Village Sewerage in Northern Tuen Mun
The scope of the project comprises (a) the construction of one sewage pumping station at Fuk Hang Tsuen (Lower); (b) the construction of about 150 metres of twin rising mains in Fuk Hang Tsuen (Lower); (c) the construction of about 11 kilometres of gravity sewers in Fuk Hang Tsuen (Lower), Po Tong Ha, Siu Hang Tsuen and Tsz Tin Tsuen; and (d) ancillary works
To improve environmental hygiene of 4 unsewered village areas, namely Fuk Hang Tsuen (Lower), Po Tong Ha, Siu Hang Tsuen and Tsz Tin Tsuen and further reduce the amount of pollutants being discharged into the nearby stream courses and marine waters. The sewerage system will serve an ultimate population of about 6250 and convey the sewage to the existing Pillar Point Sewage Treatment Works for proper treatment and disposal.
AECOM Asia Company Limited
Sang Hing – Kuly Joint Venture
About $431.20 million