Project Scope
The scope of the project comprises the construction of about 11 kilometres of sewers and one sewage pumping station in 3 unsewered villages in Tai Po (namely Kau Lung Hang San Wai, Kau Lung Hang Lo Wai and Tai Hang).
Major Improvements and Benefits
The project aims at providing public sewerage to Kau Lung Hang San Wai, Kau Lung Hang Lo Wai and Tai Hang so as to improve the water quality in nearby watercourses as well as the sanitary conditions of these unsewered villages
Consultants
AECOM Asia Company Limited
Contractor
DC/2012/04 – Hsin Chong Tsun Yip Joint Venture
Contract No.
DC/2012/04
Project Commencement Date
26 June 2012
Project Completion Date
31 May 2017
Project estimate
About $317 million
Controlling Division
Consultants Management Division
Type
Sewerage and sewage treatment
District
Tai Po
Status
Completed