APPENDICES

Appendix A            Site Map and Works Area

Appendix B            Organization Chart

Appendix C            Works Programme

Appendix D            Implementation Status of Environmental Mitigation Measures

Appendix E            Monitoring Locations

Appendix F             Monitoring Results

Appendix G            Interim Notifications of Environmental Quality Limits Exceedances

Appendix H            Complaint Log

 

TABLES

Table 3-1      Frequency of Air Quality, Noise and Water Quality Monitoring

Table 3-2      Air Quality Monitoring Locations

Table 3-3      Noise Monitoring Locations

Table 3-4      Water Quality Monitoring Locations

Table 3-5      Action & Limit Levels for Air Quality

Table 3-6      Action & Limit Levels for Noise

Table 3-7      Action & Limit Levels for Water Quality

Table 3-8      Summary of Air Quality Monitoring Results

Table 3-9      Summary of Impact Noise Monitoring Results

Table 3-10    Summary of Impact Water Quality Monitoring Results

Table 3-11    Summary of Impact Marine Water Quality Monitoring Results

Table 4-1      Waste Generated from October to December 2010

Table 4-2      Summary of Project- related Exceedances

Table 5-1      Cumulative Statistics of Environmental Complaints

Table 6-1      Cumulative Statistics of Notification of Summons and Successful Prosecutions

Table 7-1      Total Wastes Generated from October to December 2010

 


Executive Summary

1    This quarterly EM&A summary report under the Main Contract for the Design and Construction of Tsuen Wan Drainage Tunnel (hereafter referred to as the “Project”) to Maeda-CREC-SELI Joint Venture (MCSJV), which summarises the findings of environmental impact monitoring works during the period from October to December 2010.

2    Noise monitoring was performed at five monitoring stations (NSR1, NSR3, NSR6, NSR8 and NSR9).  Air quality monitoring was carried out at four monitoring stations (ASR1, ASR3, ASR8 and ASR9).  Water quality monitoring was carried out at four monitoring stations (Intake I-1, Intake I-2, Intake I-3 and Outfall O-1). Noise level was measured in terms of Leq, L10 and L90 (30min).  Air quality was measured in terms of 1-hour Total Suspended Particulates (TSP). Water quality was measured in terms of Temperature, pH, Dissolved Oxygen (DO), Turbidity (Tby) and Suspended Solid (SS).

3    Details of all monitoring stations are summarized in the below table.

Type of Monitoring

Monitoring Station ID

Name of Premises

Status of Monitoring Works during the Reporting Period

Air Quality Monitoring

ASR1

Sik Sik Yuen Ho Fung College

Ongoing

ASR3

Hong Hoi Chee Hong Temple

Ongoing

ASR8

Beach Tower (Long Beach Gardens)

Ongoing

ASR9

Greenview Terrace (Block 1)

Ongoing

Noise Monitoring

NSR1

Sik Sik Yuen Ho Fung College

Ongoing

NSR3

Hong Hoi Chee Hong Temple

Ongoing

NSR6

Squatters

Ongoing

NSR8

Beach Tower (Long Beach Gardens)

Ongoing

NSR9

Greenview Terrace (Block 1)

Ongoing

Water Quality Monitoring

I-1

Intake I-1

Ongoing

I-2

Intake I-2

Ongoing

I-3

Intake I-3

Ongoing

O-1

Outfall O-1

Ongoing

 

4    The major construction activities undertaken by the Contractor during the period from October to December 2010  include site cleaning and tidying at I-1, I-2, I-3 and outfall; drilling, excavation and rock splitting of spiral ramp at outfall; pre-bored H-pile drilling and soil nailing for Castle Peak Road (CPR) open excavation at outfall; tunnel boring machine (TBM) drilling of the tunnel and mucking out of tunnel spoil at outfall; marine dredging works for basin scheme at Portion E; drilling and excavation of vortex shaft at I-3; temporary rock dowel drilling and installation at I-3; construction of skin wall at I-3; excavation of man access shaft and vortex drop shaft at I-2; pipe jacking at Portion G at I-2; pile caps construction for temporary platform at Portion G at I-2; cascade and channel modification concrete structure works at I-1; horizontal drilling at I-1; removal of sea wall and amour rock for basin scheme at Portion E; construction of pre-bored H-Pile for PB wall at I-3; preparation work for retaining wall at I-2; construction of footing for erecting the tower crane at I-3; drilling, excavation and rock splitting of man access shaft and vortex drop shaft at I-2; construction of approach channel structure at I-2; erection of temporary steel platform for H-pile wall at Portion G at I-2; and backfilling of spiral ramp centre void at I-1.

5    No open construction activities were carried out during restricted hours in the reporting period.  Only mining works and probe drilling were conducted during restricted hours in this reporting period.

6    No project related exceedances of air quality and water quality monitoring was recorded. No exceedance of noise limit level was recorded, but EPD receives two complaints on construction noise which trigger the exceedance of noise action level. The below table summarizes the exceedances of air quality, noise and water quality in the reporting period.

 Parameter

Action Level Exceedance

Limit Level Exceedance

Air

Nil

Nil

Noise

Two complaints received on 17 Nov 2010 at NSR 9

Nil

DO

One record on 1 Nov 2010 at O-1(FT)(Surface)

Two records on 27 Oct and 3 Nov 2010  at O-1(FT)(Surface)

Three records on 27 Oct, 1 Nov and 3 Nov 2010  at O-1(FT)(Middle)

Four records on 25 Oct, 27 Oct, 1 Nov and 3 Nov 2010 at O-1(FT)(Bottom)

Two records on 27 Oct and 29 Oct 2010  at O-1(ET)(Surface)

Two records on 25 Oct and 27 Oct 2010  at O-1(ET)(Middle)

One records on 27 Oct 2010  at O-1(ET)(Bottom)

Turbidity

One record on 5 Nov 2010  at I-1

Two records on 15 Oct and 5 Nov 2010  at I-2

One record on 15 Oct  2010 at I-3

One record on 25 Oct  2010 at O-1(FT)

One record on 8 Nov  2010 at O-1(ET)

SS

Three records on 20 Oct, 5 Nov and 1 Dec 2010 at I-1

Two records on 15 Oct and 31 Dec 2010 at I-2

Three records on 27 Oct, 3 Dec and 22 Dec 2010 at O-1(FT)

Three records on 29 Oct, 10 Nov and 24 Dec 2010 at O-1(ET)

