PWP No. 4414DS
Rehabilitation of underground sewers – remaining works
Project Scope
Rehabilitation of about 5 kilometres of underground gravity sewers and associated manholes in various districts in Hong Kong
Major Improvements and Benefits
The rehabilitation works will adequately improve the reliability of the concerned parts of the sewerage network
Consultants
Binnies Hong Kong Limited
Contractor
Darwin Engineering Limited
Contract No.
DC/2023/10
Project Commencement Date
6 September 2023
Project Completion Date
End 2027
Project estimate
About $306.4 million
Controlling Division
Planning and Rehabilitation Division
Type
Sewerage and sewage treatment
District
Central & Western; Eastern; Southern; Wan Chai; Islands; Kwun Tong; North; Sai Kung; Sha Tin; Tai Po; Tuen Mun; Yuen Long
Status
On-going
Other Information