Our Projects > Contracts/Consultancies Awarded
Date of Award :
24/10/2016
Consultancy Agreement
/ Contract No :
DC/2015/05
Consultancy Agreement
/ Contract Title :
Minor Drainage Improvement Works in Northern Hong Kong Island and North District
Consultant / Contractor :
Kuly Construction & Engineering Company Limited
Date of Commencement :
28/10/2016
Anticipated Date of Completion :
27/04/2020
Awarded Consultancy Fee /
Contract Sum :
HK$ 78,888,888.00
Type of Agreement / Contract :
NEC3 ECC Option A
Project Office :
Drainage Projects Division
Back
Date of Award :
26/10/2016
Consultancy Agreement
/ Contract No :
DE/2016/03
Consultancy Agreement
/ Contract Title :
Provision of Electrical and Mechanical Equipment for Detritor Nos. 1 and 2 of To Kwa Wan Preliminary Treatment Works
Consultant / Contractor :
The Jardine Engineering Corporation Limited
Date of Commencement :
28/10/2016
Anticipated Date of Completion :
11/03/2018
Awarded Consultancy Fee /
Contract Sum :
HK$10,680,000.00
Type of Agreement / Contract :
NEC3 Opt A
Project Office :
Electrical and Mechanical Projects Division
Back