DSD awarded Agreement No. CE 1/2023 (DS) “Yuen Long South Effluent Polishing Plant – Design and Construction”
27 June 2024
The Drainage Services Department signed a consultancy agreement of about $43.50 million with Arup – Binnies Joint Venture on 27 June 2024 for undertaking the design and construction for Yuen Long South Effluent Polishing Plant.
The consultancy agreement adopts New Engineering Contract 4 (NEC4) Professional Services Contract (PSC) Option C. The consultancy agreement will last for about 128 months.
The Assistant Director/Sewage Services, Mr Raymond LEE Wai-man (third left), Chief Engineer/Harbour Area Treatment Scheme, Mr Terence TSE Koon-hung (third right) of the DSD, the Director, Mr PEGG David Owen (second left), the Director, Mr Simon TSANG Man-leung (first left) of Ove Arup & Partner Hong Kong Limited and the Managing Director, Mr Andy KWOK-yim (second right), the Director, Mr. Stephanus SHOU Wan-lok (first right) of Binnies Hong Kong Limited attended the Agreement Signing Ceremony