CONTENTS

Executive Summary................................................................................. 1

1        Introduction.................................................................................... 4

2        Project Information.......................................................................... 4

2.1     Project Organization and Management Structure................................... 4

2.2     Construction Progress................................................................................. 4

2.3     Mitigation Measures..................................................................................... 5

3        EM&A Requirement........................................................................ 5

3.1     General........................................................................................................... 5

3.2     EM&A on Air Quality; Noise and Water Quality......................................... 5

3.3     Monitoring Locations.................................................................................... 6

3.4     Performance Limits (AL Levels)................................................................. 7

3.5     Monitoring Result.......................................................................................... 8

4        Quarterly Summary; Environmental Condition and Non-Compliance Records....................................................................................... 13

4.1     Summary of Waste Disposal Records................................................... 13

4.2     Weather Conditions................................................................................... 13

4.3     Summary of Project-Related Exceedances........................................... 13

5        Complaint..................................................................................... 14

6        Summary of Notification of Summons; Successful Prosecutions and Corrective Actions......................................................................... 15

7        Comments; Recommendations and Conclusion............................... 15

 




Executive Summary

1      This quarterly EM&A summary report under the Main Contract for the Design and Construction of Tsuen Wan Drainage Tunnel (hereafter referred to as the “Project”) to Maeda-CREC-SELI Joint Venture (MCSJV), which summarises the findings of environmental impact monitoring works during the period from July to September 2009.

2      Noise monitoring was performed at five monitoring stations (NSR1, NSR3, NSR6, NSR8 and NSR9).  Air quality monitoring was carried out at four monitoring stations (ASR1, ASR3, ASR8 and ASR9).  Water quality monitoring was carried out at three monitoring stations (Intake I-1, Intake I-2 and Intake I-3). Noise level was measured in terms of Leq, L10 and L90 (30min).  Air quality was measured in terms of 1-hour Total Suspended Particulates (TSP). Water quality was measured in terms of Temperature, pH, Dissolved Oxygen (DO), Turbidity (Tby) and Suspended Solid (SS).

3      Details of all monitoring stations are summarized in the below table.

Type of Monitoring

Monitoring Station ID

Name of Premises

Status of Monitoring Works during the Reporting Period

Air Quality Monitoring

ASR1

Sik Sik Yuen Ho Fung College

Ongoing

ASR3

Hong Hoi Chee Hong Temple

Ongoing

ASR8

Beach Tower (Long Beach Gardens)

Ongoing

ASR9

Greenview Terrace (Block 1)

Ongoing

Noise Monitoring

NSR1

Sik Sik Yuen Ho Fung College

Ongoing

NSR3

Hong Hoi Chee Hong Temple

Ongoing

NSR6

Squatters

Ongoing

NSR8

Beach Tower (Long Beach Gardens)

Ongoing

NSR9

Greenview Terrace (Block 1)

Ongoing

Water Quality Monitoring

I-1

Intake I-1

Ongoing

I-2

Intake I-2

Ongoing

I-3

Intake I-3

Ongoing

O-1

Outfall O-1

Not yet commenced until construction of stilling basin is in place.

 

4      The major construction activities undertaken by the Contractor during the period from July to September 2009 include site cleaning and tidying and tree transplanting at I-1, I-2, I-3 and Outfall; drilling rig at I-3 and Outfall; soil nailing at I-1, I-3 and Outfall; breaking up exiting boulder at I-1, I-2, I-3 and Outfall; formation of access road at I-3 and Outfall; erosion control mat and green wire mesh at Outfall; Excavation and Lateral Support (ELS) at I-1; construction of skin wall at I-2 and I-3; and formation of steel platform at I-2.

5      No construction activities were carried out during the restricted hours during the reporting period.

6      No water quality monitoring was done on 4 July, 27 July and 12 August 2009 due to thunderstorm warning.

7      No project related exceedance of air quality and water quality monitoring was recorded. For noise monitoring, no exceedance of Limit level was recorded, however, six environmental complaints on noise trigger the excceedances of Action Levels during the reporting period. The below table summarizes the exceedances of air quality, noise and water quality in the reporting period.

