PWP No. 4364DS

Lam Tsuen Valley sewerage –trunk sewers, pumping station and rising mains

Project Scope

Construction of a new sewage pumping station near Lam Kam Road Interchange, about 0.7 km of rising mains at Tai Po Road-Tai Wo, about 3.7 km of gravity sewers at Lam Kam Road and nearby access roads and ancillary works.

Major Improvements and Benefits
To improve the water quality in Lam Tsuen Valley and the Sanitary condition of these unsewered villages/area.
Consultants
Ove Arup & Partners Hong Kong Limited
Contractor
DC/2008/07 - Dix Construction & Transportation Limited
Contract No.
DC/2008/07
Project Commencement Date
17 February 2009
Project Completion Date
18 October 2012
Project estimate
About $160 million
Controlling Division
Project Management Division
Type
Sewerage and sewage treatment
District
Tai Po
Status
Completed