Project Scope

The project scope comprises -
(i) rehabilitation of a 400 m long sewer along Lung Cheung Road near Ngau Chi Wan;
(ii) rehabilitation of a 1 km long sewer from Kwei Chow Street to To Kwa Wan preliminary treatment works;
(iii) rehabilitation of a 50 m long sewer along Yuen Wo Road near Sha Tin sewage pumping station;
(iv) rehabilitation of a 200 m long submarine sewer across Sai Kung Hoi linking Sai Kung Town and Tui Min Hoi;
(v) associated sewerage works and ancillary works.

Major Improvements and Benefits

The rehabilitation works will adequately improve the reliability of the concerned parts of the sewerage network

Consultants

Atkins China Limited

Contractor

China Geo-Engineering Corporation

Contract No.
DC/2017/02
Project Commencement Date
31 January 2018
Project Completion Date
31 March 2022
Project estimate

about $678.5 million

Controlling Division
Project Management Division
Type
Sewerage and sewage treatment
District
Kwun Tong; Kowloon City; Wong Tai Sin; Sai Kung; Sha Tin
Status
Completed