Table 3‑1 Air Quality Monitoring Equipment
Table 3‑2 Air Quality Monitoring Locations
Table 3‑3 Action & Limit Levels for Air
Quality
Table 3‑4 Event/Action Plan for Air Quality
Table 3‑5 Noise Monitoring Equipment
Table 3‑6 Noise Monitoring Locations
Table 3‑7 Action & Limit Levels for Noise
Table 3‑8 Event/Action Plan for Noise
Table 3‑9 Water Quality Monitoring Equipment
Table 3‑10 Water Quality Monitoring Locations
Table 3‑11 Action/Limit Levels for Water Quality
Table 3‑12 Event/Action Plan for Water Quality
Table 4-1 Air
Quality Monitoring Results
Table 4-2 Noise
Monitoring Results
Table 4-3 Summary
of Exceedances for I-1
Table 4-4 Summary
of Exceedances for I-2
Table 4-5 Summary
of Exceedances for I-3
Table 4-6 Water
Quality Monitoring Results
Table 4-7 Summary
of Project-Related Exceedances
Table 5-1 Waste Generated in April 2010
Table 6-1 Site
Inspection by ET
Table 7-1 Cumulative
Statistic of Environmental Complaint
Table 8-1 Cumulative
Statistics of Notification of Summons and Successful Prosecutions
|
APPENDICES |
|
|
Appendix A Site Map and Works Area
Appendix C Construction Programme
Appendix D Implementation Status of Environmental
Mitigation Measures
Appendix E Status of License and Permit
Appendix F Calibration Certificates
Appendix G Monitoring Locations
1.
Drainage
Services Department (DSD) has awarded the contract for the Design and
Construction of Tsuen Wan
Drainage Tunnel (hereafter referred to as the “Project”) to Maeda-CREC-SELI
Joint Venture (MCSJV). MCSJV has
appointed Hyder Consulting Limited (HCL) as the Environmental Team (ET) to
undertake the Environmental Monitoring and Audit (EM&A) works in accordance
with the Environmental Monitoring and Audit Manual (EM&A Manual) and
Environmental Permit (EP). Commencement
of the construction work had been notified to the Environmental Protection
Department (EPD) in January 2008. This
Monthly EM&A Report summarises the EM&A works undertaken in April 2010.
2.
According
to the EM&A Manual, there are four designated air quality monitoring
locations, five designated noise monitoring locations and four water quality
monitoring locations during the construction phase: (i)
Sik Sik Yuen Ho Fung
College (ASR 1, NSR 1 and Intake I-1); (ii) Hong Hoi Chee
Hong Temple (ASR 3, NSR 3 and Intake I-2); (iii) Squatters (NSR 6 and Intake
I-3); (iv) Beach Tower (Long Beach Gardens) (ASR 8, NSR 8 and Outfall O-1); and
(v) Greenview Terrace (Block 1) (ASR 9, NSR 9 and
Outfall O-1).
3.
During the non restricted hours, major construction activities
undertaken by the Contractor at TWDT included site cleaning and tidying at I-1, I-2,
I-3 and Outfall; drilling for shaft excavation at I3; pre-bored
H-pile drilling for muck hopper and conveyor support at Outfall; breaking up
exiting boulder at Outfall and I3; excavation of man access shaft & vortex
shaft at I2; installation of steel liner at air vent shaft at I2; erosion control mat and green wire mesh
at Outfall; cascade and channel modification concrete structure works at
I-1; installation of noise enclosure to gantry crane
structure at I2; concreting of air vent shaft at I2; soil nail works and pipe
jacking pit excavation at portion G at I2; and pre-assembly of TBM and TBM
drilling of the tunnel at Outfall. There was no construction
activities carried out during restricted hours within the reporting
month.
4.
No water quality monitoring was
carried out on 2 and 5 April 2010 because no construction works are carried out
during holiday. No exceedances have been
recorded for air quality, noise and water quality monitoring during
the reporting month.
5.
The status
of waste generation in the reporting month are:
·
A total of 733.6 m
·
About 10.2 m3
general waste was disposed of to NENT Landfill;
·
300 kg paper/cardboard
packaging was recycled;
·
No metals was generated in the reporting month;
·
No plastic waste was disposed of in the reporting month; and
·
No chemical waste was
disposed of in the reporting month.
6.
In this
reporting month, two site inspections and one monthly site audit were carried
out by ET and Independent Environmental Checker (IEC) respectively, to ensure
proper implementation of environmental mitigation measures specified in the
EM&A Manual and compliance with environmental legislation. All observations, which were recorded on the
inspection checklists, were passed to the Contractor together with the ET’s
recommendations.
7.
As advised
by the Contractor and verified by ET:
·
No
non-compliance regarding the site inspection was received in the reporting
month;
·
No environmental complaint was
received during the reporting month; and
·
No summons
and prosecution was received in this reporting month.
8.
The major
construction works for the upcoming three months will be:
·
Site Cleaning and Tidying at I1, I2, I3 and Outfall;
·
Erection of Muck Hopper and Conveyor Support steel structure
at Outfall;
·
Breaking Up Exiting Boulder at Outfall and I3;
·
Drilling and Excavation of Man Access Shaft & Vortex
Shaft at I2;
·
Construction of Approach Channel Structure at I2;
·
Erosion Control Mat and Green Wire Mesh at Outfall;
·
Cascade and Channel Modification concrete structure works at I-1;
·
Construction of Skin Wall at I3;
·
Assembly of TBM, TBM Drilling of the Tunnel at Outfall;
·
Installation of noise enclosure at Outfall and I2;
·
Soil nail works and pipe jacking pit excavation at Portion G
at I2;
·
Drilling and Excavation of Spiral Ramp at Outfall;
·
Drilling and Excavation of Vortex Shaft at I3; and
·
Restricted Hours – Delivery of TBM Backup Plants.
1.1.1
The
Drainage Services Department (DSD) proposed to construct a tunnel with an
internal diameter of
1.1.2
This
project is a Designated Project under Schedule 2 Part I Category Q, of the
Environmental Impact Assessment Ordinance (EIAO) as part of the proposed Tsuen Wan Drainage Tunnel (TWDT) passes underneath the
existing Tai Mo Shan Country Park. An
Environmental Impact Assessment (EIA) Study has therefore been undertaken to
provide information on the nature and extent of environmental impacts arising
from the construction and operation of the proposed designed project and
related activities taking place concurrently.
From the EIA the recommendations for monitoring contained herein, are
made.
1.1.3
The
Maeda-CREC-SELI Joint Venture (MCSJV) was awarded by DSD with the Contract – Design
and Construction of Tsuen Wan Drainage Tunnel.
1.1.4
Hyder was
commissioned by the MCSJV as the Environmental Team (ET) to implement an
EM&A program in accordance with the EM&A Manual. The proposed tunnel section flows from the
junction of Shing Mun Road
and Wo Yi Hop Road and discharges to south of Yau Kom Tau underneath Castle
Peak Road as shown in Appendix A.
1.1.5
The
construction works of the Project was commenced in January 2008. This is the twenty-fifth monthly EM&A report summarising the impact monitoring
results and audit findings of the EM&A program in April 2010.
