Contract No DE/2019/10

Upgrading of Electrical and Mechanical Facilities of Pumping Systems for Surplus Activated Sludge and Digested Sludge of Sha Tin Sewage Treatment Works

Date of Award
19 October 2020
Contractor
Chevalier (Envirotech) Limited
Date of Commencement
27 October 2020
Anticipated Date of Completion
11 March 2022
Contract Sum
HKD$8,563,000.00
Project Office
Electrical and Mechanical Projects Division