 Parameter

Action Level Exceedance

Limit Level Exceedance

Air

Nil

Nil

Noise

Five complaints were received on 29 July, 11, 12, 14 and 17 August 2009

One complaint was received on 7 September 2009

Nil

DO

Nil

Nil

Turbidity

One recorded at I-3 on 20 July 2009 (non project related)

One recorded at I-2 on 24 July 2009 (non project related)

SS

Two recorded at I-1 and I-3 on 6 and 20 July 2009 (non project related)

One recorded at I-1 on 28 August 2009 (non project related)

One recorded at I-1 on 16 September 2009 (non project related)

Six recorded at I-1, I-2 and I-3 on 6, 8, 10, 13 and 24 July 2009 (non project related)

Two recorded at I-1 and I-2 on 14 August 2009 (non project related)

Two recorded at I-1 and I-3 on 11and 14 September 2009 (non project related)

 

8      Waste figures during the reporting period are summarized in the below table.

Status of Waste Management

 

Inert C&D Material Disposed of to Public Fill at Tuen Mun (m3)

13,396.5

Inert C&D Material Reused in other Contract* (m3)

8,280.0

Metals Generated (kg)

Nil

Paper / Cardboard Packaging (kg)

700.0

Plastics (kg)

Nil

Chemical Waste (kg)

Nil

General Waste Disposed of to NENT Landfill (m3)

43.9

* Other Contracts include Proposed Rural Theme Park-Yuen Long, Tai Tong Lychee Garden, CV/2006/01, DC/2007/06, DC/2007/08, DC/2008/12, DC/2007/17, HY/2007/09 and Ocean Park.

 

9      During the reporting period, seven environmental complaints were received. One environmental complaint was received by EPD on 10 July 2009 regarding construction dust from the Outfall Construction Site. The complaint was considered not justifiable since no action & limit level exceedance on construction dust were identified. Two environmental complaints were received by SOR on 29 July and 11 August 2009 regarding daytime construction noise exceedances recorded at Greenview Terrace (NSR9) on 8, 22, 23, 27 and 29 July 2009 and a large amount dust generated at the outfall construction site. Two other environmental complaints from Greenview Terrace were received by SOR via Apple Daily on 12 August 2009 and by EPD on 14 August 2009. These complaints also referred to the daytime construction noise level exceedances and construction dust generated at the outfall construction site. One environmental complaint from Long Bench Garden was received by SOR on 17 August 2009 regarding noise nuisance generated from the daytime construction work (rock-breaking) in Portion D of the construction site.  The documented complaint on noise nuisance was considered to trigger the action level and the Contractor should enhance the on-site noise mitigation measures. One complaint was received on 7 September 2009 regarding daytime construction noise exceedance recorded at Greenview Terrace (NSR9) on 22 August 2009 at the outfall construction site.

10   No Notification of Summons was received since the commencement of the Project.


1                               Introduction

1.1.1                        The Drainage Services Department (DSD) proposes to construct a tunnel of an internal diameter of 6.5m and length 5.13km, with the purpose to alleviate the flooding risk in Tsuen Wan and Kwai Chung.

1.1.2                        This project is a Designated Project under Schedule 2 Part I Category Q, of the Environmental Impact Assessment Ordinance (EIAO) as part of the proposed Tsuen Wan Drainage Tunnel (TWDT) passes underneath the existing Tai Mo Shan Country Park.  An Environmental Impact Assessment (EIA) Study has therefore been undertaken to provide information on the nature and extent of environmental impacts arising from the construction and operation of the proposed designed project and related activities taking place concurrently.  From the EIA the recommendations for monitoring contained herein, are made.

1.1.3                        The Maeda-CREC-SELI Joint Venture (MCSJV) was awarded by DSD with the Contract – Design and Construction of Tsuen Wan Drainage Tunnel.

1.1.4                        Hyder was commissioned by the MCSJV as the ET to implement an EM&A program in accordance with the EM&A Manual.  The proposed tunnel section flows from the junction of Shing Mun Road and Wo Yi Hop Road and discharges to south of Yau Kom Tau underneath Castle Peak Road as shown in Appendix A.

1.1.5                        The construction works of the Project commenced on January 2008.  This is the sixth quarterly EM&A report summarising the impact monitoring results and audit findings of the EM&A program during the reporting period in July – September 2009.

2                               Project Information

2.1                      Project Organization and Management Structure

2.1.1                        The organization chart and lines of communication with respect to the on-site environmental management are shown in Appendix B.

2.2                      Construction Progress

2.2.1                        It is anticipated that the overall project programme from the detail design to completion of all civil works shall take approximately 54 months.  The construction programme is presented in Appendix C.

