Drainage Services Department

PWP No. 4118CD

Drainage improvement in Northern New Territories – package B (remaining Works)

Project Scope

The scope of project comprises construction of about 0.8km of stormwater drain in Tsung Yuen, New Territories.

Major Improvements and Benefits

The implementation of the project would alleviate flooding hazards in Tsung Yuen and also bring the drainage system up to the current flood protection standard.

Consultants

Mott MacDonald HK Ltd.

Contractor

Ming Hing Waterworks Engineering Company Limited

Contract No.
DC/2019/06
Project Commencement Date
13 August 2020
Project Completion Date
1 December 2022
Project estimate

About $65.5 million

Controlling Division
Drainage Projects Division
Type
Flood Prevention
District
North
Status
Completed