2.1 Project Organization and Management Structure
2.1.1
The
organization chart and lines of communication with respect to the on-site
environmental management are shown in Appendix B.
2.2.1
The overall project programme from the detail design to
completion of all civil works shall take approximately 54 months. The construction programme is presented in Appendix
C.
2.2.2
The major construction activities
undertaken in the reporting month were:
·
Site cleaning and tidying at I-1,
I-2, I-3 and Outfall;
·
Drilling for shaft excavation at I3;
·
Pre-bored H-pile drilling for Muck Hopper and Conveyor
Support at Outfall;
·
Breaking Up Exiting Boulder at Outfall and I3;
·
Excavation of Man Access Shaft & Vortex Shaft at I2;
·
Installation of steel liner at Air Vent Shaft at I2;
·
Erosion Control Mat and Green Wire Mesh at Outfall;
·
Cascade and Channel Modification concrete structure works at I-1;
·
Installation of Noise Enclosure to gantry crane structure at
I2;
·
Concreting of Air Vent Shaft at I2;
·
Soil nail works and pipe jacking pit excavation at Portion G
at I2; and
·
Pre-assembly of TBM and TBM Drilling of the Tunnel at Outfall.
2.2.3
There was
no construction activities carried out for TWDT during restricted hours within the reporting month.
2.3.1
The
implemented environmental mitigation measures and their statuses are given in
Appendix D.
2.4 Status of License and Permit
2.4.1 A summary of relevant permits and licences for the Project is given in Appendix E.
3.1.1
1-hour
Total Suspended Particulates (TSP) levels are measured at the designated air
monitoring locations in accordance with the EM&A Manual. Information such
as date of monitoring, duration, weather condition, equipment
used and monitoring results were recorded on the field data sheet developed for
the Project. The monitoring results are presented in Section 4.
3.1.2
1-hour TSP
monitoring is carried out under typical weather conditions (with no adverse
weather such as typhoon signal or rain storm warning) three times every six
days using High Volume Air Samplers (HVASs).
Monitoring should be conducted in accordance with the standard sampling
method as set out in High Volume Method for Total Suspended Particulates, Part
50 Chapter 1 Appendix B, Title 40 of the Code of
Federal Regulations of the USEPA.
3.1.3
After each
sampling, the filter paper loaded with dust is kept in a clean and tightly
sealed plastic bag. The filter paper is then re-conditioned in desiccators for
24 hours before obtaining the weight under laboratory conditions.
3.1.4
The average
concentrations of the TSP are calculated based on the following information
obtained from monitoring:
·
Flow rate;
·
Weight of
the filter paper before and after sampling; and
·
Sampling
period indicated by the elapsed-time meter.
3.1.5
All samples
should be kept in good condition (i.e. stored in sealed plastic bags, with brief
description of the monitoring dates and locations) for a period of 6 months
before disposal. Sample analysis is carried out by ALS Technichem (HK) Pty Limited
(HOKLAS Registration Number 066).
Monitoring Equipment and Calibration
3.1.6
High Volume
Air Samplers (HVASs) are used for 1-hour TSP monitoring to comply with the
USEPA specifications in Appendix B Part 5 - Reference Method for the
Determination of Suspended Particulate matter in the Atmosphere (High-Volume
Method) of the Code of Federal Regulation dated June 1, 1991.
3.1.7
All HVASs
are calibrated before commencement of monitoring using standard orifice
5-points calibration method with orifice calibrator to determine the actual
flow rate of each HVAS. This shall be
used for the calculation of the TSP level.
Calibration Kit Model - TE
|
Equipment Type |
Model |
Serial Number |
Calibration Orifice Number |
Location |
|
HVAS |
BM2000HX |
4994 |
1559 |
ASR 1 |
|
HVAS |
BM2000HX |
5875 |
1559 |
ASR 3 |
|
HVAS |
TE5005X |
0390 |
1559 |
ASR 8 |
|
HVAS |
TE5005X |
0646 |
1559 |
ASR 9 |
Table 3‑1 Air Quality Monitoring Equipment
3.1.8
Four
designated air quality-monitoring locations were identified in the contract
specific EM&A manual. They are
listed in Table
3‑2 below and shown in Appendix G.
|
Monitoring
Station ID |
Name of
Premises |
Floor
Level |
|
ASR1 |
|
G/F |
|
ASR3 |
|
Podium |
|
ASR8 |
|
G/F |
|
ASR9 |
Greenview Terrace (Block 1) |
G/F |
Table 3‑2 Air Quality Monitoring Locations
3.1.9
The Action
and Limit Levels for the 1-hour TSP monitoring is shown in Table
3‑3. In case exceedances of Action and/or Limit levels for air quality
occur, Event Contingency Plans (ECPs) would be implemented. The ECPs for Action and Limit levels exceedances are shown in Table
3‑4.
|
Station |
1-hr TSP Level in μg/m3 |
|
|
Action Level |
Limit Level |
|
|
ASR 1 |
307 |
500 |
|
ASR 3 |
327 |
500 |
|
ASR 8 |
337 |
500 |
|
ASR 9 |
329 |
500 |
Table 3‑3 Action & Limit Levels for Air
Quality
|
EVENT |
ACTION |
|||||||
|
ET |
IEC |
SOR |
CONTRACTOR |
|||||
|
ACTION
LEVEL |
||||||||
|
Exceedance
for one sample |
· Identify source, investigate the causes of exceedance and propose remedial measures; · Inform IEC and SOR; · Repeat measurement to confirm finding; · Increase monitoring frequency to daily. |
· Check monitoring data submitted by ET; · Check Contractor’s working method. |
· Notify Contractor. |
· Rectify any unacceptable practice; · Amend working methods if appropriate. |
||||
|
Exceedance
for two or more consecutive samples |
· Identify source; · Inform IEC and SOR; · Advise SOR on the effectiveness of the proposed remedial measures; · Repeat measurements to confirm findings; · Increase monitoring frequency to daily; · Discuss with IEC and Contractor on remedial actions required; · If exceedance continues, arrange meeting with IEC and SOR; · If exceedance stops, cease additional monitoring. |
· Check monitoring data submitted by ET; · Check Contractor’s working method; · Discuss with ET and Contractor on possible remedial measures; · Advise the ET on the effectiveness of the proposed remedial measures; · Supervise Implementation of remedial measures. |
· Confirm receipt of notification of exceedance in writing; · Notify Contractor; · Ensure remedial measures properly implemented. |
· Submit proposals for remedial to SOR within 3 working days of notification; · Implement the agreed proposals; · Amend proposal if appropriate. |
||||
|
LIMIT
LEVEL |
||||||||
|
Exceedance
for one sample |
· Identify source, investigate the causes of exceedance and propose remedial measures; · Inform IEC, SOR, Contractor and EPD; · Repeat measurement to confirm finding; · Increase monitoring frequency to daily; · Assess effectiveness of Contractor’s remedial actions and keep IEC, EPD and SOR informed of the results. |
· Check monitoring data submitted by ET; · Check Contractor’s working method; · Discuss with ET and Contractor on possible remedial measures; · Advise SOR on the effectiveness of the proposed remedial measures; · Supervise implementation of remedial measures. |
· Confirm receipt of notification of exceedance in writing; · Notify Contractor; · Ensure remedial measures properly implemented. |
· Take immediate action to avoid further exceedance; · Submit proposals for remedial actions to IEC within 3 working days of notification; · Implement the agreed proposals; · Amend proposal if appropriate. |
||||
|
Exceedance
for two or more consecutive samples |
· Notify IEC, SOR, Contractor and EPD; · Identify source; · Repeat measurement to confirm findings; · Increase monitoring frequency to daily; · Carry out analysis of Contractor’s working procedures to determine possible mitigation to be implemented; · Arrange meeting with IEC and SOR to discuss the remedial actions to be taken; · Assess effectiveness of Contractor’s remedial actions and keep IEC, EPD and SOR informed of the results; · If exceedance stops, cease additional monitoring. |
· Discuss amongst SOR, ET, and Contractor on the potential remedial actions; · Review Contractor’s remedial actions whenever necessary to assure their effectiveness and advise SOR accordingly; · Supervise the implementation of remedial measures. |
· Confirm receipt of notification of exceedance in writing; · Notify Contractor; · In consultation with the IEC, agree with the Contractor on the remedial measures to be implemented; · Ensure remedial measures properly implemented; · If exceedance continues, consider what portion of the work is responsible and instruct the Contractor to stop that portion of work until the exceedance is abated. |
· Take immediate action to avoid further exceedance; · Submit proposals for remedial actions to IEC within 3 working days of notification; · Implement the agreed proposals; · Resubmit proposals if problem still not under control; · Stop the relevant portion of works as determined by SOR until the exceedance is abated. |
||||
Table 3‑4 Event/Action Plan for Air Quality
3.2.1
The construction noise level is
measured in terms of equivalent A-weighted sound pressure level (Leq) measured in decibels (dB(A)). Monitoring of Leq(30
min) is carried out at the noise monitoring locations on a weekly basis
during normal construction working hours (0700-1900 hours from Monday to
Saturday except public holidays). For
all other time periods (i.e. restricted hours), Leq(5
min) would be employed for comparison with the Noise Control Ordinance
(NCO) criteria if necessary.
