PWP No. 4152CD

Drainage improvement works in Upper Lam Tsuen River, She Shan River, Upper Tai Po River, Ping Long and Kwu Hang

Project Scope

The Scope of project comprises improvement of about 4.5km of Upper Lam Tsuen River, She Shan River and Upper Tai Po River, and construction of about 45m of box culverts at Ping Long and Kwu Hang

Major Improvements and Benefits
The project aims at alleviating the risks of flooding and to cope with future development as identified in the Sha Tin and Tai Po Drainage Master Plan Study
Consultants
AECOM Asia Company Ltd (formerly known as Maunsell Consultants Asia Limited)
Contractor
DC/2007/06 - Chiu Hing Construction & Transportation Co. Ltd.
Contract No.
DC/2007/06
Project Commencement Date
28 September 2007
Project Completion Date
31 December 2012
Project estimate
$568.2 million
Controlling Division
Drainage Projects Division
Type
Flood Prevention
District
Tai Po
Status
Completed