Drainage Services Department

PWP No. 4172CD

Rehabilitation of underground stormwater drains – remaining works

Project Scope

Rehabilitation of about 19 km underground stormwater drains

Major Improvements and Benefits

The rehabilitation works will adequately improve the reliability of the concerned parts of the drainage network

Consultants

CE 47/2016(DS) - Binnies Hong Kong Limited

Contractor

Welcome Construction Company Limited

Contract No.
DC/2020/09
Project Commencement Date
28 June 2021
Project Completion Date
2 December 2025
Project estimate

About $702.7 million

Controlling Division
Planning and Rehabilitation Division
Type
Flood Prevention
District
Central & Western; Eastern; Southern; Wan Chai; Islands; Kwun Tong; North; Sai Kung; Sha Tin; Tai Po; Tuen Mun; Yuen Long
Status
Completed
Other Information