2.2.2                        The major construction activities undertaken in the reporting quarter are:

·          Site cleaning and tidying at I-1, I-2, I-3 and Outfall;

·          Tree transplanting at I-1, I-2, I-3 and Outfall;

·          Drilling rig at I-3 and Outfall;

·          Soil nailing at I-1, I-3 and Outfall;

·          Breaking up exiting boulder at I-1, I-2, I-3 and Outfall;

·          Formation of access road at I-3 and Outfall;

·          Erosion control mat and green wire mesh at Outfall;

·          Excavation and Lateral Support (ELS) at I-3;

·          Construction of skin wall at I-2 and I-3; and

·          Formation of steel platform at I-2;

2.3                      Mitigation Measures

2.3.1                        The environmental mitigation measures that have been implemented and their status are given in Appendix D.

3                               EM&A Requirement

3.1                      General

3.1.1                        The EM&A requirements are stipulated in the EM&A Manual.  The principal purposes of the EM&A program are to assess the compliance with applicable environmental legislation and associated regulations; to ensure the implementation of mitigation measures specified in the EM&A Manual; and to identify any remedial works necessary for redressing any unacceptable or unanticipated environmental impacts.

3.2                      EM&A on Air Quality; Noise and Water Quality

Monitoring Parameters

3.2.1                        The air quality, noise and water quality frequencies and parameters are shown in Table 3-1.


Type of Monitoring

Monitoring Station ID

Parameter

Frequency

Air Quality Monitoring

ASR1; ASR3; ASR8 and ASR9

1-hour TSP

Once every 6-day

Noise Monitoring

NSR1; NSR3; NSR6; NSR8 and NSR9

Leq (30 min.)

Once every week

Water Quality Monitoring

I-1; I-1-C; I-2; I-2-C; I-3; I-3-C

DO (mg/l)

Three days per week

SS (mg/l)

Turbidity (NTU)

pH

Temperature (oC)

Table 3-1          Frequency of Air Quality; Noise and Water Quality Monitoring

3.3                      Monitoring Locations

3.3.1                        The monitoring locations for air quality; noise and water quality are shown in Tables 3-2; 3-3; 3-4 and Appendix E.

Monitoring Station ID

Name of Premises

Floor Level

ASR1

Sik Sik Yuen Ho Fung College

G/F

ASR3

Hong Hoi Chee Hong Temple

Podium

ASR8

Beach Tower (Long Beach Gardens)

G/F

ASR9

Greenview Terrace (Block 1)

G/F

Table 3-2       Air Quality Monitoring Locations

Monitoring Station ID

Name of Premises

Floor Level

NSR1

Sik Sik Yuen Ho Fung College

G/F

NSR3

Hong Hoi Chee Hong Temple

Podium

NSR6

Squatters

G/F

NSR8

Beach Tower (Long Beach Gardens)

G/F

NSR9

Greenview Terrace (Block 1)

Podium (up to 6 July2009)

Roof* (from 16 July 2009)

* The noise monitoring location of NSR9 had been adjusted at rooftop from 16 July 2009.

Table 3-3       Noise Monitoring Locations


Monitoring Station ID

Name of Premises

I-1

Intake I-1

I-1-C

Control of Intake I-1

I-2

Intake I-2

I-2-C

Control of Intake I-2

I-3

Intake I-3

I-3-C^

Control of Intake I-3

O-1 (FT)*

Outfall 1During Flood Tide

O-1 (ET)*

Outfall 1During Ebb Tide

O-1-C (FT)*#

Control of Outfall O-1 During Flood Tide

O-1-C (ET)*#

Control of Outfall O-1 During Ebb Tide

Note:   *Water quality monitoring will be undertaken when the construction of rip rap is in placed.

#Note that there are two control stations for Outfall O-1; one for sampling during flood tide and one for sampling during ebb tide.  Only one of those control stations for Outfall O-1 shall be sampled during each sampling.  Control station to be sampled will be determined base on the tidal information provided by the Hong Kong Observatory.

^ The upper stream location (I-3-C^) had been relocated from end of February 2009 due to coarse stone blockage.

Table 3-4          Water Quality Monitoring Locations

3.4                      Performance Limits (AL Levels)

3.4.1                        In accordance with the EM&A Manual; the appropriate Action and Limit Levels for Air Quality; Noise and Water Quality were established and are presented in Table 3-5; Table 3-6 and Table 3-7.  Should non-compliance of the air quality; noise and water quality criteria occur; actions in accordance with the Event / Action Plan stipulated in contract specific EM&A Manual should be carried out.

