PWP No. 4388DS

Shek Wu Hui effluent polishing plant

Project Scope

Reconstruction of the existing Shek Wu Hui Sewage Treatment Works to increase the treatment capacity by 65 000 cubic metres (m3) per day to 170 000 m3 per day#, and to upgrade the sewage treatment level to tertiary standard for conversion into a “Shek Wu Hui Effluent Polishing Plant”

Note: #
the total treatment capacity will be 190 000 m3 per day with 20 000 m3 per day is funded under PWP No. 7747CL.

Major Improvements and Benefits

To upgrade the effluent standards and the treatment capacity of the Shek Wu Hui Sewage Treatment Works

Consultants

AECOM (Asia) Company Limited

Contractor

DC/2018/06 - Kwan Lee – Chun Wo Joint Venture
DC/2018/07 - Kwan Lee – Chun Wo Joint Venture
DE/2018/03 - The Jardine Engineering Corporation, Limited
DE/2018/04 - Bestwise Envirotech Limited

Contract No.
DC/2018/06, DC/2018/07, DE/2018/03 and DE/2018/04 (Stage 1)
Project Commencement Date
September 2019
Project Completion Date
2034
Project estimate

about $11,972.8 million^

Note: ^
the total project estimate is about 13,198.2 million with 1,225.4 million is funded under PWP No. 7747CL.

Controlling Division
Sewerage Projects Division
Type
Sewerage and sewage treatment
District
North
Status
On-going
Back to Top