DSD awarded Agreement No. CE 72/2021 (DS) "Enhancement Works for Preliminary Treatment Works at Harbour Side (Phase 1) – Investigation, Design and Construction"
25 April 2022
The Drainage Services Department signed a $18.92 million consultancy agreement on 25 April 2022 with AECOM Asia Company Limited for undertaking the investigation, design and construction on the enhancement works for the six Preliminary Treatment Works located at Kwai Chung, Tsing Yi, To Kwa Wan, Tseung Kwan O, Chai Wan and Shau Kei Wan.
NEC3 Option C of Professional Services Contract was adopted in this consultancy agreement. The consultancy agreement will last for about 117 months.
The Assistant Director/ Sewage Services, Mr Walter LEUNG Wing-yuen (top left), System Advisor/ System Management Division, Mr Henry CHAU Kwok-ming (bottom Left) of DSD, the Vice President (Water, Hong Kong), Mr Robert CHAN Ying-kin (top right) and Technical Director (Water, Hong Kong), Mr Tim LEE Shun-tim (bottom right) of AECOM Asia Company Limited attended the Agreement Signing Ceremony online