3.2.2
The two statistical sound levels L10
and L90: the level exceeded for 10 and 90 percent of the time
respectively, are also recorded during monitoring. Major noise sources observed, both on-site and off-site, are recorded on the field data
sheet. All measurements are recorded to
the nearest 0.1 dB(A) and presented in round numbers
in this report. Results are presented in
Section 4.
3.2.3
Sound level meters, which comply with
the International Electrotechnical Commission
Publication 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications as
referred to the Technical Memorandum (TM) issued under the Noise Control
Ordinance, are used. Noise levels for
the A-weighted levels Leq(30min), L10 and L90
are measured throughout the impact monitoring.
Average, by sound power, of six consecutive 5 minutes readings is used
to provide Leq(30 min) for non-restricted hours
(07:00-19:00 hours from Monday to Saturday except public holidays). A facade correction of 3dB(A)
is applied to the measurements that are carried out under free field
conditions.
3.2.4
During the impact monitoring,
parameters such as dates, weather condition, equipment used, measurement
results and major noise sources are recorded on the field data record
sheet. Monitoring would not be carried
out in the presence of fog, rain or strong wind with a steady speed exceeding
Monitoring Equipment and Calibration
3.2.5
Rion
Precision Sound Level Meters of Type NA-27 and Type NL
3.2.6
Prior to and following each noise
measurement, the accuracy of the sound level meters is checked using an
acoustic calibrators (Rion Type NC-73) generating a
known sound pressure level at a known frequency. Measurements are considered as valid only if
the calibration levels from before and after the noise measurement agrees to
within 1.0 dB(A). The sound level meters
and the calibrator are calibrated annually to ensure they perform to the same
level of accuracy as stated in the manufacturer’s specifications. The noise monitoring equipment used during
the reporting month is shown in Table 3‑5 below. The
calibration certificates are included in Appendix F.
|
Equipment
Type |
Manufacturer |
Type
Number |
Serial
Number |
Location |
|
Sound
Level Meter |
Rion |
NA-27 |
00201194 |
NSR1,
NSR3, NSR6, NSR8 and NSR9 |
|
Sound
Level Meter |
Rion |
NL-18 |
00360030 |
|
|
Sound
Level Calibrator |
Rion |
NC-73 |
10786708 |
|
|
Sound
Level Calibrator |
Rion |
NC-73 |
10997142 |
Table 3‑5 Noise Monitoring Equipment
3.2.7
Five designated noise monitoring
locations were identified in the contract specific EM&A manual. They are listed in Table 3‑6 below and shown in Appendix G. All the locations below are in façade measurement.
|
Monitoring Station ID |
Name of Premises |
Floor Level |
|
NSR1 |
|
G/F |
|
NSR3 |
|
Podium |
|
NSR6 |
Squatters |
G/F |
|
NSR8 |
|
G/F |
|
NSR9 |
Greenview Terrace (Block 1) |
Podium (up to 6 July2009) Roof* (from 16 July 2009) |
* The noise monitoring location of NSR9 had been
adjusted at rooftop from 16 July 2009.
Table 3‑6 Noise Monitoring Locations
Construction Groundborne Noise
3.2.8
Prediction of construction groundborne noise indicates the criteria will be achieved
at most NSRs except exceedances are predicted at Hong
Hoi Chee Hong Temple (NSR3) and Squatters
(NSR6). It is recommended to restrict
the TBM operation in non-restricted period (i.e. 0700 - 1900) at these NSRs. In
order to ensure proper control of groundborne noise
is executed by the contractor, a monitoring requirement is recommended at the
3.2.9
The criteria including Technical
Memorandum for the Assessment of Noise from Places other than Domestic
Premises, Public Places or Construction Sites (TM-Places) under the NCO
stipulates that noise transmitted primarily through the structural elements of
building, or buildings, shall be 10 dB(A) less than
the relevant ANLs. Daytime groundborne construction noise criterion of 60 dB(A)
therefore applies with reference to TM-EIAO 70 dB(A) criterion for schools and
taking account of the minus 10 dB(A) requirement under the NCO TM-Places. Following the same principle for groundborne noise criteria, groundborne
construction noise levels inside domestic premises relying on opened window for
ventilation will be limited to 65 dB(A), with reference to the daytime airborne
noise criterion of 75 dB(A) in accordance with TM-EIAO.
3.2.10
The Action and Limit levels for
construction noise are defined in Table 3‑7. If
non-compliance of the criteria occurs, actions in accordance with the Action
Plan in Table
3‑8 would be carried out.
|
Time Period |
Action |
Limit |
|
0700 – 1900 hrs on normal weekdays |
When one documented complaint is received |
75 dB(A)* |
* For
educational establishments the limit level shall be 70dB(A) and reduced to 65dB(A) during examination
periods between 0700-1900 hrs on normal weekdays.