Four records on 13 Oct, 22 Oct, 27 Oct and 8 Nov 2010  at I-1

Six records on 13 Oct, 3 Nov, 5 Nov, 17 Nov, 6 Dec and 24 Dec 2010 at I-2

One record on 24 Dec 2010  at I-3

Nine records on 25 Oct, 5 Nov, 19 Nov, 22 Nov, 24 Nov, 26 Nov, 1 Dec, 15 Dec and 29 Dec 2010  at O-1(FT)

Nine records on 25 Oct, 27 Oct, 5 Nov, 8 Nov, 12 Nov, 15 Nov, 13 Dec, 15 Dec and 29 Dec 2010  at O-1(ET)

 

7    Waste figures during the reporting period are summarized in the table below.

Status of Waste Management

 

Inert C&D Material Disposed of to Public Fill at Tuen Mun (m3)

24,652.4

Inert C&D Material Reused in this Contract (m3)

675.0

Inert C&D Material Reused in other Contract* (m3)

16,085.0

Metals Generated (kg)

18.0

Paper / Cardboard Packaging (kg)

400.0

Plastics (kg)

20.0

Chemical Waste (kg)

10,762.2

General Waste Disposed of to NENT Landfill (m3)

131.8

*    Other Contracts include DC/2007/08, DC/2008/12, YL/2009/01, HY/2007/10, DC/2007/17 and Wo Shang Wai.

 

8    During the reporting period, two environmental complaints were received. EPD received two public complaints regarding daytime construction noise from outfall construction site on 17 November 2010.  The complaints were about barge squeaking and rock breaking.  The ET have conducted site inspection at the Outfall construction site and the Greenview Terrace (NSR 9) on 2 and 17 December 2010 to review and audit the site setting, noise mitigation measures implemented on-site and the environmental performance of the contractor. Enhanced on-site noise mitigation measures have been implemented by the contractor. A noise investigation report was submitted to the EPD on 24 December 2010. The issue of noise complaints was considered closed. 

9    No Notification of Summons was received since the commencement of the Project.


1                     Introduction

1.1.1                The Drainage Services Department (DSD) proposes to construct a tunnel of an internal diameter of 6.5m and length 5.13km, with the purpose to alleviate the flooding risk in Tsuen Wan and Kwai Chung.

1.1.2                This project is a Designated Project under Schedule 2 Part I Category Q, of the Environmental Impact Assessment Ordinance (EIAO) as part of the proposed Tsuen Wan Drainage Tunnel (TWDT) passes underneath the existing Tai Mo Shan Country Park.  An Environmental Impact Assessment (EIA) Study has therefore been undertaken to provide information on the nature and extent of environmental impacts arising from the construction and operation of the proposed designed project and related activities taking place concurrently.  From the EIA the recommendations for monitoring contained herein, are made.

1.1.3                The Maeda-CREC-SELI Joint Venture (MCSJV) was awarded by DSD with the Contract – Design and Construction of Tsuen Wan Drainage Tunnel.

1.1.4                Hyder was commissioned by the MCSJV as the ET to implement an EM&A program in accordance with the EM&A Manual.  The proposed tunnel section flows from the junction of Shing Mun Road and Wo Yi Hop Road and discharges to south of Yau Kom Tau underneath Castle Peak Road as shown in Appendix A.

1.1.5                The construction works of the Project commenced in January 2008.  This is the eleventh quarterly EM&A report summarising the impact monitoring results and audit findings of the EM&A program during the reporting period between October and December 2010.

2                     Project Information

2.1               Project Organization and Management Structure

2.1.1                The organization chart and lines of communication with respect to the on-site environmental management are shown in Appendix B.

2.2               Construction Progress

2.2.1                It is anticipated that the overall project programme from the detail design to completion of all civil works shall take approximately 54 months.  The construction programme is presented in Appendix C.

2.2.2                The major construction activities undertaken in the reporting quarter are: 

·       Site cleaning and tidying at I-1, I-2, I-3 and outfall;

·       Drilling, excavation and rock splitting of spiral ramp at outfall;

·       Pre-bored H-pile drilling and soil nailing for CPR open excavation at outfall;

·       Tunnel boring machine (TBM) drilling of the tunnel and mucking out of tunnel spoil at outfall;

·       Marine dredging works for basin scheme at Portion E;

·       Drilling and excavation of vortex shaft at I-3;

·       Temporary rock dowel drilling and installation at I-3;

·       Construction of skin wall at I-3;

·       Excavation of man access shaft and vortex drop shaft at I-2;

·       Pipe jacking at Portion G at I-2;

·       Pile caps construction for temporary platform at Portion G at I-2;

·       Cascade and channel modification concrete structure works at I-1;

·       Horizontal drilling at I-1;

·       Removal of sea wall and amour rock for basin scheme at Portion E;

·       Construction of pre-bored H-Pile for PB wall at I-3;

·       Preparation work for retaining wall at I-2;

·       Construction of footing for erecting the tower crane at I-3;

·       Drilling, excavation and rock splitting of man access shaft and vortex drop shaft at I-2;

·       Construction of approach channel structure at I-2;

·       Erection of temporary steel platform for H-pile wall at Portion G at I-2; and

·                                               Backfilling of spiral ramp centre void at I-1.

2.3               Mitigation Measures

2.3.1                The environmental mitigation measures that were implemented and their statuses are given in Appendix D.

3                     EM&A Requirement

3.1               General

3.1.1                The EM&A requirements are stipulated in the EM&A Manual.  The principal purposes of the EM&A program are to assess the compliance with applicable environmental legislation and associated regulations; to ensure the implementation of mitigation measures specified in the EM&A Manual; and to identify any remedial works necessary for redressing any unacceptable or unanticipated environmental impacts.

3.2               EM&A on Air Quality; Noise and Water Quality

Monitoring Parameters

3.2.1                The air quality, noise and water quality monitoring frequencies and parameters are shown inTable 3-1.


Type of Monitoring

Monitoring Station ID

Parameter

Frequency

Air Quality Monitoring

ASR1; ASR3; ASR8 and ASR9

1-hour TSP

Once every 6 days

Noise Monitoring

NSR1; NSR3; NSR6; NSR8 and NSR9

Leq (30 min.)

Once every week

Water Quality Monitoring

I-1; I-1-C; I-2; I-2-C; I-3; I-3-C,

O-1(FT),  O-1-C(FT), O-1(ET) and O-1-C(ET)

DO (mg/l)

Three days per week

SS (mg/l)

Turbidity (NTU)

pH

Temperature (oC)

Table 3-1         Frequency of Air Quality, Noise and Water Quality Monitoring

3.3               Monitoring Locations

3.3.1                The monitoring locations for air quality, noise and water quality are shown in Tables 3-2, 3-3, 3-4 and Appendix E.

