Drainage Services Department

Contract No DC/2024/06

Shek Kip Mei Stormwater Storage Scheme and Drainage Improvement Works in Eastern District and Lei Yue Mun

Date of Award
2 August 2024
Contractor
CRBC – MAYLON Joint Venture (China Road and Bridge Corporation – Maylon Construction Company Limited Joint Venture)
Date of Commencement
15 August 2024
Anticipated Date of Completion
14 November 2028
Contract Sum
HK$1,185,786,000.00
Project Office
Drainage Projects Division
Back to Top