Station

1-hr TSP Level in μg/m3

Action Level

Limit Level

ASR1

307

500

ASR3

327

500

ASR8

337

500

ASR9

329

500

Table 3-5          Action & Limit Levels for Air Quality


Time Period

Action

Limit

0700 – 1900 hrs on normal weekdays

When one documented complaint is received

75 dB(A)*

*           For educational establishments the limit level shall be 70dB(A) and reduced to 65dB(A) during examination periods between 0700-1900 hrs on normal weekdays.

Table 3-6          Action & Limit Levels for Noise

Parameters

Action

Limit

DO in mg/l

(Surface; Middle & Bottom)

Surface & Middle

5%-ile of baseline data for surface and middle layer.

 

Bottom

5%-ile of baseline data for bottom layer.

Surface & Middle

4mg/l except 5mg/l for FCZ or

1%-ile of baseline data for surface and middle layer

Bottom

2mg/l or 1%-ile of baseline data for bottom layer

SS in mg/l

(Depth-averaged)

95%-ile of baseline data or 120% of upstream control station’s SS at the same tide of the same day

99%-ile of baseline or 130% of upstream control station’s SS at the same tide of the same day and specific sensitive receiver water quality requirements (e.g. required suspended solids levels for concerned sea water intakes)

Turbidity (Tby) in NTU (Depth-averaged)

95%-ile of baseline data or 120% of upstream control station’s Tby at the same tide of the same day

99%-ile of baseline or 130% of upstream control station’s Tby at the same tide of the same day

Notes:

·         For DO; non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

·         For SS and Tby; non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

·         All the figures given in the table are used for reference only and the EPD may amend the figures whenever it is considered as necessary.

Table 3-7          Action & Limit Levels for Water Quality

3.5                      Monitoring Result

3.5.1                        All measured air quality monitoring levels were complying with the Action and Limit Levels in the reporting period. A summary of air quality monitoring results is presented in Table 3-8 and Appendix F.

Monitoring Station

1-hour TSP (mg/m3)

Action Level

Limit Level

Range

(mg/m3)

(mg/m3)

ASR1

36.8

-

209.5

307

500

ASR3

22.7

-

197.5

327

500

ASR8

21.6

-

205

337

500

ASR9

41.1

-

239.5

329

500

Italic indicates the exceedances of Action Levels

Bold indicates the exceedances of Limit Levels

Table 3-8          Summary of Air Quality Monitoring Results

3.5.2                        Six Action Level exceedances for noise monitoring was recorded in the reporting quarter as six noise complaints were received on 29 July, 11, 12, 14 and 17 August as well as 7 September 2009. All measured noise monitoring levels were complying with the Limit Level in the reporting period. A summary of noise monitoring results is presented in Table 3-9 and Appendix F.

Monitoring Station

Leq (30mins) dB(A)

Limit Level

Range

dB(A)

NSR1

64

-

69

70

NSR3

68

-

73

75

NSR6

52

-

59

75

NSR8

63

-

69

75

NSR9

70

-

75

75

Bold indicates the exceedances of Limit Levels

Table 3-9          Summary of Impact Noise Monitoring Results

3.5.3                        A summary of water quality monitoring results is presented in Table 3-10 and Appendix F.

3.5.4                        No water quality monitoring was done on 4 July, 27 July and 12 August 2009 due to thunderstorm warning.

3.5.5                        None of exceedance related to project construction activities was recorded during reporting quarter but a total of ten non project related exceedances were recorded.

3.5.6                        A total of eight non project related exceedances were recorded in July 2009 including:

§                exceedance of Control Limit Level of SS (130% higher than I-1-C) recorded on 10 July and exceedance of Control Action Level of SS (120% higher than I-1-C) recorded on 20 July at I-1 were below baseline Action / Limit Level and were within the range of baseline SS concentration. No direct disturbance was observed from the site. The exceedance was considered to be contributed by natural variation and no action was therefore required.

§                exceedances of Control Limit Level of SS (130% higher than I-2-C) recorded at I-2 on 6, 8, and 13 July were below baseline Action / Limit Level and were within the range of baseline SS concentration. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and no action was therefore required.

