PWP No. 4204DS

Wan Chai East and North Point Sewerage, Remaining Works

Major Improvements and Benefits
The project will improve the capacity of the existing sewerage system in Wan Chai East and North Point to cater for future development needs. Part of the project will also rectify expedient connections to mitigate the existing pollution problems arising from these sources.
Consultants
Black & Veatch Hong Kong Ltd.
Contractor
DC/2002/02 - Penta-Ocean Construction Co. Ltd.
Contract No.
DC/2002/02
Project Commencement Date
28 October 2005
Project Completion Date
March 2011
Project estimate
About $220 million
Controlling Division
Consultants Management Division
Type
Sewerage and sewage treatment
District
Eastern; Wan Chai
Status
Completed
Back to Top