Contract No DE/2009/02

Harbour Area Treatment Scheme Stage 2A Provision of Covers and Deodourization Facilities to the Existing Sedimentation Tanks at Stonecutters Island Sewage Treatment Works

Date of Award
21 October 2009
Contractor
ATAL Engineering Ltd
Date of Commencement
30 October 2009
Anticipated Date of Completion
4 August 2012
Contract Sum
HK$ 188,800,000.00
Project Office
Harbour Area Treatment Scheme Division