§                exceedance of Baseline Limit Level of turbidity recorded at I-2 on 24 July was below the turbidity level at 1-2-C. The exceedance of Baseline Limit Level of SS recorded on 24 July at I-2 was slightly above the SS level at I-2-C and still complied within the Action and Limit levels at control station (I-2-C). No direct disturbance was observed from the site. The exceedances were considered to be contributed by other sources at upstream and no action was therefore required.

§                exceedance of Control Action Level of SS (120% higher than I-3-C) recorded on 6 July and exceedance of Control Limit Level of SS (130% higher than 1-3-C) recorded on 10 July at I-3 were below both baseline Action and Limit Levels and were within the range of baseline SS concentration. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and no action was therefore required.

§                exceedance of Baseline Action Level of turbidity recorded on 20 July at I-3 was below the turbidity level at 1-3-C and no exceedance of SS level was recorded for this monitoring. No direct disturbance was observed from the site. The exceedances were considered to be contributed by natural variation and no action was therefore required.

3.5.7                        A total of three non project related exceedances were recorded in August 2009 including:

§                exceedance of Control Limit Level of SS (130% higher than I-1-C) recorded at I-1 on 14 August 2009 was below baseline Action / Limit Level and was within the range of baseline SS concentration. No direct disturbance was observed from the site. The exceedance was considered to be contributed by natural variation and no action was therefore required.

§                exceedance of Control Action Level of SS (120% higher than I-1-C) recorded at I-1 on 28 August 2009 was below baseline Action / Limit Level and was within the range of baseline SS concentration. No direct disturbance was observed from the site. The exceedance was considered to be contributed by natural variation and no action was therefore required.

§                exceedance of Control Limit Level of SS (130% higher than I-2-C) recorded at I-2 on 14 August 2009 was below baseline Action / Limit Level and was within the range of baseline SS concentration. No direct disturbance was observed from the site. The exceedance was considered to be contributed by natural variation and no action was therefore required.

3.5.8                        A total of three non project related exceedances were recorded in September 2009  including:

§                exceedance of Control Limit Level of SS (130% higher than I-1-C) recorded at I-1 on 11 September 2009 was below baseline Action / Limit Level and was within the range of baseline SS concentration. No direct disturbance was observed from the site. The exceedance was considered to be contributed by natural variation and no action was therefore required.

§                exceedance of Control Action Level of SS (120% higher than I-1-C) recorded at I-1 on 16 September 2009 was below baseline Action / Limit Level and was within the range of baseline SS concentration. The exceedance was considered to be contributed by natural variation and no action was therefore required.

§                exceedance of Control Limit Level of SS (130% higher than I-3-C) recorded at I-3 on 14 September 2009 was below baseline Action / Limit Level and was within the range of baseline SS concentration. No direct disturbance was observed from the site. The exceedance was considered to be contributed by natural variation and no action was therefore required

3.5.9                        The above mentioned exceedances were considered as non project related, however, proper mitigation measures had been implemented during measurements. Details of the above mentioned investigations could be referred to the notifications of exceedances as enclosed in Appendix G.


Monitoring Station

Temperature

DO (mg/L)

pH

Turbidity (NTU)

Suspended Solid (mg/L)

Range

Range

Action / Limit Level

Range

Range

Action / Limit Level

Range

Action / Limit Level

I-1

25.70

-

29.00

3.43

-

7.32

3.42

/

3.34

5.32

-

7.76

2.07

-

7.47

9.75

/

12.47

2.00

-

8.30

8.85

/

10.17

I-1-C

25.25

-

28.80

3.15

-

7.59

 

-

 

5.28

-

7.86

2.21

-

7.63

 

-

 

2.00

-

8.70

 

-

 

I-2

25.15

-

28.80

3.71

-

7.40

3.66

/

3.63

5.41

-

7.81

1.03

-

40.40

6.63

/

6.99

2.00

-

59.45

7.68

/

8.34

I-2-C

25.50

-

28.90

3.16

-

7.55

 

-

 

5.50

-

7.66

1.09

-

41.45

 

-

 

2.00

-

58.85

 

-

 

I-3

25.30

-

28.70

3.74

-

7.50

3.65

/

3.51

5.41

-

7.71

1.17

-

4.00

3.99

/

4.18

2.00

-

4.10

6.13

/

7.23

I-3-C

25.35

-

28.55

3.49

-

7.19

 

-

 

5.38

-

7.72

1.44

-

4.38

 

-

 

2.00

-

2.85

 

-

 

 

Note:   Italic indicates the exceedances of Action Levels

Bold indicates the exceedances of Limit Levels

Table 3-10        Summary of Impact Water Quality Monitoring Results

 


4                               Quarterly Summary; Environmental Condition and Non-Compliance Records

4.1                      Summary of Waste Disposal Records

4.1.1                        According to the information provided by the Contractor; the quantities of C&D materials in the reporting period are summarized in Table 4-1. 

