Project Scope
The scope of project comprises the construction of –

(a)  Stormwater pumping scheme at Hoi Bun Road Park including an underground storage tank, a pump house, electrical & mechanical (E&M) works and associatedstormwater drain;
(b)    Stormwater pumping scheme at Kwun Tong Ferry Pier Square including an underground storage tank, a pump house, E&M works and associated stormwater drain;
(c)    Stormwater storage scheme at Sau Nga Road Playground including an underground storage tank, E&M works and associated stormwater drain; and
(d)    Ancillary works including reinstatement of the parks, playground, recreation ground and associated facilities.
Major Improvements and Benefits
The project will relieve the flood risk in the Kwun Tong area.
Consultants
AECOM Asia Company Limited (for investigation study)
Controlling Division
Drainage Projects Division
Type
Flood Prevention
District
Kwun Tong
Status
Under planning & design