Monitoring Station ID

Name of Premises

Floor Level

ASR1

Sik Sik Yuen Ho Fung College

G/F

ASR3

Hong Hoi Chee Hong Temple

Podium

ASR8

Beach Tower (Long Beach Gardens)

G/F

ASR9

Greenview Terrace (Block 1)

G/F

Table 3-2         Air Quality Monitoring Locations

Monitoring Station ID

Name of Premises

Floor Level

NSR1

Sik Sik Yuen Ho Fung College

G/F

NSR3

Hong Hoi Chee Hong Temple

Podium

NSR6

Squatters

G/F

NSR8

Beach Tower (Long Beach Gardens)

G/F

NSR9

Greenview Terrace (Block 1)

Podium (up to 6 July 2009)

Roof* (from 16 July 2009)

* The noise monitoring location of NSR9 had been adjusted at rooftop from 16 July 2009.

Table 3-3         Noise Monitoring Locations


Monitoring Station ID

Name of Premises

I-1

Intake I-1

I-1-C

Control of Intake I-1

I-2

Intake I-2

I-2-C

Control of Intake I-2

I-3

Intake I-3

I-3-C^

Control of Intake I-3

O-1 (FT) & (ET)*

Outfall 1During Flood Tide and Ebb Tide

O-1-C (FT)*#

Control of Outfall O-1 During Flood Tide

O-1-C (ET)*#

Control of Outfall O-1 During Ebb Tide

Note:   *Water quality monitoring will be undertaken when the construction of the outfall basin at the seashore is started.

#Note that there are two control stations for Outfall O-1; one for sampling during flood tide and one for sampling during ebb tide.  Only one of those control stations for Outfall O-1 shall be sampled during each sampling.  Control station to be sampled will be determined according to the tidal information provided by the Hong Kong Observatory.

^ The upper stream location (I-3-C^) had been relocated from the end of February 2009 due to coarse stone blockage.

Table 3-4         Water Quality Monitoring Locations

3.4               Performance Limits (AL Levels)

3.4.1                In accordance with the EM&A Manual; the appropriate Action and Limit Levels for air quality, noise and water quality were established and are presented in Table 3-5, Table 3-6 and Table 3-7.  Should non-compliance of the air quality, noise and water quality criteria occur, actions in accordance with the Event / Action Plan stipulated in contract specific EM&A Manual should be carried out.

Station

1-hr TSP Level in μg/m3

Action Level

Limit Level

ASR1

307

500

ASR3

327

500

ASR8

337

500

ASR9

329

500

Table 3-5         Action & Limit Levels for Air Quality

 


Time Period

Action

Limit

0700 – 1900 hrs on normal weekdays

When one documented complaint is received

75 dB(A)*

*           For educational establishments the limit level shall be 70dB(A) and reduced to 65dB(A) during examination periods between 0700-1900 hrs on normal weekdays.

Table 3-6         Action & Limit Levels for Noise

 

Parameters

Action

Limit

DO in mg/L

(Surface; Middle & Bottom)

Surface & Middle

5%-ile of baseline data for surface and middle layer.

 

Bottom

5%-ile of baseline data for bottom layer.

Surface & Middle

4mg/l except 5mg/l for Fish Culture Zone (FCZ) or

1%-ile of baseline data for surface and middle layer

Bottom

2mg/l or 1%-ile of baseline data for bottom layer

SS in mg/L

(Depth-averaged)

95%-ile of baseline data or 120% of upstream control station’s SS at the same tide of the same day

99%-ile of baseline or 130% of upstream control station’s SS at the same tide of the same day and specific sensitive receiver water quality requirements (e.g. required suspended solids levels for concerned sea water intakes)

Turbidity (Tby) in NTU (Depth-averaged)

95%-ile of baseline data or 120% of upstream control station’s Tby at the same tide of the same day

99%-ile of baseline or 130% of upstream control station’s Tby at the same tide of the same day

Notes:

·         For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

·         For SS and Tby, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

·         All the figures given in the table are used for reference only and the EPD may amend the figures whenever it is considered as necessary.

Table 3-7         Action & Limit Levels for Water Quality


3.5               Monitoring Result

3.5.1                All measured air quality monitoring levels were complying with the Action and Limit Levels in the reporting period. A summary of air quality monitoring results is presented in Table 3-103-8 and Appendix F.

Monitoring Station

1-hour TSP (mg/m3)

Action Level

Limit Level

Range

(mg/m3)

(mg/m3)

ASR1

35.5

-

253.8

307

500

ASR3

24.1

-

277.0

327

500

ASR8

30.4

-

257.5

337

500

ASR9

28.5

-

312.6

329

500

Italic indicates the exceedances of Action Levels

Bold indicates the exceedances of Limit Levels

Table 3-8         Summary of Air Quality Monitoring Results

3.5.2                All measured noise monitoring levels were complying with Limit Levels in the reporting period. However, EPD received two noise complaints on 17 November 2010 that triggered the exceedances of action level during the reporting period.  Investigation including site inspection, review and audit of noise mitigation measures implemented on-site and the Contractor’s environmental performance has been undertaken. Reports, including the nature of the complaints, observation of site inspections, proposed action taken and any further mitigation measures necessary to alleviate the impact, were submitted to EPD.

3.5.3                A summary of noise monitoring results is presented in Table 3-9 and Appendix F.

Monitoring Station

Leq (30mins) dB(A)

Limit Level

Range

dB(A)

NSR1

63

-

69

65/70

NSR3

59

-

71

75

NSR6

55

-

71

75

NSR8

60

-

70

75

NSR9

63

-

72

75

Bold indicates the exceedances of Limit Levels

Table 3-9         Summary of Impact Noise Monitoring Results

3.5.4                A summary of water quality monitoring results is presented in Table 3-10 and Appendix F.

3.5.5                None of exceedance related to project construction activities was recorded during reporting quarter but a total of 61 non project related exceedances were recorded.

River Water Quality Monitoring

3.5.7                A total of 7 non project related exceedances were recorded in October 2010 including:

·       Two exceedances of turbidity (baseline) Limit Level were recorded at I-2 and I-3 on 15 October 2010.  The measured turbidity levels on both cases were above the baseline Limit Level.  Higher turbidity levels were recorded at the upstream control stations (I-2-C and I-3-C).  On site mitigation measures had been implemented during the construction and direct disturbance of construction works was not observed from the sites.  As such, the exceedances were considered to be contributed by natural variation and no further action was required.

