Bottom |
5.93 |
- |
7.66 |
||||||||||||||||||||||
|
O-1(ET) |
Surface |
17.45 |
- |
26.53 |
6.01 |
- |
7.72 |
7.02 |
/ |
6.94 |
7.93 |
- |
8.35 |
2.92 |
- |
14.28 |
11.87 |
/ |
13.44 |
5.07 |
- |
23.20 |
13.25 |
/ |
14.39 |
|
Middle |
6.26 |
- |
7.71 |
||||||||||||||||||||||
|
Bottom |
6.24 |
- |
7.70 |
6.70 |
/ |
6.48 |
|||||||||||||||||||
|
O-1-C(ET) |
Surface |
16.92 |
- |
26.67 |
5.96 |
- |
7.79 |
- |
/ |
- |
7.97 |
- |
8.40 |
2.90 |
- |
14.41 |
- |
/ |
- |
3.97 |
- |
22.00 |
- |
/ |
- |
|
Middle |
6.05 |
- |
7.76 |
||||||||||||||||||||||
|
Bottom |
5.46 |
- |
7.72 |
||||||||||||||||||||||
Note: Italic indicates the exceedances of Action Levels
Bold indicates the exceedances of Limit Levels
Table 3-11 Summary of Impact Marine Water Quality Monitoring Results
3.6 DO, Temperature and pH Data Monitored on 29 November 2010 and 1 December 2010
3.6.1 The previous calibration certificate for the multimeter
(for pH, temperature and DO measurements) was expired on 27 November 2010 and
the multimeter was recalibrated on 3 December 2010. Therefore, the water
quality data (pH, temperature and DO) collected on 29 November 2010 and 1 Dec
2010 were not covered under a valid calibration certificate of the
multimeter. Although the recalibration of the multimeter on 3 December
2010 indicated that the multimeter was functioning normally within acceptable
deviations, it is considered that the water quality data (pH, temperature and
DO) measured on 29 November 2010 and 1 December 2010 shall be considered for
reference only. Nevertheless, it is noted that the pH, temperature
and DO data monitored at various stations on 29 November 2010 are similar to
the values measured on 26 November 2010 and on 1 December 2010 are similar to
the values measured on 3 December 2010. Effluent discharges from the
construction sites at I-1, I-2 and I-3 have been controlled under the wastewater
discharge licenses. Mitigation measures were deployed at various
construction sites during monitoring. These included: (1) silt curtains
for marine works (rock removal) at the marine basin of Outfall; (2) wastewater
treatment plants at I-1, I-2 and I-3; (3) diversion of existing streams that
were bunded by sealed concrete block walls at I-1, I-2 and I-3; and (4) bunded
off the existing stream by sand bag to prevent washing out of excavated
material from the working area at I-2. Thus, adverse water quality impact
on DO at various stations due to the Project on 29 November 2010 and 1 December
2010 was not anticipated.
3.7 Turbidity Data Monitored on 24 December 2010
3.7.1 The previous calibration certificate for the turbidimeter
(serial no. 215619) was expired on 24 December 2010 and the turbidimeter was
recalibrated on 28 December 2010. Therefore, the turbidity data collected
on 24 December were not covered under a valid calibration certificate of the
turbidimeter. The recalibration of the turbidimeter on 28 December 2010
indicated that the turbidimeter was functioning normally within acceptable
deviations. However, the turbidity data measured on 24 December 2010 should be
considered for reference only.
3.7.2 The turbidity levels measured at various control stations were higher than the turbidity level of the corresponding impact stations on 24 December 2010. Four-point on-site calibration of the turbidimeter was conducted before subsequent measurements and, thus, all measurements on 24 December 2010 were based on same calibration curve. The higher turbidity levels at control stations (where the water qualities were not affected by the project) and the relatively lower turbidity levels of the impact stations (where water qualities were or were not affected by the Project) showed that the Project did not contribute any significant adverse impact on the turbidity levels at the various impact monitoring stations.
3.7.3 In addition, effluent discharges from the construction sites at I-1, I-2 and I-3 have been controlled under the wastewater discharge licenses and mitigation measures were deployed at various construction sites during monitoring, including: (1) silt curtains for marine works (rock removal) at the marine basin of Outfall; (2) wastewater treatment plants at I-1, I-2 and I-3; and (3) diversion of existing streams that were bunded by sealed concrete block walls at I-1, I-2 and I-3, so the water quality of various locations are under sufficient protection. Therefore, adverse water quality impact on turbidity at various monitoring stations due to the Project on 24 December 2010 was not anticipated.
4 Quarterly Summary; Environmental Condition and Non-Compliance Records
4.1 Summary of Waste Disposal Records
4.1.1 According to the information provided by the Contractor; the quantities of C&D materials in the reporting period are summarized in Table 4-1
|
Status of Waste Management |
October 10 |
November 10 |
December 10 |
|
Inert C&D Material Disposed of to Public Fill at Tuen Mun (m3) |
5,386 |
6,581.8 |
12,684.6 |
|
Inert C&D Material Reused in this Contract (m3) |
65 |
15.0 |
595.0 |
|
Inert C&D Material Reused in other Contract* (m3) |
6,700 |
4430.0 |
4,955.0 |
|
Metals Generated (kg) |
Nil |
Nil |
18.0 |
|
Paper / Cardboard Packaging (kg) |
Nil |
Nil |
400.0 |
|
Plastics (kg) |
Nil |
Nil |
20.0 |
|
Chemical Waste (kg) |
2,392.0 |
920.0 |
7,450.2 |
|
General Waste Disposed of to NENT Landfill (m3) |
34.6 |
41.2 |
56.0 |
* Other
Contracts include DC/2007/08, DC/2008/12, YL/2009/01, HY/2007/10, DC/2007/17
and Wo Shang Wai.
