Drainage Services Department

PWP No. 4200CD

Drainage improvement works in Sha Tin and Sai Kung – phase 1

Project Scope

The scope of the project comprises –
(a)   construction of an underground stormwater storage tank with a capacity of about 8 600 cubic metres, a stormwater pumping station and the associated above ground structure at Sha Tin Park;
(b)   re-provision and enhancement of part of Sha Tin Park;
(c)   construction of stormwater drains of about 1.6 kilometres (km) long with diameters ranging from 375 millimetres to 2.2 metres (m) at Pak Hok Ting Street, Sha Tin Centre Street, Yi Ching Lane and Tai Po Road – Sha Tin in Sha Tin, and Po Lo Che Road in Sai Kung;
(d)   improvement of existing drainage channels of about 90 m long by increasing the height by 1 m at Wong Chuk Yeung Village in Sha Tin; 
(e)   construction of flood walls of about 1.8 km long and about 1 m tall along Shing Mun River and at Kau To Hang in Sha Tin; and
(f)   carrying out ancillary works

Major Improvements and Benefits

To upgrade the capacity of the drainage system concerned and alleviate the flood risks in Sha Tin and in the vicinity of Po Lo Che in Sai Kung

Consultants

CE 44/2021(DS) - AECOM Asia Company Limited

Contractor

Lanon – Sinohydro – Excel JV (Lanon Development Limited – Sinohydro Corporation Limited – Excel Engineering Company Limited Joint Venture)

Contract No.
DC/2024/07
Project Commencement Date
15 August 2024
Project Completion Date
Mid 2029
Project estimate

About $706.8 million

Controlling Division
Drainage Projects Division
Type
Flood Prevention
District
Sai Kung; Sha Tin
Status
On-going
Other Information
Back to Top