Contract No DC/2009/05
Harbour Area Treatment Scheme Stage 2A Construction of the Interconnection Tunnel and Diaphragm Wall for Main Pumping Station at Stonecutters Island Sewage Treatment Works
Date of Award
3 September 2009
Contractor
China State - Shanghai Tunnel Joint Venture
Date of Commencement
17 September 2009
Anticipated Date of Completion
30 June 2012
Contract Sum
HK$ 612,514,000.00
Project Office
Harbour Area Treatment Scheme