PWP No. 4380DS
Construction of dry weather flow interceptor at Cherry Street box culvert
Project Scope
The project aims at providing a dry weather flow interceptor at Cherry Street box culvert and its associated pumping facilities
Major Improvements and Benefits
To improve the water quality of the New Yau Ma Tei Typhoon Shelter
Consultants
Binnies Hong Kong Limited
Contractor
China Metallurgical Group Corporation - Top Express Construction Engineering Limited Joint Venture
Contract No.
DC/2017/01
Project Commencement Date
19 December 2017
Project Completion Date
29 October 2022
Project estimate
About $664.6 million
Controlling Division
Harbour Area Treatment Scheme Division
Type
Sewerage and sewage treatment
District
Yau Tsim Mong
Status
Completed
Other Information