Drainage Services Department

PWP No. 4186CD

Rehabilitation of underground stormwater drains stage 2

Project Scope

Condition survey and rehabilitation of some underground stormwater drains and the associated manholes in Tsuen Wan, Kwai Tsing, Sham Shui Po, Yau Tsim Mong, Kowloon City and Wong Tai Sin districts

Major Improvements and Benefits

The condition survey and rehabilitation works will adequately improve the reliability of the concerned parts of the drainage network

Consultants

Binnies Hong Kong Limited

Contractor

Welcome Construction Company Limited

Contract No.
DC/2019/04
Project Commencement Date
22 September 2020
Project Completion Date
Early 2025
Project estimate

About $515 million

Controlling Division
Planning and Rehabilitation Division
Type
Flood Prevention
District
Kowloon City; Sham Shui Po; Wong Tai Sin; Yau Tsim Mong; Kwai Tsing; Tsuen Wan
Status
On-going