Table 3‑7 Action & Limit
Levels for Noise
|
Event |
Action |
|||
|
ET
Leader |
IEC |
SOR |
Contractor |
|
|
Action
Level |
· Notify IEC and the Contractor. · Carry out investigation. · Report the results of investigation to IEC and the Contractor. · Discuss with the Contractor and formulate remedial measures. · Increase monitoring frequency to check mitigation measures. |
· Review with analysed results submitted by ET. · Review the proposed remedial measures by the Contractor and advise SOR accordingly. · Supervise the implement of remedial measures. |
· Confirm receipt of notification of exceedance in writing. · Notify the Contractor. · Require the Contractor to propose remedial measures for the analysed noise problem. · Ensure remedial measures are properly implemented. |
· Submit noise mitigation proposals to IEC. · Implement noise mitigation proposals. |
|
Limit
Level |
· Identify the source. · Notify IEC, SOR, EPD and the Contractor. · Repeat measurement to confirm findings. · Increase monitoring frequency. · Carry out analysis of Contractor’s working procedures to determine possible mitigation to be implemented. · Inform IEC, SOR, and EPD the causes & actions taken for the exceedances. · Assess effectiveness of the Contractor’s remedial actions and keep IEC, EPD and SOR informed of the results. · If exceedance stops, cease additional monitoring. |
· Discuss amongst SOR, ET Leader and the Contractor on the potential remedial actions. · Review the Contractor’s remedial actions whenever necessary to assure their effectiveness and advise SOR accordingly. · Supervise the implementation of remedial measures. |
· Confirm receipt of notification of exceedance in writing. · Notify the Contractor. · Require the Contractor to propose remedial measures for the analysed noise problem. · Ensure remedial measures are properly implemented. · If exceedance continues, consider what activity of the work is responsible and instruct the Contractor to stop that activity of work until the exceedance is abated. |
· Take immediate action to avoid further exceedance. · Submit proposals for remedial actions to IEC within 3 working days of notification. · Implement the agreed proposals. · Resubmit proposals if problem still not under control. · Stop the relevant activity of works as determined by the SOR until the exceedance is abated. |
Table 3‑8 Event/Action Plan for Noise
3.3.1
The water
quality impact would be insignificant with the protection measures recommended
in Section 5.6 of the EIA report.
However in view of the sensitive nature of the rivers/streams and
bathing beaches in
the Study Area, it is suggested that a programme of monitoring should be
established to confirm the mitigation measures are protecting these water
bodies.
3.3.2
Monitoring for Dissolved Oxygen (DO), temperature, turbidity, pH and
suspended solids (SS) should be undertaken at designated monitoring locations. It should be noted that DO,
temperature, turbidity and pH should be measured in-situ whereas SS is assayed
in a laboratory.
3.3.3
In association with the water quality parameters, other relevant data
should also be measured, such as monitoring location/position, time, weather
conditions, and any special phenomena and description of work
underway at the construction site etc.
3.3.4
In accordance with the EM&A Manual, the water quality monitoring
for all specified parameters shall be measured at all designated monitoring
locations including control points at an interval of 3 days per week. DO,
temperature, turbidity, pH and SS shall be undertaken at designated monitoring
locations.
3.3.5
It should be noted that water
samples for all monitoring parameters should be collected, stored, preserved
and analysis according to Standard Methods, APHA 17 ed. and/or methods agreed
by the Director of Environmental Protection.
3.3.6
Each sample
shall be analysed in accordance with the APHA Standard Methods for the
Examination of Water and Wastewater, 18th edition, or an equivalent method
approved by the EPD. If an in-house or
non-standard method is proposed, details of the method verification may require
to be submitted to the EPD. In any circumstance,
the sample testing should comply with a comprehensive quality assurance and
quality control programme. The
laboratory should be prepared to demonstrate the quality programmes to the EPD
when requested.
Monitoring Equipment and Calibration
3.3.7
All the water samples collected should be transferred to clearly labelled and pre-cleaned sample containers
with necessary preservatives immediately after collection. The sample containers should be provided by a
HOKLAS accredited laboratory. Sufficient
quantity of samples should be collected for all laboratory analyses. Following sampling, samples should be stored in a cool box at
temperature of between 0 and 4oC, and transported to the laboratory
within the sample retention time as advised by the laboratory under proper
chain-of-custody system. The water quality monitoring equipment used
during the reporting month is shown in Table 3‑9 below.
|
Equipment Type |
Manufacturer |
Model |
Quantity |
|
pH Meter / DO / Temperature Meter |
WTW |
PH/Oxi 340i |
1 |
|
Tuibidimeter |
EUTECH |
TN-100 |
1 |
Table 3‑9 Water Quality Monitoring Equipment
3.3.8
All pH
meters, DO meters and turbidimeters shall be checked
and calibrated prior to use. DO meters
and turbidimeters shall be calibrated by a laboratory
accredited under HOKLAS or any other international accreditation scheme, and
subsequently re-calibrated at 3 monthly intervals throughout all stages of the
water quality monitoring. Responses of
sensors and electrodes shall be checked with certified standard solutions
before each use. Wet bulb calibrations
for all DO meters shall be carried out before measurement at each monitoring
location. For the on-site calibration of
field equipment, BS 127:1993, "Guide to field and on-site test methods for
the analysis of waters" should be observed.
The calibration certificates are included in Appendix
F.
3.3.9
Four
designated monitoring locations were
identified
in the contract specific EM&A Manual for
water quality monitoring. While the construction of the outfall basin at the
seashore has not been started, monitoring of marine water quality is only
required during which the stilling basin is placed at the seashore area. These
four monitoring stations are listed in Table 3‑10 below and shown in Appendix G.
|
Monitoring Station ID |
Name of Premises |
|
I-1 |
Intake I-1 |
|
I-1-C |
Control of Intake I-1 |
|
I-2 |
Intake I-2 |
|
I-2-C |
Control of Intake I-2 |
|
I-3 |
Intake I-3 |
|
I-3-C* |
Control of Intake I-3 |
|
O-1 (FT) & (ET) |
Outfall 1During Flood Tide and Ebb Tide |
|
O-1-C (FT) |
Control of Outfall O-1 During Flood Tide |
|
O-1-C (ET) |
Control of Outfall O-1 During Ebb Tide |
*The upper stream
location (I-3-C*) had been relocated from end of February 2009 due to coarse
stone blockage.
Table 3‑10 Water Quality Monitoring Locations
3.3.10
Note that there are two control stations for Outfall O-1, one for
sampling during flood tide and one for sampling during ebb tide. Only one of those control stations for
Outfall O-1 shall be sampled during each sampling. Control station to be sampled will be
determined based on the tidal information provided by the Hong Kong
Observatory.
3.3.11
The Action and Limit levels for water
quality monitoring parameters are defined in Table 3‑11. In case of any exceedance,
appropriate actions will be undertaken in accordance with the Event and Action
Plan as described in Table 3‑12.
|
Parameters |
Action |
Limit |
|
DO in
mg/l (Surface,
Middle & Bottom) |
Surface
& Middle 5%-ile of baseline data for surface and
middle layer. Bottom 5%-ile of baseline data for bottom layer. |
Surface
& Middle 4mg/l
except 5mg/l for FCZ or 1%-ile of baseline data for surface and middle layer Bottom 2mg/l
or 1%-ile of baseline data for bottom layer |
|
SS in
mg/l (depth-averaged) |
95%-ile of baseline data or 120% of upstream control
station’s SS at the same tide of the same day |
99%-ile of baseline or 130% of upstream control station’s SS
at the same tide of the same day and specific sensitive receiver water
quality requirements (e.g. required suspended solids levels for concerned sea
water intakes) |
|
Turbidity
(Tby) in NTU (depth-averaged) |
95%-ile of baseline data or 120% of upstream control
station’s Tby at the same tide of the same day |
99%-ile of baseline or 130% of upstream control station’s Tby at the same tide of the same day |
Notes:
·
For DO,
non-compliance of the water quality limits occurs when monitoring result is
lower than the limits.
