Project Scope
The scope of project comprises construction of about 5.1km of drainage channels in Ping Kong, Kau Lung Hang, Yuen Leng, Nam Wa Po and Tai Hang areas
Major Improvements and Benefits
The implementation of the project would alleviate flooding hazards in Ping Kong, Kau Lung Hang, Yuen Leng, Nam Wa Po and Tai Hang areas and also bring the drainage system up to the current flood protection standard and meet the long-term development needs
Contractor
DC/2006/09 - Chiu Hing Construction & Transportation Co. Ltd.
Contract No.
DC/2006/09
Project Commencement Date
29 December 2006
Project Completion Date
October 2012
Project estimate
$358.4 million
Controlling Division
Drainage Projects Division
Type
Flood Prevention
District
North; Tai Po
Status
Completed