·       Four exceedances of SS Limit Level were recorded on 13, 22 and 27 at I-1 and I-2 and one exceedance of SS Action Level was recorded on 20 October 2010 at I-2.  The measured SS levels at the impact monitoring stations were either 20% (Action Level) or 30% (Limit Level) more than the corresponding measurement results of the upstream control stations (I-1-C and I-2-C), where low SS levels were measured (between 2 mg/L and 2.9 mg/L). The SS results on these days were within the range of baseline SS concentration (1 - 8.5 mg/L).  Since direct disturbance of construction works was not observed from the construction sites at I-1 and I-2 and suitable mitigation measures had been implemented, the exceedances were considered to be contributed by natural variation.  No further action was required.

·       Another exceedance of SS Action Level was recorded on 15 October 2010 at I-2.  The measured SS level at the impact monitoring station was higher than 95 percentile of the baseline data.  Higher SS level was measured at the upstream control station I-2-C.   Since direct disturbance of construction works was not observed from the construction site at I-2 and suitable mitigation measures had been implemented, the exceedances were considered to be contributed by natural variation and the wet weather on that day (about 3.9 mm of rainfall were recorded at the Hong Kong Observatory on 15 October 2010).  No further action was required.

3.5.7                A total of 7 non project related exceedances were recorded in November 2010 including:

·       An exceedance of turbidity Action Level was recorded at I-1 on 5 November 2010. The measured turbidity level (10.45 NTU) was above baseline Action Level, but it was lower than the turbidity level measured at the upstream control station I-1-C (10.89 NTU).  General site cleaning and housekeeping, dismantle formwork for Bay 19 spiral ramp, erection of formwork for Bay 22 and 23 spiral ramp, and horizontal drilling were undertaken during measurement. No direct disturbance was observed from the site and the turbidity result at monitoring station was below the level of control station. Thus, the exceedance was considered to be contributed by natural variation and no action was required.

·       An exceedance of turbidity Limit Level was recorded at I-2 on 5 November 2010.  The measured turbidity level (13.61 NTU) was above the Baseline Limit level.  However, it was lower than the turbidity level measured at the upstream control station I-2-C (14.33 NTU).  Construction activities including general site cleaning and housekeeping, excavation (hole drilling) at vortex drop shaft, excavation (rock splitting and mucking) at man access shaft, preparation work for skin wall, pipe jacking (rock breaking for 13th jacking pipe) at Portion G, and dismantling formwork for pile caps were undertaken during measurement.  No direct disturbance was observed from the site.  Thus, the exceedance was considered to be due to natural variation and no action was required.

·       An exceedance of SS Limit Level was recorded at I-2 on 3 November 2010. The measured SS level (2.90 mg/L) was below the baseline Action / Limit Level and was within the range of baseline SS concentration (1 - 8.5 mg/L).  It was higher than the SS level measured at upstream control station I-2-C (2.0 mg/L).  General site cleaning and housekeeping, install wire mesh and shotcreting at vortex drop shaft, excavation (hole drilling) at man access shaft, preparation work for skin wall, erect steel frame for ventilation system at 20T gantry, pipe jacking (rock breaking for 12th jacking pipe) at Portion G, and erect formwork and rebar fixing of pile caps at Portion G were undertaken during the measurement.  No direct disturbance was observed from the site. Thus, the exceedance was considered to be contributed by natural variation and no action was required.

·       An exceedance of SS Action Level was recorded at I-1 on 5 November 2010. The measured SS level (4.10 mg/L) was below the baseline Action Level.  It was also within the range of baseline SS concentration (1 - 10.5 mg/L), but was higher than the SS level measured at upstream control station I-2-C (3.35 mg/L).  General site cleaning and housekeeping, dismantle formwork for Bay 19 spiral ramp, erection of formwork for Bay 22 and 23 spiral ramp and horizontal drilling were undertaken during measurement.  No direct disturbance was observed from the site.  As such, the exceedance was considered to be contributed by natural variation and no action was required.

·       An exceedance of SS Limit Level was recorded at I-2 on 5 November 2010. The measured SS level (11.80 mg/L) was above the baseline Action / Limit Level. However, the measured SS level was below 120% of the control station’s (I-2-C) SS level (10.80 mg/L). General site cleaning and housekeeping, excavation (drilling holes and mucking) at vortex drop shaft, excavation (rock splitting and mucking) at man access shaft, preparation for skin wall, erect platform for air compressor,  pipe jacking (rock breaking for 13th jacking pipe) at Portion G, dismantle formwork for pile caps at Portion G were undertaken during measurement.  No direct disturbance was observed from the site.  Thus, the exceedance was considered to be contributed by natural variation and no action was required.

·       An exceedance of SS Limit Level was recorded at I-1 on 8 November 2010. The measured SS level (3.35 mg/L) was below the baseline Action Level.  It was also within the range of baseline SS concentration (1 - 10.5 mg/L), but was higher than the SS level measured at the upstream control station I-1-C (2.40 mg/L).  General site cleaning and housekeeping, general cleaning at Bay 21 spiral ramp, dismantle formwork for Bay 22 spiral ramp, rebar fixing for Bay 23 spiral ramp, and horizontal drilling were undertaken during measurement. No direct disturbance was observed from the site.  Hence, the exceedance was considered to be contributed by natural variation and no action was required.

·       An exceedance of SS Limit Level was recorded at I-2 on 17 November 2010. The measured SS level (4.05 mg/L) was below the baseline Action / Limit Level and within the range of baseline SS concentration (1 - 8.5 mg/L).  However, it was more than 130% of the SS level measured at the upstream control station I-2-C (2.00 mg/L).  General site cleaning and housekeeping, excavation (drilling holes and rock splitting) at vortex drop shaft, excavation (drilling holes) at man access shaft, preparation for skin wall, erection of the noise enclosure for ventilation fan, pipe jacking (rock breaking for the 14th jacking pipe) at Portion G, pipe jacking (jacking for the 13th concrete pipe) at Portion G, and erection of the 60-tonne temporary steel platform at Portion G were undertaken during measurement.  No direct disturbance was observed from the site.  Thus, the exceedance was considered to be contributed by natural variation and no action was required.

