Contract No DE/2024/10
Relocation of Sha Tin Sewage Treatment Works to Caverns – Electrical and Mechanical Works for Sewage Treatment Facilities and Associated Works
Date of Award
22 September 2025
Contractor
ATAL Engineering Limited
Date of Commencement
30 September 2025
Anticipated Date of Completion
30 August 2030
Contract Sum
HK$4,633,479,872.00
Project Office
Cavern Projects Division