Contract No DC/2018/08

Inter-reservoirs Transfer Scheme – Water Tunnel between Kowloon Byewash Reservoir and Lower Shing Mun Reservoir

Date of Award
14 February 2019
Contractor
Bouygues Travaux Publics
Date of Commencement
27 February 2019
Anticipated Date of Completion
26 April 2022
Contract Sum
HK$ 762,781,000.00