Milestone

The drainage improvement works have been substantially completed

April, 2018

The construction of 400m (approx.) long box culvert (red section) and river deepening works (light blue section) have been substantially completed. The drainage capacities at the bottlenecks (i.e. junctions at Shatin Pass Road and Tai Shing Street) have been increased by more than 100%. Flood risk to nearby areas is thus significantly reduced.
 

Progress Milestone

 

 

Progress by Year

Rehabilitation works adjacent to Wong Tai Sin Police Station are in progress

11 June 2018

Rehabilitation works adjacent to Wong Tai Sin Police Station are in progress

Box culvert construction works from Wong Tai Sin Police Station to Morse Park No. 1 are substantially completed

29 March 2018

Box culvert construction works from Wong Tai Sin Police Station to Morse Park No. 1 are substantially completed

Remaining box culvert construction works next to Kai Tak Garden and Lower Wong Tai Sin Estate commenced

27 February 2018

Remaining box culvert construction works next to Kai Tak Garden and Lower Wong Tai Sin Estate commenced

River works adjacent to Morse Park No. 1, Kai Tak Garden and Lower Wong Tai Sin Estate are substantially completed

31 January 2018

River works adjacent to Morse Park No. 1, Kai Tak Garden and Lower Wong Tai Sin Estate are substantially completed

River beautification near Tung Tau Estate (II) is in progress

01 December 2017

River beautification near Tung Tau Estate (II) is in progress

Nullah deepening near Lower Wong Tai Sin Estate has completed

28 November 2017

Nullah deepening near Lower Wong Tai Sin Estate has completed

Nullah deepening near Tung Tau Estate (II) has completed

19 September 2017

Nullah deepening near Tung Tau Estate (II) has completed

Reconstruction of Jogging Track in Morse Park (Park No.1) has completed and has been opened to the Public

30 June 2017

Reconstruction of Jogging Track in Morse Park (Park No.1) has completed and has been opened to the Public

Mini-piling works near Wong Tai Sin Police Station and Kowloon Walled-City Community Hall has commenced

29 June 2017

Mini-piling works near Wong Tai Sin Police Station and Kowloon Walled-City Community Hall has commenced

Construction of Box Culvert near Morse Park No. 1 has completed

28 June 2017

Construction of Box Culvert near Morse Park No. 1 has completed

Construction of Box Culvert near Wong Tai Sin Police Station and Shatin Pass Road has commenced

25 June 2017

Construction of Box Culvert near Wong Tai Sin Police Station and Shatin Pass Road has commenced

Temporary Traffic Arrangement near Choi Hung Road/ Shatin Pass Road junction has cancelled

11 June 2017

Temporary Traffic Arrangement near Choi Hung Road/ Shatin Pass Road junction has cancelled

Construction of Access Ramp near Wong Chung Ming Secondary School has completed

06 June 2017

Construction of Access Ramp near Wong Chung Ming Secondary School has completed

Nullah deepening and Construction of Skin Wall near Lower Wong Tai Sin Estate and Kai Tak Garden are in progress

27 May 2017

Nullah deepening and Construction of Skin Wall near Lower Wong Tai Sin Estate and Kai Tak Garden are in progress

Construction of Box Culvert near Wong Tai Sin Police Station has completed

28 April 2017

Construction of Box Culvert near Wong Tai Sin Police Station has completed

Construction of new nullah bed near Tung Tau Estate (II) has completed

28 April 2017

Construction of new nullah bed near Tung Tau Estate (II) has completed

Mini-piling works near Tung Tai Lane Footbridge has commenced

08 April 2017

Mini-piling works near Tung Tai Lane Footbridge has commenced

Riverbed and Nullah Wall Construction near Tung Wui Estate has completed

02 April 2017

Riverbed and Nullah Wall Construction near Tung Wui Estate has completed

Nullah deepening near Tung Tau Estate (II) are in progress

30 March 2017

Nullah deepening near Tung Tau Estate (II) are in progress

Construction of Box Culvert near Kai Tak Garden has commenced

27 February 2017

Construction of Box Culvert near Kai Tak Garden has commenced

Construction of Box Culvert near Kei Tak Primary School has commenced

03 January 2017

Construction of Box Culvert near Kei Tak Primary School has commenced

Nullah deepening works and Construction of Skin Wall near Morse Park (No. 1) are in progress

31 December 2016

Nullah deepening works and Construction of Skin Wall near Morse Park (No. 1) are in progress

Construction of Box Culvert near Morse Park No. 1 has commenced

30 November 2016

Construction of Box Culvert near Morse Park No. 1 has commenced

Construction of Pipe Pile Wall near Kai Tak Garden has commenced

28 November 2016

Construction of Pipe Pile Wall near Kai Tak Garden has commenced

Riverbed and Nullah Wall Construction near Tung Wui Estate has commenced

02 November 2016

Riverbed and Nullah Wall Construction near Tung Wui Estate has commenced

Riverbed and Nullah Wall Construction near Lower Wong Tai Sin Estate and Kai Tak Garden has commenced