Status of Waste Management

July 09

August 09

September 09

Inert C&D Material Disposed of to Public Fill at Tuen Mun (m3)

3,219.0

6,403.3

3,774.2

Inert C&D Material Reused in other Contract* (m3)

3,615.0

2,695.0

1,970.0

Metals Generated (kg)

Nil

Nil

Nil

Paper / Cardboard Packaging (kg)

400.0

Nil

300

Plastics (kg)

Nil

Nil

Nil

Chemical Waste (kg)

Nil

Nil

Nil

General Waste Disposed of to NENT Landfill (m3)

9.6

11.7

22.6

* Other Contracts include Proposed Rural Theme Park-Yuen Long, Tai Tong Lychee Garden, CV/2006/01, DC/2007/06, DC/2007/08, DC/2008/12, DC/2007/17, HY/2007/09 and Ocean Park.

Table 4-1          Waste Generated from July to September 2009

4.2                      Weather Conditions

4.2.1                        The weather conditions during the period from July to September 2009 were mainly sunny, cloudy and sometimes fine weather. 

4.3                      Summary of Project-Related Exceedances

4.3.1                        Summary of exceedance results are summarized in Table 4-2.  For the exceedances that are considered to be non-related to the construction activities; please refer to the monthly EM&A reports separately. Appendix G shows the Interim Notifications of Environmental Quality Limits Exceedances recorded in the reporting period.

Environmental Monitoring

Total No. of Measurement

Action Level Exceedance

% of Action Level Exceedance

Limit Level Exceedance

% of Limit Level Exceedance

Air Quality

192

0

0

0

0

Noise

79

6 (complaints)

7.6%

0

0

Water

222

0

0

0

0

Table 4-2          Summary of Project- related Exceedances

 

5                               Complaint

5.1.1                        A complaint hotline at 9850 3241 of the Contractor has been established for the Project. 

5.1.2                        During the reporting period, seven environmental complaints were received.

5.1.3                        One environmental complaint was received by EPD on 10 July 2009 regarding construction dust from the Outfall Construction Site. The complaint was considered not justifiable since no action & limit level exceedance on construction dust were identified. Detail of the complaint investigation can be referred to Appendix H.

5.1.4                        Two environmental complaints were received by SOR on 29 July and 11 August 2009 regarding daytime construction noise exceedances recorded at Greenview Terrace (NSR9) on 8, 22, 23, 27 and 29 July 2009 and a large amount dust generated at the outfall construction site. Two other environmental complaints from Greenview Terrace were received by SOR via Apple Daily on 12 August 2009 and by EPD on 14 August 2009. These complaints also referred to the daytime construction noise level exceedances and construction dust generated at the outfall construction site. One environmental complaint was received by SOR on 7 September 2009 regarding daytime construction noise exceedance recorded at Greenview Terrace (NSR9) on 22 August 2009 at the outfall construction site. In accordance with the 1-hr TSP monitoring from July to August 2009, all 1-hr TSP concentrations at ASR9 were below the established Action and Limit Levels and no exceedance of 1-hr TSP was recorded during this period. However, the dust complaint on 22 July 2009 was found due to the soil nailing works. The documented complaints for noise were considered to trigger the action level and the Contractor was reminded to enhance the on-site noise mitigation measures, such as tools box talk for Contractor’s Team was carried out for reminding that the movable barrier should be placed to the breaking activities as much as possible, three movable noise barriers had been placed on site and the movable noise barriers were modified, a joint filler wall was installed at the vertical face of westbound to mitigate the noise rebound from the vertical face to high level of Greenview Terrace and noise monitoring frequency would be maintained twice per week until no further complaint from Greenview Terrace. Detail of the complaint investigation can be referred to Appendix H.

