PWP No. 4102CD

Drainage Improvement in Tuen Mun and Sham Tseng – Package B

Project Scope
Construction of :
1,100 m of drainage channel at So Kwun Wat; and 750 m of drainage pipeline, drainage channel and box culvert at Nai Wai
Major Improvements and Benefits
To alleviate the flooding risk at So Kwun Wat and Nai Wai
Consultants
Not Applicable
Contractor
DC/2006/04 - Hong Kong Construction (Hong Kong) Limited
Contract No.
DC/2006/04
Project Commencement Date
25 July 2007
Project Completion Date
May 2012
Project estimate
$84.8 million
Controlling Division
Drainage Projects Division
Type
Flood Prevention
District
Tuen Mun
Status
Completed