Drainage Services Department

PWP No. 4463DS

Hung Shui Kiu Effluent Polishing Plant – Phase 1

Project Scope

The scope of the project comprises –
(a)   construction of Hung Shui Kiu Effluent Polishing Plant ("HSKEPP"), including construction of all civil structures and installation of the initial phase of electrical and mechanical facilities to provide a sewage treatment capacity of 60 000 cubic metres per day at Hung Shui Kiu/Ha Tsuen New Development Area ("HSK/HT NDA");
(b)   implementation of ancillary works including construction of utilities bridge, connection of the HSKEPP to the existing effluent discharge tunnel and associated modification works, utilities diversion, road and drainage works, sewerage connection and landscape works, implementation of temporary traffic measures and renewable energy installations, etc.; and
(c)   implementation of environmental mitigation measures, and environmental monitoring and audit programme and construction supervision for the works mentioned in items (a) to (b) above

Major Improvements and Benefits

HSKEPP will be an essential sewerage infrastructure of HSK/HT NDA and nearby areas, to provide reliable sewage treatment services to the public.  HSKEPP is expected to be at secondary-plus treatment level

Consultants

CE 32/2022(DS) - AECOM Asia Company Limited

Contractor

DC/2024/11 - China State – Best Build Joint Venture (China State Construction Engineering (Hong Kong) Limited – Best Build Construction Company Limited Joint Venture)

DE/2024/09 - REC-CEL JV (REC Engineering Company Limited-Chevalier (Envirotech) Limited Joint Venture)

Contract No.
DC/2024/11, DE/2024/09
Project Commencement Date
25 June 2025
Project Completion Date
Mid 2031
Project estimate

About $6,695.0 million

Controlling Division
Harbour Area Treatment Scheme Division
Type
Sewerage and sewage treatment
District
Yuen Long
Status
On-going
Other Information