01 November 2016

Riverbed and Nullah Wall Construction near Lower Wong Tai Sin Estate and Kai Tak Garden has commenced

Construction of Access Ramp near Wong Chung Ming Secondary School has commenced

31 October 2016

Construction of Access Ramp near Wong Chung Ming Secondary School has commenced

Construction of Box Culvert near Wong Tai Sin Police Station has commenced

31 October 2016

Construction of Box Culvert near Wong Tai Sin Police Station has commenced

Riverbed and Nullah Wall Construction near Wong Chung Ming Secondary School has completed

28 October 2016

Riverbed and Nullah Wall Construction near Wong Chung Ming Secondary School has completed

Construction of new Tung Tai Lane footbridge (partial opening to public)

24 October 2016

Construction of new Tung Tai Lane footbridge (partial opening to public)

Temporary Traffic Arrangement- Choi Hung Road/ Shatin Pass Road junction

29 May 2016

Temporary Traffic Arrangement- Choi Hung Road/ Shatin Pass Road junction

Morse Park (Park No. 1) Improvement Works has commenced

03 May 2016

Morse Park (Park No. 1) Improvement Works has commenced

Operate the completed box culvert sections (approximately 200m long) between Shatin Pass Road and Tai Shing Street

01 April 2016

Operate the completed box culvert sections (approximately 200m long) between Shatin Pass Road and Tai Shing Street

Riverbed Construction near Ng Wah Catholic Secondary School has completed

31 March 2016

Riverbed Construction near Ng Wah Catholic Secondary School has completed

Riverbed Construction near Wong Chung Ming Secondary School has commenced

31 March 2016

Riverbed Construction near Wong Chung Ming Secondary School has commenced

Riverbed Construction near Choi Hung Road has completed

31 March 2016

Riverbed Construction near Choi Hung Road has completed

Construction of Box Culvert near Lower Wong Tai Sin Estate has completed

17 March 2016

Construction of Box Culvert near Lower Wong Tai Sin Estate has completed

Pipe pile Installation near Tung Wui Estate has completed

20 February 2016

Pipe pile Installation near Tung Wui Estate has completed

Construction of Box Culvert near Kei Tak Primary School has commenced

06 February 2016

Construction of Box Culvert near Kei Tak Primary School has commenced

Riverbed construction near Choi Hung Road has commenced

02 February 2016

Riverbed construction near Choi Hung Road has commenced

Pipe Pile Installation near Tung Wui Estate has commenced

31 January 2016

Pipe Pile Installation near Tung Wui Estate has commenced

Pipe Pile Installation near Ng Wah Catholic Secondary School has completed

31 December 2015

Pipe Pile Installation near Ng Wah Catholic Secondary School has completed

Riverbed Construction near Ng Wah Catholic Secondary School has commenced

31 December 2015

Riverbed Construction near Ng Wah Catholic Secondary School has commenced

Construction of Box Culvert near Kai Tak Garden has completed

21 December 2015

Construction of Box Culvert near Kai Tak Garden has completed

Pipe Pile Installation near Lower Wong Tai Sin Estate/Kai Tak Garden has completed

14 December 2015

Pipe Pile Installation near Lower Wong Tai Sin Estate/Kai Tak Garden has completed

Nullah Wall Construction near Ng Wah Catholic Secondary School has completed

26 October 2015

Nullah Wall Construction near Ng Wah Catholic Secondary School has completed

Nullah Wall Construction near Choi Hung Road has completed

14 October 2015

Nullah Wall Construction near Choi Hung Road has completed

Nullah Wall Construction near Tung Tau Estate has completed

14 September 2015

Nullah Wall Construction near Tung Tau Estate has completed

Nullah Wall Construction near Nga Tsin Wai Village has completed

05 August 2015

Nullah Wall Construction near Nga Tsin Wai Village has completed

Pipe Pile Installation near Tung Tau II Estate (eastern side of the river) has completed

16 July 2015

Pipe Pile Installation near Tung Tau II Estate (eastern side of the river) has completed

Riverbed Construction near Tung Tau Estate has completed

30 June 2015

Riverbed Construction near Tung Tau Estate has completed

Riverbed Construction near Tung Tau Estate has commenced

30 May 2015

Riverbed Construction near Tung Tau Estate has commenced

Riverbed Construction near Nga Tsin Wai Village has completed

31 March 2015

Riverbed Construction near Nga Tsin Wai Village has completed

Pipe Pile Installation near Tung Tau II Estate (western side of the river) has completed

28 March 2015

Pipe Pile Installation near Tung Tau II Estate (western side of the river) has completed

