DSD awarded Agreement No. CE 50/2019 (DS) “Upgrading of Tai Po Sewage Treatment Works – Investigation”

31 March 2020

The Drainage Services Department (DSD) signed a HK$22.8 million consultancy agreement on 31 March 2020 with Black & Veatch Hong Kong Limited for undertaking the investigation for the upgrading of Tai Po Sewage Treatment Works (TPSTW). 

The consultancy agreement adopts New Engineering Contract 3 (NEC3) Processional Services Contract (PSC) Option C. The NEC3 PSC enables DSD and the consultant to timely complete the study on viable schemes for the proposed upgrading works within the preset time frame and advances the implementation of feasible, innovative and sustainable sewage treatment solutions. Its scope comprises review, site investigation, impact assessments and preliminary design for the upgrading of TPSTW. The consultancy agreement will last for about 36 months.