Project Scope
The project aims at alleviating the flooding problems in East Kowloon including Hung Hom, Kowloon City and San Po Kong areas.
The project scope including construction of approximately 4.3km long stromwater drains and 1.3km long box culverts started in May 2006 for completion in Jan 2010.
Major Improvements and Benefits
The existing drains of insufficient capacity will be replaced with larger drain pipes and box culverts, so that the system will be greatly improved. The severe and persistent flooding problems at the flooding prone areas shall be resolved by the successful implementation of this project.
Consultants
Black & Veatch Hong Kong Limited.
Contractor
DC/2005/12 - China Harbour - Peako Joint Venture
Contract No.
DC/2005/12
Project Commencement Date
30 May 2006
Project Completion Date
10 February 2010
Project estimate
About $240 million
Controlling Division
Project Management Division
Type
Flood Prevention
District
Kowloon City; Wong Tai Sin
Status
Completed