Date of Award :
24/07/2017
Consultancy Agreement
/ Contract No :
CE 49/2016 (DS)
Consultancy Agreement
/ Contract Title :
Review of Drainage Master Plan in Tuen Mun, Tsuen Wan and Kwai Tsing – Feasibility Study
Consultant / Contractor :
Black & Veatch Hong Kong Limited
Date of Commencement :
01/08/2017
Anticipated Date of Completion :
31/07/2020
Awarded Consultancy Fee /
Contract Sum :
HK$8.0M
Type of Agreement / Contract :
Feasibility Study
Project Office :
Land Drainage Division
Back
Date of Award :
27/07/2017
Consultancy Agreement
/ Contract No :
DE/2017/01
Consultancy Agreement
/ Contract Title :
Upgrading of Kwun Tong Preliminary Treatment Works
Consultant / Contractor :
Chevalier-CPC Joint Venture
Date of Commencement :
31/07/2017
Anticipated Date of Completion :
29/07/2021
Awarded Consultancy Fee /
Contract Sum :
HK$206,645,600.00
Type of Agreement / Contract :
NEC ECC Option C
Project Office :
Electrical and Mechanical Projects Division