PWP No. 4359DS

North District sewerage stage 1 phase 2B

Project Scope

North District sewerage stage 1 phase 2B involves the provision of sewerage to 12 unsewered villages/areas in Fanling, New Territories. The scope of the project comprises the construction of :
(a) about 11 km of sewers, ranging from 150 mm to 400 mm in diameter for 12 unsewered areas in North District;
(b) three sewage pumping stations, respectively in San Wai, Tung Kok Wai and Wing Ning Tsuen; and
(c) about 1.4 km of rising mains, ranging from 100 mm to 250 mm in diameter, in association with the construction of the three sewage pumping stations in (b) above.

Major Improvements and Benefits
The project aims at providing public sewerage to 12 unsewered villages/areas in the North District so as to improve the water quality in Deep Bay and the sanitary conditions of these unsewered villages/areas.
Consultants
AECOM Asia Co. Ltd.
Contractor
DC/2006/17 - Sum Kee Construction Limited
Contract No.
DC/2006/17, , , ,
Project Commencement Date
28 March 2007
Project Completion Date
Mid 2011
Project estimate
About $185 million
Controlling Division
Consultants Management Division
Type
Sewerage and sewage treatment
District
North
Status
Completed