3.5.8                A total of 5 non project related exceedances were recorded in December 2010 including:

·       An exceedance of SS Action Level was recorded at I-1 on 1 December 2010. The measured SS level (2.70 mg/L) was below the baseline Action / Limit Level and was within the range of baseline SS concentration (1 – 10.5 mg/L).  It was higher than the SS level measured at upstream control station I-1-C (2.20 mg/L). General site cleaning and housekeeping, rebar fixing at Bay 23, formwork at Bay 23, horizontal drilling and GI monitoring were undertaken during measurement.  No direct disturbance was observed from the site.  Thus, the exceedance was considered to be contributed by natural variation and no action was required.

·       An exceedance of SS Limit Level was recorded at I-2 on 6 December 2010.  The measured SS level (3.20 mg/L) was below baseline Action / Limit Level and within the range of baseline SS concentration (1 - 8.5 mg/L), but was more than 130% of the SS level measured at the upstream control station (I-2-C)(2.00 mg/L). General site cleaning and housekeeping, excavation (drilling holes) at vortex drop shaft, excavation (drilling holes) at man access shaft, rock breaking for jacking pipe at Portion G and erection of 60 ton temporary steel platform at Portion G were undertaken during measurement.  No direct disturbance was observed from the site.  Thus, the exceedance was considered to be contributed by natural variation and no action was required.

·       An exceedance of SS Limit Level was recorded at I-2 on 24 December 2010. The measured SS level (3.05 mg/L) was below baseline Action / Limit Level and within the range of baseline SS concentration (1 - 8.5 mg/L) but was more than 130% of the SS level measured at the upstream control station (I-2-C) (2.10 mg/L). General site cleaning and housekeeping, excavation (drilling holes) at vortex drop shaft and excavation (drilling holes) at man access shaft, rock breaking for 16th jacking pipe at Portion G, erection of 60 ton temporary steel platform at Portion G and excavation for 750 step channel (SC) and catchpit were undertaken during measurement.  No direct disturbance was observed from the site. Thus, the exceedance was considered to be contributed by natural variation and no action was required.

·       An exceedance of SS Limit Level was recorded at I-3 on 24 December 2010. The measured SS level (4.15 mg/L) was below baseline Action / Limit Level and within the range of baseline SS concentration (1 - 7.5 mg/L) but was more than 130% of the SS level measured at the upstream control station (I-3-C) (2.00 mg/L). General site cleaning and housekeeping, PB wall H-pile extension, approach channel extension, and shaft excavation were undertaken during measurement.  No direct disturbance was observed from the site.  Thus, the exceedance was considered to be contributed by natural variation and no action was required.

·       An exceedance of SS Action Level was recorded at I-2 on 31 December 2010. The measured SS level (2.45 mg/L) was below baseline Action / Limit Level and within the range of baseline SS concentration (1 - 8.5 mg/L) but was more than 120% of the SS level measured at the upstream control station (I-2-C) (2.00 mg/L). General site cleaning, housekeeping and temporary traffic arrangement (TTA), excavation (drilling holes) at vortex drop shaft, excavation (drilling holes and rock spilling) at man access shaft, closed formwork for dry flow channel, rock breaking for 16th jacking pipe at Portion G, erection of 60 ton temporary steel platform at Portion G and excavation for 750 step channel (SC) and catchpit were undertaken during measurement. No direct disturbance was observed from the site. Thus, the exceedance was considered to be contributed by natural variation and no action was required.

Marine Water Quality Monitoring

3.5.9                A total of 16 non project related exceedances were recorded in October 2010 including:

·       Four exceedances at O-1(FT) and five exceedances at O-1(ET) of DO baseline Limit Level were recorded on 25, 27 and 29 October 2010.

·       Marine buoys and silt curtains were set up on 25 and 27 October 2010 and there was no dredging on these two days. As such, the eight exceedances of DO baseline limit on 25 and 27 October 2010 were considered due to natural variation.

·       An exceedance of surface DO limit level was recorded at O-1(ET) (6.75 mg/L) during the ebb tide on 29 October 2010 (in contrast to the DO level of 7.44 mg/L measured at the upstream control station O-1-C(ET) during the same tide).  During monitoring, silt curtains were deployed at the construction site and marine dredging was conducted within these curtains.  Thus, any impact upon DO level associated with pollutants released from the marine sediment during dredging would only be confined within the construction site.  As such, the surface DO exceedance at O-1(ET) was considered to be contributed by natural variation.  No further action was required.

·       An exceedance of turbidity baseline Limit Level was recorded on 25 October 2010 at O-1(FT) (14.13 NTU).  High turbidity level was also recorded at the upstream control station O-1-C(FT) on the same tide of 25 October 2010 (13.77 NTU).  As no marine dredging was conducted on that day, the exceedance was considered to be contributed by natural variation.  No action was required.

·       Three exceedances of SS Limit Level were recorded on 25 October 2010 at O-1(FT) and O-1(ET), and on 27 October 2010 at O-1(ET).  Another exceedance of SS Action Level was recorded on 27 October 2010 at O-1(FT).  As there were no dredging works undertaken in these two days, the exceedances were considered to be contributed by natural variation.

·       An exceedance of SS Action Level was recorded on 29 October 2010 at O-1(ET).  The SS level measured at O-1(ET) was 13.33 mg/L, which was more than 95 percentile of the baseline data.  In contrast, higher SS level (17.15 mg/L) was recorded at the upstream control station at O-1-C(ET) on 29 October 2010.  While marine dredging was undertaken at the outfall basin on the same day, mitigation measures had been adopted, including:

  Silt curtains deployed along the dredging boundary line and extended from the seawater level to the bottom of seabed;

  Frame-type silt curtain deployed for the marine mud dredging at the derrick barge;

  Closed grab dredging confined within the frame type silt curtain; 

  Daily dredging rate limited to a maximum 960 m3;

  Silt curtain with sufficient slack to ensure the curtain rested on the seabed to cope with waves and tides.

  The condition of the silt curtains was checked by the supervisor on-broad per working day to ensure proper implementation and functioning prior to any marine works activities.

·       Having considered the good forms of silt curtains and measures to limit SS generation, any SS dispersion was localised and limited within the construction site.  Thus, the exceedance was considered to be contributed by natural variation.  No further action was required.

3.5.10              A total of 17 non project related exceedances were recorded in November 2010 including:

·       An exceedance of DO Action Level was recorded at the surface layer of O-1(FT) on 1 November 2010. The measured DO level (6.83 mg/L) was just below the baseline Action Level (6.84 mg/L).  Dredging was conducted at the Outfall basin (portion E) on 1 November 2010.  During monitoring, silt curtains were deployed along the dredging boundary line and extended from the seawater level to the seabed.  Frame-type silt curtain had also been employed at the derrick barge and all dredging operation was confined in the frame-type silt curtain.  Thus, any impact upon DO level associated with pollutants released from the marine sediment during dredging would only be confined within the construction site.   As such, the exceedance was considered to be contributed by natural variation.  No further action was required.

