Contract No DE/2018/04

Shek Wu Hui Effluent Polishing Plant - Main Works Stage 1- E&M Works for Sewage Treatment Facilities

Date of Award
20 November 2019
Contractor
Bestwise Envirotech Limited
Date of Commencement
2 December 2019
Anticipated Date of Completion
14 May 2024
Contract Sum
HK$ 557,592,635.00
Project Office
Sewerage Projects Division