Contract No DC/2008/09

Harbour Area Treatment Scheme Stage 2A Construction of Sewage Conveyance System from Ap Lei Chau to Aberdeen

Date of Award
4 August 2009
Contractor
Paul Y. Construction Company, Limited
Date of Commencement
17 August 2009
Anticipated Date of Completion
16 August 2012
Contract Sum
HK$236,500,000.00
Project Office
Harbour Area Treatment Scheme Division