Project Scope

The scope of the project comprises the construction of about 6 kilometres of gravity sewers in three unsewered areas in Fanling, namely Fanling Wai, So Kwun Po and Leng Pei Tsuen

Major Improvements and Benefits

To improve environmental hygiene and further reduce the amount of pollutants being discharged into the nearby River Indus and Deep Bay

Consultants

CE 61/2013 (DS) - AtkinsRealis Asia Limited

Contractor

Welcome Construction Company Limited

Contract No.
DC/2020/01
Project Commencement Date
13 January 2021
Project Completion Date
31 August 2025
Project estimate

About $179.7 million

Controlling Division
Harbour Area Treatment Scheme Division
Type
Sewerage and sewage treatment
District
North
Status
Completed