Village sewerage in Fanling Wai, So Kwun Po and Leng Pei Tsuen, Fanling
Project Scope
The scope of the project comprises the construction of about 6 kilometres of gravity sewers in three unsewered areas in Fanling, namely Fanling Wai, So Kwun Po and Leng Pei Tsuen
Major Improvements and Benefits
To improve environmental hygiene and further reduce the amount of pollutants being discharged into the nearby River Indus and Deep Bay
Consultants
CE 61/2013 (DS) - AtkinsRealis Asia Limited
Contractor
Welcome Construction Company Limited
Contract No.
DC/2020/01
Project Commencement Date
13 January 2021
Project Completion Date
31 August 2025
Project estimate
About $179.7 million
Controlling Division
Harbour Area Treatment Scheme Division
Type
Sewerage and sewage treatment
District
North
Status
Completed