DSD awarded Contract No. DC/2022/04 “Drainage Improvement in Southern Hong Kong Island – Package 2 (Remaining Works)”
23 August 2022
The Drainage Services Department signed a works contract of about 189.85 million with Best Build Construction Company Limited on 23 August 2022. The works include construction of approximate 2.4 km of stormwater drains of diameters ranging from 375mm to 1800mm in Tin Wan, Aberdeen, Ap Lei Chau, Wong Chuk Hang, Shouson Hill and Stanley of Southern Hong Kong Island and the Peak. This 41-month works contract commenced on 19 August 2022.
The Assistant Director / Projects and Development, Mr CHOI Wing-hing (second right), the Chief Engineer / Drainage Projects, Mr WONG Hip-lik, Thomas (first right) of the DSD, the Director, Mr WONG Chung-yin, Victor (second left) and Construction Manager, Mr CHAN Ka-shing (first left) of Best Build Construction Company Limited attended the Contract Signing Ceremony