·       Five exceedances of DO Limit Level were recorded at middle and bottom layers on 1 November and at surface, middle and bottom layers on 3 November 2010 respectively at O-1(FT). The measured DO levels (that varied from 6.51 to 6.70 mg/L) were below the baseline Action / Limit Level of the corresponding layer.  (In contrast, the corresponding DO levels measured at the upstream control station O-1-C(FT) varied from 6.74 to 7.18 mg/L).  Dredging was conducted at the Outfall basin (portion E) on both 1 and 3 November 2010.  During monitoring, silt curtains were deployed along the dredging boundary line and extended from the seawater level to the seabed.  Frame-type silt curtain had also been employed at the derrick barge and all dredging operation was confined in the frame-type silt curtain.  Thus, any impact upon DO level associated with pollutants released from the marine sediment during dredging would only be confined within the construction site.  As such, the exceedances were considered to be contributed by natural variation.  No further action was required.

·       An exceedance of Turbidity Limit Level was recorded at O-1(ET) on 8 November 2010. The measured SS level (depth-averaged) (14.28 NTU) at O-1(ET) was above the baseline Action/Limit Level but below the control station's SS level (O-1-C(ET)) (14.41 NTU) at the same tide of the same day.  Dredging was undertaken at Portion E on 8 November 2010.  Silt curtains had been deployed along the dredging boundary line and extended from the seawater level to the seabed.  Frame-type silt curtain had been employed at the derrick barge and all dredging operation was confined in the frame-type silt curtain.  As such, the exceedance was considered to be contributed by natural variation (high background level of SS) and no further action was required.

·       Five exceedances of SS Limit Level were recorded on 5, 19, 22, 24 and 26 November 2010 at O-1(FT). The measured SS levels (varied from 8.83 to 12.42 mg/L) were below the baseline Action/Limit Level but was higher than 130% of the control station's SS level (O-1-C(FT)) (varied from 6.67 to 9.28 mg/L) at the same tide of the same day.  No marine dredging activity was undertaken on 5 and 19 November 2010 and only rock removal at Portion E was undertaken on 22 and 24 November 2010.  For 26 November 2010, rock removal at Portion E and installation of noise insulation blanket next to wire drums were undertaken.  Silt curtains had been provided along Portion E boundary line and extended from seawater level to the bottom of seabed during the marine works.  Frame / floating type silt curtains had also been employed at the derrick barge, and rock removal operation was confined in the inner (frame / floating type) silt curtain.   As such, the exceedances were considered to be contributed by natural variation and no further action was required.

·       Four exceedances of SS Limit Level were records on 5, 8, 12 and 15 November 2010 at O-1(ET).  The measured SS levels (depth-averaged) (varied from 14.42 to 23.20 mg/L) were above the baseline Action / Limit Level.  However, the measured SS levels were below the control station's SS level on 12 November 2010 (19.35 mg/L), below 120% of the control station's SS level on 5 and 8 November 2010 (13.23 and 22.00 mg/L respectively) and below 130% of the control station’s SS level on 15 November 2010 (11.72 mg/L).  Since there was no dredging activity undertaken on 5 and 15 November 2010, the exceedances were considered not related to the construction activities.  During the marine works on 8 November 2010 (dredging at Portion E) and 12 November 2010 (rock removal), mitigation measures had been implemented on-site.  These included silt curtains provided along Portion E boundary line and extended from seawater level to the bottom of seabed, and frame / floating type silt curtains employed at the derrick barge.  Dredging and rock removal operation were confined in the inner (frame / floating type) silt curtain.   As such, the exceedances were considered to be contributed by natural variation and no further action was required.

·       An exceedance of SS Action Level was recorded on 10 November 2010. The measured SS level (depth-averaged) (13.72 mg/L) at O-1(ET) was between the baseline Action Level and the Limit Level, and was below the control station's SS level (at O-1-C(ET)) (15.78 mg/L) at the same tide of the same day.  Marine dredging was undertaken at the Outfall basin (Portion E) on 10 November 2010.  Silt curtains had been deployed along the dredging boundary line and extended from the seawater level to the seabed.  Frame-type silt curtain had been employed at the derrick barge and all dredging operation was confined in the frame-type silt curtain.  As such, the exceedance was considered to be contributed by natural variation (high background level of suspended solids) and no further action was required.

3.5.11              A total of 9 non project related exceedances were recorded in December 2010 including:

·       Two exceedances of SS Action Level were recorded on 3 and 22 December 2010 at O-1(FT). The measured SS levels (7.38 and 12.95 mg/L respectively) were below the baseline Action/Limit Level but was higher than 120% of the control station's SS level (O-1-C(FT)) (6.13 and 10.40 mg/L respectively) at the same tide of the same day.  Only rock removal at Portion E on 3 December 2010 and armour rock removal from the sea wall to the derrick barge at Portion E on 22 December 2010 were undertaken during measurement. Silt curtains had been provided along Portion E boundary line and extended from seawater level to the bottom of seabed during the marine works.  Frame / floating type silt curtains had also been employed at the derrick barge, and rock removal operation was confined in the inner (frame / floating type) silt curtain. As such, the exceedances were considered to be contributed by natural variation and no further action was required.

·       Three exceedances of SS Limit Level were recorded on 1, 15 and 29 December 2010 at O-1(FT).  The measured SS levels (varied from 3.20 to 7.83 mg/L) were below the baseline Action / Limit Level but higher than 130% of the control station's SS level (O-1-C(FT)) (varied from 2.37 to 5.28 mg/L) at the same tide of the same day. Only rock-fill removal from sea bed was undertaken on 1 December 2010 and no marine dredging activities were undertaken on 15 and 29 December 2010. As silt curtains were provided along Portion E boundary line and extended from seawater level to the bottom of seabed, frame / floating type silt curtains were deployed at the derrick barge, and dredging / rock removal operation were confined in the inner (frame / floating type) silt curtain.   As such, the exceedances were considered to be contributed by natural variation and no further action was required.

·       An exceedance of SS Action Level was recorded on 24 December 2010. The measured SS level (depth-averaged) (9.82 mg/L) at O-1(ET) was below the baseline Action/Limit Level but higher than 120% of the control station's SS level (O-1-C(ET)) (7.87 mg/L) at the same tide of the same day. No marine works was undertaken during measurement.  As silt curtains had been deployed along the dredging boundary line and extended from the seawater level to the seabed and floating type silt curtain had been employed at the inner side, the exceedance was considered to be contributed by natural variation and no further action was required.

