Drainage Services Department

PWP No. 4181CD

Drainage improvement works in Eastern District – remaining works

Project Scope

The scope of the project comprises –
(a)   construction of a set of drainage tunnel of about 3.6 kilometres long and with diameter of about 5 metres from Shau Kei Wan and Chai Wan to Pak Sha Wan;
(b)   construction of seven intakes, six connection adits and an outfall; and
(c)   carrying out ancillary works

Major Improvements and Benefits

The overall capacity of the drainage system in the district is expected to be enhanced and the flood risks will be alleviated

Consultants

CE 73/2022(DS) - Binnies Hong Kong Limited

Contractor

CRBC – Bouygues TP – VSL (HKEDT) JV

Contract No.
DC/2026/04
Project Commencement Date
5 August 2026
Project Completion Date
Mid 2031
Project estimate

About $2,718.2 million

Controlling Division
Project Management Division
Type
Flood Prevention
District
Eastern
Status
On-going