PWP No. 4186CD
Rehabilitation of underground stormwater drains stage 2
Project Scope
Condition survey and rehabilitation of some underground stormwater drains and the associated manholes in Tsuen Wan, Kwai Tsing, Sham Shui Po, Yau Tsim Mong, Kowloon City and Wong Tai Sin districts
Major Improvements and Benefits
The condition survey and rehabilitation works will adequately improve the reliability of the concerned parts of the drainage network
Consultants
Binnies Hong Kong Limited
Contractor
Welcome Construction Company Limited
Contract No.
DC/2019/04
Project Commencement Date
22 September 2020
Project Completion Date
Early 2025
Project estimate
About $515 million
Controlling Division
Planning and Rehabilitation Division
Type
Flood Prevention
District
Kowloon City; Sham Shui Po; Wong Tai Sin; Yau Tsim Mong; Kwai Tsing; Tsuen Wan
Status
On-going