·       Three exceedances of SS Limit Level were recorded on 13, 15 and 29 December 2010. The measured SS levels (depth-averaged) (9.20, 5.53 and 9.07 mg/L respectively) were below the baseline Action and Limit Level but higher than 130% of the control station's SS level (O-1-C(ET)) (5.18, 3.97 and 6.03 mg/L respectively) at the same tide of the same day. No marine works were undertaken on 13, 15 and 29 December 2010. As such, the exceedances were considered to be contributed by natural variation and no further action was required.

3.5.12              The above mentioned exceedances were considered not project related. However, proper mitigation measures had been implemented during measurements. Details of the above mentioned investigations could be referred to the Interim Notifications of Environmental Quality Limits Exceedances as enclosed in Appendix G.


Monitoring Station

Temperature

DO (mg/L)

pH

Turbidity (NTU)

Suspended Solid (mg/L)

Range

Range

Action / Limit Level

Range

Range

Action / Limit Level

Range

Action / Limit Level

I-1

17.20

-

29.70

5.05

-

8.06

3.42

/

3.34

7.50

-

8.91

2.39

-

10.45

9.75

/

12.47

2.00

-

7.45

8.85

/

10.17

I-1C

17.40

-

29.80

5.08

-

8.50

 

-

 

7.52

-

8.90

2.48

-

10.89

 

-

 

2.00

-

6.25

 

-

 

I-2

17.00

-

29.50

4.92

-

7.90

3.66

/

3.63

7.62

-

8.87

1.20

-

13.61

6.63

/

6.99

2.00

-

11.80

7.68

/

8.34

I-2C

17.10

-

29.50

5.11

-

8.27

 

-

 

7.61

-

8.88

1.25

-

14.33

 

-

 

2.00

-

11.20

 

-

 

I-3

17.00

-

29.35

5.02

-

7.90

3.65

/

3.51

7.60

-

8.90

1.23

-

7.80

3.99

/

4.18

2.00

-

6.05

6.13

/

7.23

I-3C

16.90

-

29.60

5.09

-

8.26

 

-

 

7.56

-

8.91

1.30

-

7.88

 

-

 

2.00

-

6.20

 

-

 

Note:   Italic indicates the exceedances of Action Levels

Bold indicates the exceedances of Limit Levels

Table 3-10       Summary of Impact Water Quality Monitoring Results


 

Monitoring
Station

Temperature

DO (mg/L)

pH

Turbidity (NTU)

Suspended Solid (mg/L)

Range

Range

Action / Limit Level

Range

Range

Action / Limit Level

Range

Action / Limit Level

O-1(FT)

Surface

17.67

-

27.10

5.50

-

7.63

6.84

/

6.81

7.93

-

8.32

2.82

-

14.13

10.35

/

13.15

2.67

-

21.65

14.10

/

18.08

Middle

5.88

-

7.65

Bottom

5.87

-

7.89

6.99

/

6.96

O-1-C(FT)

Surface

17.58

-

26.83

5.62

-

7.67

-

/

-

7.87

-

8.33

3.01

-

13.77

-

/

-

2.33

-

24.32

-

/

-

Middle

5.76

-

7.62

Bottom

5.93

-

7.66

O-1(ET)

Surface

17.45

-

26.53

6.01

-

7.72

7.02

/

6.94

7.93

-

8.35

2.92

-

14.28

11.87

/

13.44

5.07

-

23.20

13.25

/

14.39

Middle

6.26

-

7.71

Bottom

6.24

-

7.70

6.70

/

6.48

O-1-C(ET)

Surface

16.92

-

26.67

5.96

-

7.79

-

/

-

7.97

-

8.40

2.90

-

14.41

-

/

-

3.97

-

22.00

-

/

-

Middle

6.05

-

7.76

Bottom

5.46

-

7.72

Note:   Italic indicates the exceedances of Action Levels

Bold indicates the exceedances of Limit Levels

Table 3-11       Summary of Impact Marine Water Quality Monitoring Results


3.6               DO, Temperature and pH Data Monitored on 29 November 2010 and 1 December 2010

3.6.1            The previous calibration certificate for the multimeter (for pH, temperature and DO measurements) was expired on 27 November 2010 and the multimeter was recalibrated on 3 December 2010.  Therefore, the water quality data (pH, temperature and DO) collected on 29 November 2010 and 1 Dec 2010 were not covered under a valid calibration certificate of the multimeter.  Although the recalibration of the multimeter on 3 December 2010 indicated that the multimeter was functioning normally within acceptable deviations, it is considered that the water quality data (pH, temperature and DO) measured on 29 November 2010 and 1 December 2010 shall be considered for reference only.   Nevertheless, it is noted that the pH, temperature and DO data monitored at various stations on 29 November 2010 are similar to the values measured on 26 November 2010 and on 1 December 2010 are similar to the values measured on 3 December 2010.  Effluent discharges from the construction sites at I-1, I-2 and I-3 have been controlled under the wastewater discharge licenses.  Mitigation measures were deployed at various construction sites during monitoring.  These included: (1) silt curtains for marine works (rock removal) at the marine basin of Outfall; (2) wastewater treatment plants at I-1, I-2 and I-3; (3) diversion of existing streams that were bunded by sealed concrete block walls at I-1, I-2 and I-3; and (4) bunded off the existing stream by sand bag to prevent washing out of excavated material from the working area at I-2.  Thus, adverse water quality impact on DO at various stations due to the Project on 29 November 2010 and 1 December 2010 was not anticipated.

3.7               Turbidity Data Monitored on 24 December 2010

3.7.1            The previous calibration certificate for the turbidimeter (serial no. 215619) was expired on 24 December 2010 and the turbidimeter was recalibrated on 28 December 2010.  Therefore, the turbidity data collected on 24 December were not covered under a valid calibration certificate of the turbidimeter. The recalibration of the turbidimeter on 28 December 2010 indicated that the turbidimeter was functioning normally within acceptable deviations. However, the turbidity data measured on 24 December 2010 should be considered for reference only.

3.7.2            The turbidity levels measured at various control stations were higher than the turbidity level of the corresponding impact stations on 24 December 2010.  Four-point on-site calibration of the turbidimeter was conducted before subsequent measurements and, thus, all measurements on 24 December 2010 were based on same calibration curve.  The higher turbidity levels at control stations (where the water qualities were not affected by the project) and the relatively lower turbidity levels of the impact stations (where water qualities were or were not affected by the Project) showed that the Project did not contribute any significant adverse impact on the turbidity levels at the various impact monitoring stations.

