Drainage Services Department

Contract No DE/2022/04

Upgrading of Sludge Dewatering System and Associated Facilities for Imported Sludge at Sha Tin Sewage Treatment Works

Date of Award
15 August 2022
Contractor
Hsin Chong Aster Building Services Limited
Date of Commencement
24 August 2022
Anticipated Date of Completion
25 January 2024
Contract Sum
HK$19,250,600.00
Project Office
Electrical & Mechanical Projects Division