·
For SS and Tby, non-compliance of the water quality limits occurs when
monitoring result is higher than the limits.
·
All the
figures given in the table are used for reference only and the EPD may amend
the figures whenever it is considered as necessary.
Table 3‑11 Action/Limit Levels for Water Quality
|
Event |
ET Leader |
IEC |
SOR |
Contractor |
|
Action Level being exceeded by one sampling day |
· Repeat in-situ measurement to confirm finding; · Identify source(s) of impact; · Inform IEC and Contractor; · Check monitoring data, all plant, equipment and Contractor’s working methods; · Discuss mitigation measures with IEC and Contractor; and · Repeat measurement on next day of exceedance. |
· Discuss with ET and Contractor on the mitigation measures; · Review proposals on mitigation measures submitted by Contractor and advise the SOR accordingly; and · Assess the effectiveness of the implemented mitigation measures. |
· Discuss with IEC on the proposed mitigation measures; and · Make agreement on the mitigation measures to be implemented. |
· Inform the SOR and confirm notification of the non-compliance in writing; · Rectify unacceptable practice; · Check all plant and equipment; · Consider changes of working methods; · Discuss with ET and IEC and propose mitigation measures to IEC and SOR; and · Implement the agreed mitigation measures. |
|
Action Level being exceeded by more than one consecutive sampling day |
· Repeat in-situ measurement to confirm finding; · Identify source(s) of impact; · Inform IEC and Contractor; · Check monitoring data, all plant, equipment and Contractor’s working methods; · Discuss mitigation measures with IEC and Contractor; · Ensure mitigation measures are implemented; · Prepare to increase the monitoring frequency to daily; and · Repeat measurement on next day of exceedance. |
· Discuss with ET and Contractor on the mitigation measures; · Review proposals on mitigation measures submitted by Contractor and advise the SOR accordingly; and · Assess the effectiveness of the implemented mitigation measures. |
· Discuss with IEC on the proposed mitigation measures; · Make agreement on the mitigation measures to be implemented; and · Assess the effectiveness of the implemented mitigation measures. |
· Inform the Engineer and confirm notification of the non-compliance in writing; · Rectify unacceptable practice; · Check all plant and equipment; · Consider changes of working methods; · Discuss with ET and IEC and propose mitigation measures to IEC and SOR within 3 working days; and · Implement the agreed mitigation measures. |
|
Limit Level being exceeded by one sampling day |
· Repeat in-situ measurement to confirm finding; · Identify source(s) of impact; · Inform IEC, Contractor and EPD; · Check monitoring data, all plant, equipment and Contractor’s working methods; · Discuss mitigation measures with IEC, SOR and Contractor; · Ensure mitigation measures are implemented; and · Increase the monitoring frequency to daily until no exceedance of Limit level. |
· Discuss with ET and Contractor on the mitigation measures; · Review proposals on mitigation measures submitted by Contractor and advise the SOR accordingly; and · Assess the effectiveness of the implemented mitigation measures.
|
· Discuss with IEC, ET and Contractor on the proposed mitigation measures; and · Request Contractor to critically review the working methods; · Make agreement on the mitigation measures to be implemented; and · Assess the effectiveness of the implemented mitigation measures. |
· Inform the Engineer and confirm notification of the non-compliance in writing; · Rectify unacceptable practice; · Check all plant and equipment; · Consider changes of working methods; · Discuss with ET and IEC and SOR and propose mitigation measures to IEC and SOR within 3 working days; and · Implement the agreed mitigation measures. |
|
Limit Level being exceeded by more than one consecutive sampling day |
· Repeat in-situ measurement to confirm finding; · Identify source(s) of impact; · Inform IEC, Contractor and EPD; · Check monitoring data, all plant, equipment and Contractor’s working methods; · Discuss mitigation measures with IEC, SOR and Contractor; · Ensure mitigation measures are implemented; and · 7. Increase the monitoring frequency to daily until no exceedance of Limit level for two consecutive days. |
· Discuss with ET and Contractor on the mitigation measures; · Review proposals on mitigation measures submitted by Contractor and advise the SOR accordingly; and · Assess the effectiveness of the implemented mitigation measures. |
· Discuss with IEC, ET and Contractor on the proposed mitigation measures; and · Request Contractor to critically review the working methods; · Make agreement on the mitigation measures to be implemented; · Assess the effectiveness of the implemented mitigation measures; and · Consider and instruct, if necessary, the Contractor to slow down or to stop all or part of the marine work until no exceedance of Limit Level. |
· Inform the SOR and confirm notification of the non-compliance in writing; · Rectify unacceptable practice; · Check all plant and equipment; · Consider changes of working methods; · Discuss with ET and IEC and SOR and propose mitigation measures to IEC and SOR within 3 working days; · Implement the agreed mitigation measures; and · As directed by the Engineer, to slow down or to stop all or part of the marine work or construction activities. |
Table 3‑12 Event/Action Plan for Water Quality
4.1.1
The air
quality monitoring schedule of the reporting period is given in Appendix
H.
4.1.2
Results of 1-hours TSP level are shown
in Table 4-1. All
measurements were recorded to the nearest
|
Station |
Monitoring Date |
Monitoring Result (mg/m3) |
Action/Limit Levels (mg/m3) |
|
ASR 1 |
01-Apr-10 |
124.6 |
307/500 |
|
89.9 |
|||
|
89.9 |
|||
|
07-Apr-10 |
120.8 |
||
|
27.0 |
|||
|
43.7 |
|||
|
13-Apr-10 |
93.8 |
||
|
110.5 |
|||
|
60.4 |
|||
|
19-Apr-10 |
65.5 |
||
|
93.8 |
|||
|
75.8 |
|||
|
23-Apr-10 |
74.5 |
||
|
88.7 |
|||
|
69.4 |
|||
|
29-Apr-10 |
86.1 |
||
|
186.3 |
|||
|
169.6 |
|||
|
ASR 3 |
01-Apr-10 |
110.6 |
327/500 |
|
114.3 |
|||
|
94.6 |
|||
|
07-Apr-10 |
124.1 |
||
|
60.2 |
|||
|
126.6 |
|||
|
13-Apr-10 |
24.6 |
||
|
114.3 |
|||
|
54.1 |
|||
|
19-Apr-10 |
73.7 |
||
|
159.8 |
|||
|
65.1 |
|||
|
23-Apr-10 |
66.4 |
||
|
54.1 |
|||
|
57.8 |
|||
|
29-Apr-10 |
125.3 |
||
|
178.2 |
|||
|
168.4 |
|||
|
ASR 8 |
01-Apr-10 |
120.3 |
337/500 |
|
115.3 |
|||
|
27.9 |
|||
|
07-Apr-10 |
89.9 |
||
|
35.5 |
|||
|
45.6 |
|||
|
13-Apr-10 |
78.5 |
||
|
98.8 |
|||
|
55.7 |
|||
|
19-Apr-10 |
95.0 |
||
|
67.1 |
|||
|
53.2 |
|||
|
23-Apr-10 |
68.4 |
||
|
49.4 |
|||
|
15.2 |
|||
|
29-Apr-10 |
119.1 |
||
|
173.5 |
|||
|
83.6 |
|||
|
ASR 9 |
01-Apr-10 |
102.2 |
329/500 |
|
122.9 |
|||
|
109.1 |
|||
|
07-Apr-10 |
136.8 |
||
|
23.5 |
|||
|
41.4 |
|||
|
13-Apr-10 |
91.2 |
||
|
82.9 |
|||
|
73.2 |
|||
|
19-Apr-10 |
120.2 |
||
|
56.6 |
|||
|
63.5 |
|||
|
23-Apr-10 |
60.8 |
||
|
62.2 |
|||
|
51.1 |
|||
|
29-Apr-10 |
89.8 |
||
|
103.6 |
|||
|
74.6 |
Note: Italic indicates the occurrence of exceedance
of Action level
Bold indicates the occurrence of exceedance of Limit Level
Table 4-1 Air Quality
Monitoring Results
4.1.3
No project related exceedance was recorded in the reporting month.