Pipe Pile Installation near Tung Tau Estate has completed

26 February 2015

Pipe Pile Installation near Tung Tau Estate has completed

Pipe Pile Installation near Ng Wah Catholic Secondary School has commenced

26 February 2015

Pipe Pile Installation near Ng Wah Catholic Secondary School has commenced

Riverbed Construction near Nga Tsin Wai Village has commenced

09 February 2015

Riverbed Construction near Nga Tsin Wai Village has commenced

Pipe Pile Installation near Wong Chung Ming Secondary School has completed

31 December 2014

Pipe Pile Installation near Wong Chung Ming Secondary School has completed

Pipe Pile Installation near Tung Tau Estate has commenced

27 December 2014

Pipe Pile Installation near Tung Tau Estate has commenced

Nullah Wall Construction near Ng Wah Catholic Secondary School has commenced

10 December 2014

Nullah Wall Construction near Ng Wah Catholic Secondary School has commenced

Pipe Pile Installation near Wong Chung Ming Secondary School has commenced

30 October 2014

Pipe Pile Installation near Wong Chung Ming Secondary School has commenced

Pipe Pile Installation near Kowloon Walled City Community Hall (eastern side of the river) has completed

30 October 2014

Pipe Pile Installation near Kowloon Walled City Community Hall (eastern side of the river) has completed

Pipe Pile Installation near Tung Tau II Estate (eastern side of the river) has commenced

24 October 2014

Pipe Pile Installation near Tung Tau II Estate (eastern side of the river) has commenced

Pipe Pile Installation near Choi Hung Road has completed

30 September 2014

Pipe Pile Installation near Choi Hung Road has completed

Pipe Pile Installation near Nga Tsin Wai Village has completed

23 September 2014

Pipe Pile Installation near Nga Tsin Wai Village has completed

Nullah Wall Construction near Tung Tau Estate has commenced

21 August 2014

Nullah Wall Construction near Tung Tau Estate has commenced

Pipe Pile Installation near Kowloon Walled City Community Hall (western side of the river) has completed

07 August 2014

Pipe Pile Installation near Kowloon Walled City Community Hall (western side of the river) has completed

Nullah Wall Construction near Wong Chung Ming Secondary School has commenced

31 July 2014

Nullah Wall Construction near Wong Chung Ming Secondary School has commenced

Pipe Pile Installation near Choi Hung Road has commenced

31 July 2014

Pipe Pile Installation near Choi Hung Road has commenced

Pipe Pile Installation near Nga Tsin Wai Village has commenced

30 June 2014

Pipe Pile Installation near Nga Tsin Wai Village has commenced

Pipe Pile Installation near Kowloon Walled City Community Hall (eastern side of the river) has commenced

30 June 2014

Pipe Pile Installation near Kowloon Walled City Community Hall (eastern side of the river) has commenced

Foundation works for new Tung Tai Lane footbridge has commenced

27 June 2014

Foundation works for new Tung Tai Lane footbridge has commenced

Nullah Wall Construction near Choi Hung Road has commenced

29 April 2014

Nullah Wall Construction near Choi Hung Road has commenced

Shifting of Choi Hung Road near Tai Shing Street/Tseuk Luk Street/Tung Kwong Road Section has completed

29 April 2014

Shifting of Choi Hung Road near Tai Shing Street/Tseuk Luk Street/Tung Kwong Road Section has completed

Nullah Wall Construction near Nga Tsin Wai Village has commenced

12 April 2014

Nullah Wall Construction near Nga Tsin Wai Village has commenced

Commencement of Midstream Contract No. DC/2013/03

30 December 2013

Commencement of Midstream Contract No. DC/2013/03

Pipe Pile Installation near Kowloon Walled City Community Hall (western side of the river) has commenced

12 December 2013

Pipe Pile Installation near Kowloon Walled City Community Hall (western side of the river) has commenced

Pipe Pile Installation near Kei Tak Primary School has completed

04 September 2013

Pipe Pile Installation near Kei Tak Primary School has completed

Construction of Box Culvert near Lower Wong Tai Sin Estate has commenced

19 March 2013

Construction of Box Culvert near Lower Wong Tai Sin Estate has commenced

Pipe Pile Installation near Lower Wong Tai Sin Estate/ Kai Tak Garden has commenced

15 December 2012

Pipe Pile Installation near Lower Wong Tai Sin Estate/ Kai Tak Garden has commenced

Pipe Pile Installation near Kei Tak Primary School (western side of the river) has commenced

31 August 2012

Pipe Pile Installation near Kei Tak Primary School (western side of the river) has commenced

Pipe Pile Installation near Tung Tau (II) Estate (western side of the river) has commenced

13 June 2012

Pipe Pile Installation near Tung Tau (II) Estate (western side of the river) has commenced

Pipe Pile installation near Morse Park (Park No. 1) has commenced

23 March 2012

Pipe Pile installation near Morse Park (Park No. 1) has commenced

Shifting of Choi Hung Road Shatin Pass Road/Tai Shing Street Section has completed

01 February 2012

Shifting of Choi Hung Road Shatin Pass Road/Tai Shing Street Section has completed

Commencement of Upstream Contract No. DC/2011/04

31 October 2011

Commencement of Upstream Contract No. DC/2011/04