Harbour Area Treatment Scheme Stage 2A - Demolition of Chemically Enhanced Primary Treatment Tanks and Associated Facilities at Cyberport Sewage Treatment Works

Contract No. DC/2009/20
Harbour Area Treatment Scheme Stage 2A - Demolition of Chemically Enhanced Primary Treatment Tanks and Associated Facilities at Cyberport Sewage Treatment Works

Scope of Works

The works include demolition of chemically enhanced primary treatment works at Cyberport Sewage Treatment Works.

Contract Particulars

Contract Commencement : 31/08/2016
Completion Date : 15/12/2017
Contract Sum : $11.54 million
Government Department : Drainage Services Department
Consultant :Ove Arup & Partners Hong Kong Ltd.
Contractor : Build King (Zens) Engineering Limited

Progress Photos

Back to Top