Consultancy Agreement
/ Contract No
CE 28/2015 (DS)
Consultancy Agreement
/ Contract Title
Study on Revitalisation of Water Bodies - Feasibility Study
Date of Award11/12/2015
Consultant / ContractorAECOM Asia Company Limited
Date of Commencement11/12/2015
Anticipated Date of Completion10/12/2017
Awarded Consultancy Fee /
Contract Sum
HK$10,880,000.00
Type of Agreement / ContractFeasibility Study
Project Office Land Drainage Division
Back
Consultancy Agreement
/ Contract No
CE 29/2015 (DS)
Consultancy Agreement
/ Contract Title
Climate Change Impact Study on Sewerage Facilities in Hong Kong – Feasibility Study
Date of Award28/12/2015
Consultant / ContractorBlack & Veatch Hong Kong Limited
Date of Commencement28/12/2015
Anticipated Date of Completion27/12/2017
Awarded Consultancy Fee /
Contract Sum
HK$6,300,000.00
Type of Agreement / ContractFeasibility Study
Project Office Land Drainage Division
Back
Consultancy Agreement
/ Contract No
DE/2014/01
Consultancy Agreement
/ Contract Title
Provision of Electrical and Mechanical Facilities for Shek Wu Hui Sewage Treatment Works – Further Expansion Phase 1A – Advance Works and Ng Chow South Road
Date of Award28/12/2015
Consultant / ContractorThe Jardine Engineering Corporation Limited
Date of Commencement30/12/2015
Anticipated Date of Completion23/10/2018
Awarded Consultancy Fee /
Contract Sum
HK$183,800,000.00
Type of Agreement / ContractNEC3 ECC Option C contract
Project Office Electrical and Mechanical Projects Division
Back
Consultancy Agreement
/ Contract No
DE/2015/01
Consultancy Agreement
/ Contract Title
Provision of Operation and Maintenance Services for Various Sewage Treatment and Stormwater Facilities
Date of Award14/12/2015
Consultant / ContractorATAL Engineering Limited
Date of Commencement01/02/2016
Anticipated Date of Completion31/01/2019
Awarded Consultancy Fee /
Contract Sum
HK$186,220,000.00
Type of Agreement / ContractService Contract
Project Office Sewage Treatment 2 Division
Back
Consultancy Agreement
/ Contract No
DE/2015/02
Consultancy Agreement
/ Contract Title
Term Contract for Inspection, Overhaul and Testing of E&M Installations at Various Sewage Treatment Works and Pumping Stations
Date of Award30/12/2015
Consultant / ContractorHUD General Engineering Services Limited
Date of Commencement01/02/2016
Anticipated Date of Completion31/01/2019
Awarded Consultancy Fee /
Contract Sum
HK$488,966,510.00
Type of Agreement / ContractNEC TSC Option A Contract
Project Office Sewage Treatment 2 Division
Back
Consultancy Agreement
/ Contract No
DE/2015/03
Consultancy Agreement
/ Contract Title
Upgrading of high voltage switchgears and motor starters in Cheung Sha Wan sewage pumping station
Date of Award23/12/2015
Consultant / ContractorTorishima (Hong Kong) Limited
Date of Commencement29/12/2015
Anticipated Date of Completion11/05/2017
Awarded Consultancy Fee /
Contract Sum
HK$17,690,000.00
Type of Agreement / ContractNEC3 ECC Option A contract
Project Office Electrical and Mechanical Projects Division
Back