Table 4-1 Waste Generated from October to
December 2010
4.2.1 The weather conditions during the period from October to December 2010 were mainly sunny, fine, cloudy and rainy.
4.3 Summary of Project-Related Exceedances
4.3.1 Summary of exceedance results are summarized in Table 4-2. Appendix G shows the Interim Notifications of Environmental Quality Limits Exceedances issued in the reporting period.
|
Environmental Monitoring |
Total No. of Measurement |
Action Level Exceedance |
% of Action Level Exceedance |
Limit Level Exceedance |
% of Limit Level Exceedance |
|
Air Quality |
192 |
0 |
0 |
0 |
0 |
|
Noise |
67 |
2 (complaints) |
2.99 |
0 |
0 |
|
Water |
350 |
0 |
0 |
0 |
0 |
Table 4-2 Summary of Project- related
Exceedances
5.1.1
A complaint
hotline at 9850 3241 of the Contractor has been established for the
Project.
5.1.2
During the
reporting period, two environmental complaints were received. EPD received two public complaints regarding daytime
construction noise from outfall construction site on 17 November 2010. The complaints were about barge squeaking and
rock breaking. The ET have conducted
site inspection at the Outfall construction site and the Greenview Terrace (NSR
9) on 2 and 17 December 2010 to review and audit the site setting, noise mitigation
measures implemented on-site and the environmental performance of the
contractor. Enhanced on-site noise mitigation measures were implemented by the
contractor. A noise investigation report was submitted to the EPD on 24
December 2010. The issue of noise complaints was considered closed. Details of the complaint investigation and observations can
be referred to Appendix H.
5.1.3
Cumulative
statistics of environmental complaints are shown in Table 5-1.
|
Complaints Received in the Reporting Period |
Cumulative Number of Complaints |
|
2 |
20 |
Table 5-1 Cumulative Statistics of Environmental Complaints
6 Summary of Notification of Summons, Successful Prosecutions and Corrective Actions
6.1.1
No summons
and successful prosecution was received during the reporting period.
6.1.2 Cumulative statistics of Notification of Summon; Successful Prosecutions and Convictions are shown in Table 6-1.
|
Notification of Summons |
Successful Prosecution |
||
|
October – December 10 |
Cumulative |
October – December 10 |
Cumulative |
|
0 |
0 |
0 |
0 |
Table 6-1 Cumulative Statistics of Notification of Summons and Successful Prosecutions
7 Comments, Recommendations and Conclusion
7.1.1 During the reporting period, no project related exceedance of air quality monitoring was recorded. No exceedance of noise limit level was recorded, but EPD received two noise complaints on 17 November 2010 that triggered the exceedances of action level. Finally, Exceedances of water quality monitoring were recorded but none of these exceedances were related to Project’s construction activities.
7.1.2 EPD received two public complaints regarding daytime construction noise from outfall construction site on 17 November 2010. The complaints were about barge squeaking and rock breaking. The ET have conducted site inspection at the Outfall construction site and the Greenview Terrace (NSR 9) on 2 and 17 December 2010 to review and audit the site setting, noise mitigation measures implemented on-site and the environmental performance of the contractor. Enhanced on-site noise mitigation measures have been implemented by the contractor. A noise investigation report was submitted to the EPD on 24 December 2010. The issue of noise complaints was considered closed.
7.1.3
No
Notification of Summons has been received since the commencement of the
Project.
7.1.4
Waste
management mitigation measures have been implemented by the Contractor within
the reporting period. Waste figures
during the reporting period are summarized in Table 7-1.
|
Status of Waste Management |
|
|
Inert C&D Material Disposed of to Public Fill
at Tuen Mun (m3) |
24,652.4 |
|
Inert C&D Material
Reused in this Contract (m3) |
675.0 |
|
Inert C&D Material Reused in other Contract*
(m3) |
16,085.0 |
|
Metals Generated (kg) |
18.0 |
|
Paper / Cardboard Packaging (kg) |
400.0 |
|
Plastics (kg) |
20.0 |
|
Chemical Waste (kg) |
10,762.2 |
|
General Waste Disposed of to NENT Landfill (m3) |
131.8 |
* Other Contracts include DC/2007/08, DC/2008/12,
YL/2009/01, HY/2007/10, DC/2007/17 and Wo Shang Wai.
Table 7-1 Total Wastes Generated From October to December 2010
|
|
|
|
|
Site Map and Works Area |
|
|
|
|
|
Organization Chart |
|
|
|
|
|
Work Programme |
|
|
|
|
|
Implementation Status of Environmental Mitigation Measures |
|
|
|
|
|
Monitoring Locations |
|
|
|
|
|
Monitoring Results |
|
|
|
|
|
Interim Notifications of Environmental Quality Limits Exceedances |
|
|
|
|
|
Complaint Log |