5.1.5                        One environmental complaint from Long Beach Garden was received by SOR on 17 August 2009 regarding noise nuisance generated from the daytime construction work (rock-breaking) in Portion D of the construction site. The documented complaint on noise nuisance was considered to trigger the action level and the Contractor should enhance the on-site noise mitigation measures. The enhanced mitigation measures included: (1) Tools box talk for construction team was carried out for reminding that the movable barrier was placed to the breaking activities as much as possible. (2) The movable noise barriers had been placed on site and also had been placed facing to the Long Bench Garden. (3) A joint filler wall was installed at the vertical face of slope to mitigate the noise rebound. (4) Noise monitoring frequency was increased to twice per week starting from the week of 24 August 2009. All measured noise levels were complied with the limit level in accordance with the EIAO-TM during the reporting period.  No further complaint was received from Long Bench Garden in September 2009. Detail of the complaint investigation can be referred to Appendix H.

5.1.6                        Cumulative statistics of environmental complaints are shown in Table 5-1.

Complaints Received in the Reporting Period

Cumulative Number of Complaints

7

10

Table 5-1          Cumulative Statistic of Environmental Complaints

6                               Summary of Notification of Summons; Successful Prosecutions and Corrective Actions

6.1.1                        No summons and successful prosecution was received during the reporting period.

6.1.2                        Cumulative statistics of Notification of Summon; Successful Prosecutions and Convictions are shown in Table 6-1.

Notification of Summons

Successful Prosecution

July – September 09

Cumulative

July – September 09

Cumulative

0

0

0

0

Table 6-1          Cumulative Statistics of notification of summons and successful prosecutions

7                               Comments; Recommendations and Conclusion

7.1.1                        During the reporting period, no project related exceedance of air quality was recorded but six Action Level exceedances of noise monitoring were recorded.  Exceedances of water quality monitoring were recorded but none of these exceedances were related to Project’s construction activities.

7.1.2                        Waste management mitigation measures have been implemented by the Contractor within the reporting period.  Waste figures during the reporting period are summarized in the below table.


Status of Waste Management

 

Inert C&D Material Disposed of to Public Fill at Tuen Mun (m3)

13,396.5

Inert C&D Material Reused in other Contract* (m3)

8,280.0

Metals Generated (kg)

Nil

Paper / Cardboard Packaging (kg)

700.0

Plastics (kg)

Nil

Chemical Waste (kg)

Nil

General Waste Disposed of to NENT Landfill (m3)

43.9

* Other Contracts include Proposed Rural Theme Park-Yuen Long, Tai Tong Lychee Garden, CV/2006/01, DC/2007/06, DC/2007/08, DC/2008/12, DC/2007/17, HY/2007/09 and Ocean Park.

7.1.3                        During the reporting period, seven environmental complaints were received. One environmental complaint was received by EPD on 10 July 2009 regarding construction dust from the Outfall Construction Site. The complaint was considered not justifiable since no action & limit level exceedance on construction dust were identified. Two environmental complaints were received by SOR on 29 July and 11 August 2009 regarding daytime construction noise exceedances recorded at Greenview Terrace (NSR9) on 8, 22, 23, 27 and 29 July 2009 and a large amount dust generated at the outfall construction site. Two other environmental complaints from Greenview Terrace were received by SOR via Apple Daily on 12 August 2009 and by EPD on 14 August 2009. These complaints also referred to the daytime construction noise level exceedances and construction dust generated at the outfall construction site. One environmental complaint from Long Bench Garden was received by SOR on 17 August 2009 regarding noise nuisance generated from the daytime construction work (rock-breaking) in Portion D of the construction site.  The documented complaint on noise nuisance was considered to trigger the action level and the Contractor should enhance the on-site noise mitigation measures. One complaint was received on 7 September 2009 regarding daytime construction noise exceedance recorded at Greenview Terrace (NSR9) on 22 August 2009 at the outfall construction site.

7.1.4                        No Notification of Summons has been received since the commencement of the Project.

7.1.5                        There were totally seven environmental complaints received during the reporting period and the Contractor was reminded to enhance the on-site noise mitigation measures. All the noise mitigation measures mentioned in Section 5.1.4 and 5.1.5 were implemented during the reporting period and no exceedances of Limit levels of the measured noise levels were recorded .


 

Appendix A

Site Map and Works Area


 

Appendix B

Organization Chart


 

Appendix C

Work Programme


 

Appendix D

Implementation Status of Environmental Mitigation Measures


 

Appendix E

Monitoring Locations


 

Appendix F

Monitoring Results


 

Appendix G

Interim Notifications of Environmental Quality Limits Exceedances


 

Appendix H

Complaint Log