3.7.3            In addition, effluent discharges from the construction sites at I-1, I-2 and I-3 have been controlled under the wastewater discharge licenses and mitigation measures were deployed at various construction sites during monitoring, including: (1) silt curtains for marine works (rock removal) at the marine basin of Outfall; (2) wastewater treatment plants at I-1, I-2 and I-3; and (3) diversion of existing streams that were bunded by sealed concrete block walls at I-1, I-2 and I-3, so the water quality of various locations are under sufficient protection.  Therefore, adverse water quality impact on turbidity at various monitoring stations due to the Project on 24 December 2010 was not anticipated.

 

4                     Quarterly Summary; Environmental Condition and Non-Compliance Records

4.1               Summary of Waste Disposal Records

4.1.1                According to the information provided by the Contractor; the quantities of C&D materials in the reporting period are summarized in Table 4-1

Status of Waste Management

October 10

November 10

December 10

Inert C&D Material Disposed of to Public Fill at Tuen Mun (m3)

5,386

6,581.8

12,684.6

Inert C&D Material Reused in this Contract (m3)

65

15.0

595.0

Inert C&D Material Reused in other Contract* (m3)

6,700

4430.0

4,955.0

Metals Generated (kg)

Nil

Nil

18.0

Paper / Cardboard Packaging (kg)

Nil

Nil

400.0

Plastics (kg)

Nil

Nil

20.0

Chemical Waste (kg)

2,392.0

920.0

7,450.2

General Waste Disposed of to NENT Landfill (m3)

34.6

41.2

56.0

*    Other Contracts include DC/2007/08, DC/2008/12, YL/2009/01, HY/2007/10, DC/2007/17 and Wo Shang Wai.

Table 4-1         Waste Generated from October to December 2010

4.2               Weather Conditions

4.2.1                The weather conditions during the period from October to December 2010 were mainly sunny, fine, cloudy and rainy.

4.3               Summary of Project-Related Exceedances

4.3.1                Summary of exceedance results are summarized in Table 4-2. Appendix G shows the Interim Notifications of Environmental Quality Limits Exceedances issued in the reporting period.


 

Environmental Monitoring

Total No. of Measurement

Action Level Exceedance

% of Action Level Exceedance

Limit Level Exceedance

% of Limit Level Exceedance

Air Quality

192

0

0

0

0

Noise

67

2 (complaints)

2.99

0

0

Water

350

0

0

0

0

Table 4-2         Summary of Project- related Exceedances

5                     Complaint

5.1.1                A complaint hotline at 9850 3241 of the Contractor has been established for the Project. 

5.1.2                During the reporting period, two environmental complaints were received. EPD received two public complaints regarding daytime construction noise from outfall construction site on 17 November 2010.  The complaints were about barge squeaking and rock breaking.  The ET have conducted site inspection at the Outfall construction site and the Greenview Terrace (NSR 9) on 2 and 17 December 2010 to review and audit the site setting, noise mitigation measures implemented on-site and the environmental performance of the contractor. Enhanced on-site noise mitigation measures were implemented by the contractor. A noise investigation report was submitted to the EPD on 24 December 2010. The issue of noise complaints was considered closed.  Details of the complaint investigation and observations can be referred to Appendix H.

 

5.1.3                Cumulative statistics of environmental complaints are shown in Table 5-1.

Complaints Received in the Reporting Period

Cumulative Number of Complaints

2

20

Table 5-1         Cumulative Statistics of Environmental Complaints

6                     Summary of Notification of Summons, Successful Prosecutions and Corrective Actions

6.1.1                No summons and successful prosecution was received during the reporting period.

6.1.2                Cumulative statistics of Notification of Summon; Successful Prosecutions and Convictions are shown in Table 6-1.

Notification of Summons

Successful Prosecution

October  – December 10

Cumulative

October  – December 10

Cumulative

0

0

0

0

Table 6-1         Cumulative Statistics of Notification of Summons and Successful Prosecutions

7                     Comments, Recommendations and Conclusion

7.1.1                During the reporting period, no project related exceedance of air quality monitoring was recorded. No exceedance of noise limit level was recorded, but EPD received two noise complaints on 17 November 2010 that triggered the exceedances of action level. Finally, Exceedances of water quality monitoring were recorded but none of these exceedances were related to Project’s construction activities.

7.1.2                EPD received two public complaints regarding daytime construction noise from outfall construction site on 17 November 2010.  The complaints were about barge squeaking and rock breaking.  The ET have conducted site inspection at the Outfall construction site and the Greenview Terrace (NSR 9) on 2 and 17 December 2010 to review and audit the site setting, noise mitigation measures implemented on-site and the environmental performance of the contractor. Enhanced on-site noise mitigation measures have been implemented by the contractor. A noise investigation report was submitted to the EPD on 24 December 2010. The issue of noise complaints was considered closed. 

7.1.3                No Notification of Summons has been received since the commencement of the Project. 

7.1.4                Waste management mitigation measures have been implemented by the Contractor within the reporting period.  Waste figures during the reporting period are summarized in Table 7-1.

Status of Waste Management

 

Inert C&D Material Disposed of to Public Fill at Tuen Mun (m3)

24,652.4

Inert C&D Material Reused in this Contract (m3)

675.0

Inert C&D Material Reused in other Contract* (m3)

16,085.0

Metals Generated (kg)

18.0

Paper / Cardboard Packaging (kg)

400.0

Plastics (kg)

20.0

Chemical Waste (kg)

10,762.2

General Waste Disposed of to NENT Landfill (m3)

131.8

*    Other Contracts include DC/2007/08, DC/2008/12, YL/2009/01, HY/2007/10, DC/2007/17 and Wo Shang Wai.

Table 7-1         Total Wastes Generated From October to December 2010


 

Appendix A

RuleBentDown

Site Map and Works Area


 

Appendix B

RuleBentDown

Organization Chart


 

Appendix C

RuleBentDown

Work Programme


 

Appendix D

RuleBentDown

Implementation Status of Environmental Mitigation Measures


 

Appendix E

RuleBentDown

Monitoring Locations


 

Appendix F

RuleBentDown

Monitoring Results


 

Appendix G

RuleBentDown

Interim Notifications of Environmental Quality Limits Exceedances


 

Appendix H

RuleBentDown

Complaint Log