4.2.1
The noise monitoring schedule of the
reporting period is given in Appendix H.
Results of measured noise level, in terms of Leq
(30min), during the construction are shown in Table
4-2.
All measurements including L10 and L90 are recorded to the nearest 0.1 dB(A) and presented in round numbers in this report. Detail results including weather conditions
and graphical presentation are presented in Appendix I.
|
Station |
Monitoring Date |
Leq (30 min) dB(A) |
Limit Levels dB(A) |
|
NSR 1 |
07-Apr-10 |
65.7 |
70/65** |
|
13-Apr-10 |
62.5 |
||
|
19-Apr-10 |
64.0 |
||
|
30-Apr-10 |
64.4 |
||
|
NSR 3 |
07-Apr-10 |
72.3 |
75 |
|
13-Apr-10 |
66.0 |
||
|
19-Apr-10 |
70.0 |
||
|
30-Apr-10 |
65.3 |
||
|
NSR 6 |
07-Apr-10 |
67.2 |
|
|
13-Apr-10 |
70.5 |
||
|
19-Apr-10 |
65.9 |
||
|
30-Apr-10 |
65.1 |
||
|
NSR 8 |
07-Apr-10 |
67.1 |
|
|
13-Apr-10 |
64.4 |
||
|
19-Apr-10 |
64.4 |
||
|
29-Apr-10 |
65.7 |
||
|
NSR 9 |
07-Apr-10 |
69.8 |
|
|
13-Apr-10 |
68.6 |
||
|
19-Apr-10 |
71.9 |
||
|
29-Apr-10 |
68.7 |
**
Noise Limit level at NSR1
was reduced from 70 dB(A) to 65 dB(A) during
examination periods between 12 and 15 April 2010.
Table 4-2 Noise Monitoring Results
4.2.2
No exceedances of Action and Limit Levels were recorded in our
regular noise monitoring during the reporting month.
4.3.1
The water quality monitoring schedule
of the reporting period is given in Appendix H.
Summaries of exceedances for water quality
monitoring are provided in Table 4-3 to Table 4-5.
|
Parameter |
Action
Level Exceedance |
Limit
Level Exceedance |
|
DO |
Nil |
Nil |
|
Turbidity |
Nil |
Nil |
|
SS |
Nil |
Nil |
|
Total |
Nil |
Nil |
Table 4-3 Summary of Exceedances for I-1
|
Parameter |
Action
Level Exceedance |
Limit
Level Exceedance |
|
DO |
Nil |
Nil |
|
Turbidity |
Nil |
Nil |
|
SS |
NIl |
Nil |
|
Total |
Nil |
Nil |
Table 4-4 Summary of Exceedances for I-2
Parameter |
Action
Level Exceedance |
Limit
Level Exceedance |
|
DO |
Nil |
Nil |
|
Turbidity |
Nil |
Nil |
|
SS |
Nil |
Nil |
|
Total |
Nil |
Nil |
Table 4-5 Summary of Exceedances for I-3
4.3.2
Results
of measured water quality parameters during the reporting month are shown in Table 4-6 and detailed results including weather conditions
and graphical presentations are enclosed in Appendix I.
4.3.3
No water quality monitoring was carried out on 2 and 5 April 2010 because no
construction works are carried out during holiday. No exceedances of Action
and Limit Levels were recorded in our water quality monitoring during the
reporting month.
|
Station |
Date |
Temperature |
DO
(mg/L) |
Action/Limit
Level for DO (mg/L) |
pH |
Turbidity
(NTU) |
Action/Limit
Level for Turbidity (NTU) |
SS
(mg/L) |
Action/Limit
Level for SS (mg/L) |
|
I-1 |
07-Apr-10 |
17.60 |
5.84 |
3.42 /
3.34 |
7.48 |
6.47 |
9.75 / 12.47 |
5.20 |
8.85 /
10.17 |
|
|
09-Apr-10 |
20.60 |
4.76 |
|
7.31 |
4.63 |
|
2.00 |
|
|
|
12-Apr-10 |
22.70 |
5.55 |
|
7.62 |
3.13 |
|
2.00 |
|
|
|
14-Apr-10 |
23.10 |
5.02 |
|
7.56 |
4.87 |
|
2.65 |
|
|
|
16-Apr-10 |
20.20 |
4.71 |
|
7.62 |
5.11 |
|
3.40 |
|
|
|
19-Apr-10 |
22.50 |
4.97 |
|
7.53 |
4.89 |
|
2.10 |
|
|
|
21-Apr-10 |
24.00 |
6.02 |
|
7.63 |
5.76 |
|
2.70 |
|
|
|
23-Apr-10 |
23.90 |
5.58 |
|
7.56 |
4.07 |
|
2.00 |
|
|
|
26-Apr-10 |
23.00 |
5.50 |
|
7.58 |
5.57 |
|
2.15 |
|
|
|
28-Apr-10 |
23.60 |
5.48 |
|
7.55 |
6.15 |
|
2.55 |
|
|
|
30-Apr-10 |
24.70 |
5.46 |
|
7.55 |
8.98 |
|
8.80 |
|
|
Station |
Date |
Temperature |
DO
(mg/L) |
Action/Limit
Level for DO (mg/L) |
pH |
Turbidity
(NTU) |
Action/Limit
Level for Turbidity (NTU) |
SS
(mg/L) |
Action/Limit
Level for SS (mg/L) |
|
I-1-C |
07-Apr-10 |
17.95 |
4.90 |
- / - |
7.51 |
6.76 |
- / - |
4.40 |
- / - |
|
|
09-Apr-10 |
20.90 |
5.50 |
|
7.30 |
4.86 |
|
2.00 |
|
|
|
12-Apr-10 |
22.40 |
5.16 |
|
7.61 |
3.20 |
|
2.00 |
|
|
|
14-Apr-10 |
23.00 |
4.79 |
|
7.51 |
4.84 |
|
2.70 |
|
|
|
16-Apr-10 |
20.10 |
4.87 |
|
7.60 |
5.07 |
