Contract No DE/2018/03

Shek Wu Hui Effluent Polishing Plant – Main Works Stage 1 – Sidestream Treatment Facilities and E&M Works for Sludge Treatment Facilities

Date of Award
11 October 2019
Contractor
The Jardine Engineering Corporation, Limited
Date of Commencement
23 October 2019
Anticipated Date of Completion
4 April 2024
Contract Sum
HK$ 933,202,283.60
Project Office
Sewerage Projects Division