PWP No. 4180CD

Rehabilitation of underground stormwater drains stage 1

Project Scope

Condition surveys of about 35 kilometres (km) of stormwater drains and the associated manholes distributed throughout the territory; rehabilitation of about 11 km of stormwater drains and the associated manholes distributed throughout the territory; and ancillary works.

Major Improvements and Benefits

The condition survey and rehabilitation works will adequately improve the reliability of the concerned parts of the drainage network.

Consultants

Black & Veatch Hong Kong Limited.

Contractor

Kwan On Construction Company Limited.

Contract No.
DC/2018/10
Project Commencement Date
14 January 2019
Project Completion Date
mid 2022
Project estimate

about $122.8 million

Controlling Division
Project Management Division
Type
Flood Prevention
District
Central & Western; Eastern; Southern; Wan Chai; Islands; Kwun Tong; Kowloon City; Sham Shui Po; Wong Tai Sin; Yau Tsim Mong; Kwai Tsing; North; Sai Kung; Sha Tin; Tai Po; Tsuen Wan; Tuen Mun; Yuen Long; West Kowloon
Status
On-going