|
3.95 |
|
|
|
19-Apr-10 |
22.75 |
5.97 |
|
7.55 |
4.74 |
|
2.80 |
|
|
|
21-Apr-10 |
13.20 |
5.63 |
|
7.66 |
5.99 |
|
5.35 |
|
|
|
23-Apr-10 |
23.50 |
5.48 |
|
7.53 |
4.11 |
|
2.00 |
|
|
|
26-Apr-10 |
22.70 |
5.57 |
|
7.60 |
5.66 |
|
2.40 |
|
|
|
28-Apr-10 |
23.40 |
5.35 |
|
7.53 |
6.41 |
|
2.60 |
|
|
|
30-Apr-10 |
24.95 |
4.90 |
|
7.58 |
8.74 |
|
8.85 |
|
|
Station |
Date |
Temperature |
DO
(mg/L) |
Action/Limit
Level for DO (mg/L) |
pH |
Turbidity
(NTU) |
Action/Limit
Level for Turbidity (NTU) |
SS
(mg/L) |
Action/Limit
Level for SS (mg/L) |
|
I-2 |
07-Apr-10 |
17.95 |
5.55 |
3.66 / 3.63 |
7.55 |
2.11 |
6.63 / 6.99 |
2.00 |
7.68 / 8.34 |
|
|
09-Apr-10 |
20.60 |
4.71 |
|
7.51 |
1.91 |
|
2.00 |
|
|
|
12-Apr-10 |
23.05 |
5.40 |
|
7.54 |
1.84 |
|
2.00 |
|
|
|
14-Apr-10 |
23.50 |
4.95 |
|
7.62 |
2.02 |
|
2.30 |
|
|
|
16-Apr-10 |
20.05 |
4.58 |
|
7.53 |
1.94 |
|
2.00 |
|
|
|
19-Apr-10 |
23.15 |
4.99 |
|
7.65 |
1.98 |
|
2.00 |
|
|
|
21-Apr-10 |
23.65 |
5.67 |
|
7.50 |
2.04 |
|
2.00 |
|
|
|
23-Apr-10 |
24.20 |
5.50 |
|
7.63 |
2.09 |
|
2.40 |
|
|
|
26-Apr-10 |
23.80 |
5.44 |
|
7.46 |
1.82 |
|
2.00 |
|
|
|
28-Apr-10 |
23.80 |
5.55 |
|
7.57 |
2.25 |
|
2.00 |
|
|
|
30-Apr-10 |
24.05 |
5.87 |
|
7.53 |
3.62 |
|
4.40 |
|
|
Station |
Date |
Temperature |
DO
(mg/L) |
Action/Limit
Level for DO (mg/L) |
pH |
Turbidity
(NTU) |
Action/Limit
Level for Turbidity (NTU) |
SS
(mg/L) |
Action/Limit
Level for SS (mg/L) |
|
I-2-C |
07-Apr-10 |
17.80 |
5.56 |
- / - |
7.56 |
2.25 |
- / - |
2.00 |
- / - |
|
|
09-Apr-10 |
20.80 |
4.75 |
|
7.51 |
2.04 |
|
2.00 |
|
|
|
12-Apr-10 |
22.80 |
5.43 |
|
7.56 |
1.95 |
|
2.05 |
|
|
|
14-Apr-10 |
24.00 |
5.01 |
|
7.61 |
2.08 |
|
2.55 |
|
|
|
16-Apr-10 |
20.70 |
4.70 |
|
7.55 |
2.02 |
|
2.00 |
|
|
|
19-Apr-10 |
23.00 |
4.92 |
|
7.60 |
2.09 |
|
2.00 |
|
|
|
21-Apr-10 |
24.05 |
5.81 |
|
7.55 |
2.11 |
|
2.00 |
|
|
|
23-Apr-10 |
23.95 |
5.56 |
|
7.61 |
2.11 |
|
2.80 |
|
|
|
26-Apr-10 |
23.30 |
5.44 |
|
7.50 |
1.89 |
|
2.00 |
|
|
|
28-Apr-10 |
24.00 |
5.52 |
|
7.55 |
2.37 |
|
2.00 |
|
|
|
30-Apr-10 |
24.30 |
5.92 |
|
7.56 |
3.80 |
|
4.95 |
|
|
Station |
Date |
Temperature |
DO
(mg/L) |
Action/Limit
Level for DO (mg/L) |
pH |
Turbidity
(NTU) |
Action/Limit
Level for Turbidity (NTU) |
SS
(mg/L) |
Action/Limit
Level for SS (mg/L) |
|
I-3 |
07-Apr-10 |
18.20 |
5.52 |
3.65 / 3.51 |
7.59 |
2.71 |
3.99 / 4.18 |
2.00 |
6.13 /
7.23 |
|
|
09-Apr-10 |
20.80 |
4.68 |
|
7.49 |
1.82 |
|
2.00 |
|
|
|
12-Apr-10 |
23.35 |
5.43 |
|
7.60 |
1.78 |
|
2.00 |
|
|
|
14-Apr-10 |
24.00 |
4.79 |
|
7.60 |
1.92 |
|
2.00 |
|
|
|
16-Apr-10 |
20.50 |
4.65 |
|
7.50 |
2.12 |
|
2.00 |
|
|
|
19-Apr-10 |
22.70 |
5.00 |
|
7.40 |
2.82 |
|
2.00 |
|
|
|
21-Apr-10 |
24.00 |
5.86 |
|
7.42 |
2.38 |
|
2.00 |
|
|
|
23-Apr-10 |
24.40 |
5.49 |
|
7.40 |
2.32 |
|
2.00 |
|
|
|
26-Apr-10 |
23.80 |
5.44 |
|
7.46 |
1.82 |
|
2.00 |
|
|
|
28-Apr-10 |
23.30 |
5.66 |
|
7.41 |
2.00 |
|
2.00 |
|
|
|
30-Apr-10 |
24.65 |
5.67 |
|
7.48 |
3.20 |
|
2.80 |
|
|
Station |
Date |
Temperature |
DO
(mg/L) |
Action/Limit
Level for DO (mg/L) |
pH |
Turbidity
(NTU) |
Action/Limit
Level for Turbidity (NTU) |
SS
(mg/L) |
Action/Limit
Level for SS (mg/L) |
|
I-3-C |
07-Apr-10 |
18.15 |
5.47 |
- / - |
7.60 |
2.77 |
- / - |
2.00 |
- / - |
|
|
09-Apr-10 |
20.70 |
4.83 |
|
7.51 |
1.92 |
|
2.00 |
|
|
|
12-Apr-10 |
23.75 |
5.39 |
|
7.61 |
1.80 |
|
2.00 |
|
|
|
14-Apr-10 |
23.25 |
4.80 |
|
7.61 |
1.97 |
|
2.00 |
|
|
|
16-Apr-10 |
20.40 |
4.68 |
|
7.49 |
2.21 |
|
2.00 |
|
|
|
19-Apr-10 |
22.50 |
5.10 |
|
7.39 |
2.84 |
|
2.00 |
|
|
|
21-Apr-10 |
23.25 |
5.89 |
|
7.40 |
2.19 |
|
2.10 |
|
|
|
23-Apr-10 |
24.00 |
5.52 |
|
7.49 |
2.43 |
|
2.00 |
|
|
|
26-Apr-10 |
23.30 |
5.44 |
|
7.50 |
1.89 |
|
2.20 |
|
|
|
28-Apr-10 |
23.50 |
5.71 |
|
7.43 |
1.97 |
|
2.00 |
|
|
|
30-Apr-10 |
24.50 |
5.76 |
|
7.50 |
3.27 |
|
3.60 |
|
Note: Italic indicates the
occurrence of exceedance of Action level.
Bold
indicates the occurrence of exceedance of Limit
level.
Table
4-6 Water Quality Monitoring Results
4.4 Summary of Project-Related Exceedances
4.4.1
Table 4-7 summarises
the project-related exceedance results recorded in April 2010. Note that exceedances that are considered not related to the
construction activities are not included in this table.
|
Environmental Monitoring |
Total No. of Measurement |
Action Level Exceedance |
% of Action Level Exceedance |
Limit Level Exceedance |
% of Limit Level Exceedance |
|
Air Quality |
72 |
0 |
0 |
0 |
0 |
|
Noise |
20 |
0 |
0 |
0 |
0 |
|
Water |
66 |
0 |
0 |
0 |
0 |
Note: Exceedances that
are considered not related to the construction activities are not included in
this table.
Table 4-7 Summary of Project-Related Exceedances
5.1.1
The status of waste management is
summarized in Table 5-1 below.
|
Status of waste management |
Quantity |
|
Inert C&D Material Disposed of to Public Fill at Tuen Mun (m3) |
733.6 |
|
Inert C&D Material Reused in other Contracts* (m3) |
800.0 |
|
Metals Generated (kg) |
Nil |
|
Paper / Cardboard Packaging (kg) |
300.0 |
|
Plastics (kg) |
Nil |
|
Chemical Waste (kg) |
Nil |
|
General Waste Disposed of to NENT Landfill (m3) |
10.2 |
* Other Contracts
include DC/2007/08, DC/2007/06, DC/2006/04, ST/2008/02 and HY/2007/09.
Table 5-1 Waste Generated in April 2010
6 NON-COMPLIANCE AND DEFICIENCY
6.1.1
ET has carried out two site
inspections in the reporting month. All
observations together with the appropriate recommended mitigation measures
where necessary were recorded in the audit checklists that were passed to the
Contractor. Major environmental
deficiencies observed during site inspection/audits and recommendation, which
were made by the ET, are summarised in Table 6-1 below. No
non-compliance was observed.
|
Inspection Date |
Observation |
Recommendation |
Status |
|
8 April
2010 |
1. Tarpaulin was used to wrap the breaker tip of the
breaker at Outfall. The movable noise barrier was far away to the noise
source. 2. Milky wastewater was observed in the
sedimentation tank at I2. 3. Gaps were observed between the noise screening
sheets at I3. |
1.
The Contractor
shall properly wrap the breaker tip of the breaker at Outfall with acoustic
material. The location of movable
noise barrier shall also be adjusted from time to time to block the line of
sight between the breaker and nearby sensitive receivers. 2.
The Contractor was reminded to provide
adequate sedimentation and wastewater treatment facilities for the wastewater
discharge at I2 to ensure compliance with discharge license. 3.
The Contractor is reminded to fix the noise
screening sheets at I3 to avoid gaps. |
1.During the site inspection on 30 April 2010,
breaker tip of the breaker was wrapped with acoustic material and location of
movable noise barrier was adjusted to block the line of sight between the
breaker and nearby sensitive receivers. (Closed). 2.During the site inspection on 30 April 2010, one
more sedimentation tank was provided for the wastewater treatment before
discharge at I2. (Closed) 3.During the site inspection on 30 April 2010,
noise screening sheets were fixed with no gaps. (Closed) |
|
30
April 2010 |
1.
Chemical waste drums were observed without any
mitigation measures at Outfall. 2.
Stagnant water was observed at a few locations
at Outfall. 3.
Waste or unused materials were observed nearby
the stream at I2. |
1.
The Contractor was reminded to provide drip
trap to the chemical waste drums or removed them to the designated storage
area. 2.
The Contractor was reminded to remove the
stagnant water after rainfall. 3.
The Contractor was reminded to clean up and
remove the waste and unused material away to the nearby water course at I2. |
1.
The
chemical waste drums were removed to the designated site in the site inspection
on 6 May 2010. (Closed) 2.
The stagnant water was removed and the area
was sealed properly in the site inspection on 6 May 2010.(Closed) 3.
No waste and unused material were observed
nearby the water course at I2 in the site inspection on 6 May 2010.(Closed) |
Table 6-1 Site Inspection by ET
7 COMPLAINT
7.1.1
A complaint
hotline at 9850
3241 of the Contractor has been established for the Project.
7.1.2
No
environmental complaint was received during the reporting month. Details of the complaint investigation can be referred to Appendix K.
7.1.3
Cumulative statistics of
environmental complaints are shown in Table 7-1.
|
Complaints Received in the Reporting Month |
Cumulative Number of Complaints |
|
0 |
17 |
Table 7-1 Cumulative Statistic of Environmental Complaint
8 SUMMARY OF NOTIFICATION OF SUMMONS, SUCCESSFUL PROSECUTIONS AND CORRECTIVE ACTIONS
8.1.1
No summons and successful prosecution was received during the
reporting month.
8.1.2
Cumulative
statistics of Notification of Summons, Successful Prosecutions and Convictions
are shown in Table 8-1.
|
Notification of Summons |
Successful Prosecution |
||
|
April 2010 |
Cumulative |
April 2010 |
Cumulative |
|
0 |
0 |
0 |
0 |
Table 8-1 Cumulative Statistics of Notification of Summons
and Successful Prosecutions
9.1.1
The forecast of construction works
for the upcoming three months are:
·
Site Cleaning and Tidying at I1, I2, I3 and Outfall;
·
Erection of Muck Hopper and Conveyor Support steel structure
at Outfall;
·
Breaking Up Exiting Boulder at Outfall and I3;
·
Drilling and Excavation of Man Access Shaft & Vortex
Shaft at I2;
·
Construction of Approach Channel Structure at I2;
·
Erosion Control Mat and Green Wire Mesh at Outfall;
·
Cascade and Channel Modification concrete structure works at I-1;
·
Construction of Skin Wall at I3;
·
Assembly of TBM, TBM Drilling of the Tunnel at Outfall;
·
Installation of noise enclosure at Outfall and I2;
·
Soil nail works and pipe jacking pit excavation at Portion G
at I2;
·
Drilling and Excavation of Spiral Ramp at Outfall;
·
Drilling and Excavation of Vortex Shaft at I3; and
·
Restricted Hours – Delivery of TBM Backup Plants.
|
|
|
|
|
Site Map and Works Area |
|
|
|
|
|
Organization Chart |
|
|
|
|
|
Construction Programme |
|
|
|
|
|
Implementation Status of Environmental Mitigation Measures |
|
|
|
|
|
Status of License and Permit |
|
|
|
|
|
Calibration Certificates |
|
|
|
|
|
Monitoring Locations |
|
|
|
|
|
EM&A Schedule |
|
|
|
|
|
Monitoring Results |
|
|
|
|
|
Complaint Log |